Last year, the Aberdeen to Inverness Improvement Project
(A2I) redoubled 8.5km of track between Aberdeen and Dyce as reported in issue
168 (October 2018). However, this redoubled track could not carry any passenger
trains until this year’s completion of the 25.5km Aberdeen to Inverurie
redoubling work in August on which we report this month.
The completion of this redoubling marks the end of phase one
of the A2I programme which, as reported in issue 158 (December 2017) included
earlier work to provide a relocated station at Forres, on a new straight 1.25km
loop, and work at Elgin, which included platform extensions, the provision of a
turnback facility and extension of the loop from 650 metres to 1.5km.
This work was completed in October 2017. It also included
signalling and telecommunications improvements which saw the section of the
line from Inverness to Keith controlled from a new Highland workstation at the
Inverness signalling centre.
Prior to that, telecommunications enhancements provided a
new multi-protocol label switching (MPLS) transmission network to support
operational and station systems along the route. This required further network
upgrade works both between Aberdeen and Dundee and between Inverness and Perth
to ensure diverse routing. Other telecommunications work included the provision
of an internet protocol telephone concentrator at Inverness, for the
user-worked crossing phones previously controlled by the closed signal boxes,
and the alteration of GSM-R call routing due to the transfer of control to
Inverness.
The investment of £330 million on A2I phase one follows the 2009 Scottish Government Strategic Transport Projects Review, which concluded that A2I was one of Scotland’s top four transport priorities. Over the past ten years, there has been an 87 per cent increase in patronage between Inverness and Aberdeen with most of this increase between Aberdeen and Dyce (146 per cent) and Inverurie (247 per cent).
Journey time over the 173-kilometre-long Aberdeen and
Inverness route is around 2 ¼ hours with an irregular, about two-hourly service
frequency. At each end of the route there is also a roughly hourly local
service between Inverness and Elgin and between Aberdeen to Inverurie.
Whilst the Scottish Government’s long-term objective for the
Aberdeen to Inverness line is the provision of an hourly service with a
two-hour journey time, A2I also delivers the more immediate requirement of
improving local services at either end of the line and the provision of
additional stations at Dalcross and Kintore without affecting journey times.
For this reason, the provision of the proposed new station at Dalcross will
require the provision of a new two-kilometre loop.
Both these stations are subject to separate funding
agreements. For Kintore, this was agreed between Transport Scotland,
Aberdeenshire Council and North East Regional Transport Partnership (Nestrans)
and the £14.5 million contract for the station’s construction was awarded to
BAM Nuttall in May. This enabled much of its construction to be done during the
2019 blockade.
Although planning permission has been agreed for Dalcross station, arrangements for its funding have yet to be finalised.
The 2018 blockade
The track laid last summer between Kittybrewster and Dyce
was the first stage of the redoubling of the line between Aberdeen and
Inverurie. The new double track starts at Kittybrewster, 1.5km from Aberdeen
station, as redoubling the Hutcheson Street and Schoolhill tunnels would have
required track lowering at significant cost and was not necessary for a
15-minute service.
This involved much more than just putting the track back as,
since it was lifted in 1968, numerous assets have been placed on the track bed,
the single line now followed the double trackbed racing line and some
underbridges only had a single-track deck. Moreover, the original earthworks
cannot accommodate a double track in accordance with current standards and this
largely built-up section required significant neighbour engagement as a result
of tracks being laid closer to adjacent houses.
Earthworks retention was therefore a large part of the work.
This was achieved by interlocking concrete blocks, high friction fill material
or king-post retaining walls. These use H piles driven to pre-determined depths
into the ground with timbers inserted between the webs of the H section.
For these reasons, redoubling this 26km corridor required
significant reconstruction of the railway corridor, for which a blockade was
the only option. As it was considered unacceptable to close the railway for the
six months that this would take, it was decided that it would be done in two
summer blockades, each of about three months, with the loop at Dyce enabling
the redoubling to be staged into two parts.
On completion, the newly laid track was left unused, which
presented an unusual signal-sighting problem as the new Up line could not be
used by trains until the end of the 2019 blockade. Until then, what was to
become the Down line remained as the single bi-directional Up/Down line. This
meant that, until the 2019 commissioning, some signals for Up direction trains
were relocated as temporary signals to the right of the single line as the new
Up line prevented them being located on the left. These temporary signals were
replaced by new permanent signals on the left of the new Up line during the
2019 blockade.
With the newly laid track left unused, the operational railway was essentially unchanged by the 2018 blockade and therefore did not require significant signalling work. This also meant that it was only necessary to bus passengers between Aberdeen and Dyce, as Dyce station could stay open during the blockade.
The 2019 blockade
Contractual arrangements for this year’s blockade were the same as for other A2I phase one works in that Network Rail engaged Siemens for the signalling and telecommunications work and BAM Nuttall for everything else. BAM Nuttall’s main sub-contractors were AECOM and Jacobs for design, Babcock for track work and Stobart Rail for ancillary civil engineering work.
This year’s blockade was from 4 May to 19 August and
differed significantly from last year’s work. It laid nearly 15km of new track,
almost twice that of last year’s blockade, though the complication of the
racing line was not such a significant issue this time. Furthermore, instead of
being in an urban area it was largely through farmland and so had various level
crossings to contend with.
The programme required a large amount of bridge works,
including two underbridge replacements, seven underbridge bridge extensions,
one infill, strengthening six underbridges and the removal of two overbridges.
This year’s blockade also required significant work to strengthen the five-span
viaduct over the River Don, just south of Inverurie.
Advantage was also taken of the blockade’s extension to
Huntly, as described below, to extend the short platforms at Insch to 160
metres to accommodate ScotRail’s Inter7City sets. These are the newly
refurbished five-coach High Speed Trains which now serve Scotland’s seven
cities.
The 2019 work also involved work on the existing railway at
both ends of the new double track section which meant changes to the
replacement buses during the blockade. For the first six weeks, the bus
replacement services were between Dyce and Inverurie, then buses ran for
another eight weeks between Dyce and Huntly, where temporary welfare facilities
had to be provided for train crews. The final nine days of the blockade saw
buses between Aberdeen and Inverness for three days and then six days of buses
between Aberdeen and Huntly.
Rail Engineer visited the redoubling works on 17 July during
week 11 of the 15-week blockade and had an opportunity to tour the site with
its programme manager, Colin MacDonald, at BAM Nuttall’s project office and
compound at Inverurie. This site office also includes ‘Hotel BAM’, which
provides temporary accommodation for around thirty and has a fully equipped
gym. With a shortage of hotels in the immediate vicinity, this is a
cost-effective way of accommodating the workforce.
Building this temporary accommodation is one solution to the problem of the project being a three-hour journey from Scotland’s central belt, where many of its project personnel are based. For example, as well as overseeing the work on site, the Network Rail project team must liaise with engineers, designers, operational planners and others based in Glasgow.
Touring the work
The tour started at the newly laid S&C by the Inverurie
project office. This is the western limit of the new double-track section,
where a new turnback facility has been provided capable of accommodating
ScotRail’s Inter7city sets. Two synchronised S&C tampers were seen working
together to simultaneously tamp the ballast under the crossing bearers.
At the Don viaduct works, Colin explained that this presented
significant challenges in view of the requirement to avoid putting significant
additional weight on the substructure, as this would have required costly
in-river work and could have delayed the project. For this reason, the
ballasted track option, which would have added 2,000 tonnes to the weight of
the bridge, was rejected. Rails over the viaduct have therefore been laid on
longitudinal timbers in new timber cradle units.
Works to strengthen the viaduct were viewed from a temporary crash deck below the bridge superstructure. These included the replacement of all cross girders – replaced by deeper ones – and additional plating on the side beams. The abutments had also been strengthened to resist the worst-case scenario of the force of a braking ballast train. Further protection against such forces is provided by shock absorbers that have been installed at the pillars and abutments.
Next stop on the tour was a bridge overlooking the station
work at Kintore. When built, this will be an unmanned station with a 166-space
car park. The station is immediately adjacent to the A96 dual carriageway, so
it is expected to be a busy park and ride station. Colin explained that,
although this was a separate contract to the main blockade works, its
construction was an integral part of the project as a whole. With limited
access to the north side of the line, it was important to make best use of the
blockade to construct the north-side platforms.
Nearby, Boat of Kintyre level crossing was being upgraded
from a single line AHB (automatic half barrier) to a MCBOD (manually controlled
barriers obstacle detection) double-tracked crossing. The signaller’s workload
was a significant factor in the choice of the MCBOD crossing as this does not
require the close study of CCTV images to determine when it is safe to lower
the barriers.
This level-crossing work required a road closure for the
duration of the blockade, with only pedestrian access across the railway. It
also needed extra land by the crossing for its equipment housing, which had to
be built on most of the garden of the adjacent house that the owner had agreed
to sell.
The A2I redoubling works also required the upgrade of three
user-worked crossings and the closure of two more – as a result of arrangements
negotiated with those affected, this included the purchase of a house that
could only be accessed by the crossing.
Another deal had to be made to allow the demolition of the
paper mill bridge near Inverurie, the central pillar of which would have
obstructed the double tracking. Colin noted that, although it is normally
possible to reach suitable agreements with those affected, such issues present
significant risks to major projects, such as A2I, that have no compulsory
powers. There may not be an alternative design solution if someone doesn’t wish
to sell their land under any circumstances, a situation which could cause major
problems.
The last call on the guided tour was to see the retention work at Kinaldie, where king-post retaining walls could be seen supporting the embankment to the east for a kilometre or so, a clear indication of the work required to replace a track lifted fifty years ago.
Programming the blockade
To allow track laying to commence at the start of the
blockade, almost all the civil works required for track laying were completed
beforehand. This included retention work that could safely be done whilst the
single line was open. Night-time ‘rules of the route’ possessions were used for
work that affected the track support zone or had plant and equipment that could
not be safely separated from trains.
Other than the Don viaduct, the only bridgework done during
the blockade was the re-decking of underbridge 67 over the old canal,
immediately south of the viaduct.
Disruptive possessions from 20 to 22 April (72 hours) and
27/28 April (54 hours) saw work done on six underbridges, including deck
renewals and extensions, retention earthworks, track formation work and
ancillary civils works. The latter was sequenced to give priority to the
subsequent work (equipment bases and the troughing between them) so that cables
could be run out.
In this way, most of the lineside signalling infrastructure
was completed prior in advance, which was key to allowing track installation to
commence from the outset of the blockade.
Track laying used a seven-sleeper spreader beam to lift
sleepers from wagons and place them into position with the correct spacing.
Continuously welded rail, which had previously been laid alongside the existing
single line, was then thimbled into position by road-rail vehicles and clipped
up by a fastclipping machine.
The programme required the completion of all work requiring engineering trains and road-rail vehicles by 13 August to support the final phase of signalling commissioning and associated wheels free testing. The new double-track railway was commissioned in the early hours of 17 August to allow three days of familiarisation runs for the route’s 176 drivers, with the passenger service resuming on 20 August.
Signalling black hole
Prior to the blockade, signalling between Aberdeen and
Inverness was controlled by Aberdeen signalling centre, mechanical signal boxes
at Dyce, Inverurie, Insch, Huntly and Keith, and the Inverness signalling
centre’s Highland workstation, which was commissioned as part of the October
2017 A2I works.
The 2019 blockade saw the closure of Dyce and Inverurie
signal boxes with control of the line from Kittybrewster to Insch transferred
to the Highland workstation. The long-term aspiration is that this workstation
will eventually control the route throughout. However, for now trains between
Keith and Insch disappear from the Highland workstation panel only to reappear
about an hour later.
This recontrol required the modification of interlockings,
changes to train describers and the provision of fringe controls at Insch, for
Inverness’s Highland workstation, and at Kittybrewster for the NX panel at
Aberdeen signalling centre. Control of the blockade’s level crossings, as well
as the sidings at Kittybrewster and Raiths Farm, were also transferred to the
Highland workstation.
The new signalling equipment includes 51 signals, many of which are single lens LED colour lights, and nine new switch and crossing units. It is controlled by Siemens Westrace interlockings and train detection is by a combination of 92 newly installed Frauscher axle counters and some DC track circuits between Aberdeen and Dyce.
Job done
Completion of the blockade marked the end of the Aberdeen to
Inverness phase one works. 25 kilometres of track had been laid on 39,000
sleepers using 110,000 tonnes of ballast, of which 20,000 tonnes was recycled
ballast. Laying this track required the removal of 20,000 tonnes of spoil and
the provision of 5,000 tonnes of engineering material, along with 27 kilometres
of embankment retention. The signalling work also required over 137 kilometres
of cables.
Impressive though these statistics are, what counts for
passengers is the extra train services, made possible by this project, that
ScotRail will introduce during the December timetable change. A total of 20
additional services a day between Aberdeen and Inverurie will provide a minimum
of a half-hourly service – every 20-minutes at the peak. ScotRail will also
introduce a new Montrose to Aberdeen service that, in most hours, will be
extended to provide a Montrose to Inverurie service.
At the other end of the line, an additional six
Elgin-Inverness services will add to the nine such services introduced in
December 2018, giving Elgin an hourly all-day service. Those who wish to travel
longer distances from stations on the route will also benefit in December from
the provision of six through services from Inverness to the central belt of
Scotland via Aberdeen.
It has taken four years to deliver A2I phase one – one of
the UK’s longest redoubling projects – as well as a series of enhancements to
provide more-efficient loop operation. On a single-track railway, this is
perhaps likely to offer greater time savings than line speed enhancements.
As Inverness to Aberdeen is the only UK inter-city rail service operated largely over a single track, it’s good to see serious money spent on such targeted enhancements. It will be interesting to see how phase two can bring further improvements.
A proposal to install a public access route across Bennerley Viaduct in the East Midlands is currently being considered by planning authorities.
The structure – owned by Railway Paths Ltd – is one of the country’s only two surviving wrought iron trestle viaducts. The other, at Meldon in Devon, also hosts a cycle path.
A campaign group – the Friends of Bennerley Viaduct – has been carrying out works beneath the Grade II* listed structure, establishing different wildlife habitats within each of the main spans. As part of the proposal, these would be linked together by a footpath.
Most of the £700,000 project cost has already been raised and it’s hoped contractors will be on site in the autumn.
Plantworx & Railworx a success despite the summer weather
Every two years, the Construction Equipment Association organises a big plant show – Plantworx. And it is big – the likes of Caterpillar, JCB, Doosan, Volvo and Komatsu spend weeks building their stands, to show their equipment in the best possible light and, above all, to show it working.
For 2019, two things were new. One was the location – the
show moved to the East of England Arena at Peterborough for the first time.
Secondly, due to the amount of rail construction that has
been going on recently, and with more to come in the shape of HS2 and Crossrail
2, to name just a couple of projects, the decision was taken to add a Railworx
section to the show. Here, rail suppliers would be able to show off both plant
and equipment.
So, Rail Media was tasked with arranging for the key players
in rail to come along and join in the show. Some 50 exhibitors, from all areas
of the industry, accepted the challenge and came to Peterborough.
First among equals
Chief among them was Network Rail itself. The Signalling Innovation Group took a stand to show off some of its latest ideas, and Hitachi Information Control Systems Europe took the stand next door.
In contrast, Genwork chose Railworx to launch its brand new Klik-Lok range of purpose-designed environmental noise barrier solutions, specifically aimed at infrastructure projects involving road and rail where noise reduction is of critical importance.
A series of panels lock together in a vertical frame, with the frame giving good vertical stability and the locking action reducing the assembly time and removing the need for heavy plant.
On its stand, Genwork was displaying a pair of
three-metre-high barriers, which business development director Roger Kemp
explained was the minimum height for effective sound reduction. Made in the UK,
the panels, which were a fetching shade of green at Railworx, can be
manufactured in any colour to suit a contractor’s needs.
With an estimated life of 40 years, the Klik-Lok noise
barrier system can be used for both permanent and temporary installations. The
show organisers were so impressed that they presented Genwork with a New
Product Launch award on the middle day of the show.
Soggy Tuesday
The award was presented on the middle day because, however much one plans for an outdoor show, there is one thing that can’t be predicted – the British weather. On the first day, Tuesday 11 June, the heavens opened. Literally. It rained ALL day.
To avoid the weather, the depleted crowd of visitors stayed in the indoor section of the show, which they had to walk through anyway as it was straight after the visitor entrance.
This was where staging the show at a permanent facility really paid off, tarmac walkways and hard standing parking saved the day. From there it was a short walk to the show entrance, a quick scan of the pre-printed badge, and then into the show.
Through the door into the main hall, and there was plenty to
see.
Peli Products had a stand that required no lighting – they had brought enough of their own! LED lights, protective cases (the well-known ‘Peli Cases’) and even covers for iPads – all were attracting interest. One of the appeals of Plantworx is its cross-industry spread of visitors, and Peli confirmed they had been visited by a number of utility contractors, and at a very high level. They were certainly pleased with the level of interest.
Oilaway occupied a double-size stand and also seemed to be doing business with visitors from a range of sectors. Protective clothing specialists Portwest Clothing and Safeaid were glad they were indoors so their racks of clothing weren’t soaking up the rain like a sponge, and Role Recruitment was talking to anyone who walked past about – recruitment.
Platform Edge Protection had started off outdoors. When part of their stand blew away, one of three that did, organisers found them a space indoors.
At a corner of the hall, Rail Media colleagues Railway People were also talking to visitors and sheltering exhibitors alike. The charity Mind and JW’s CV-writing service were in the same area.
When contractors are on site, safety is naturally a priority. Minor injuries outnumber major accidents, so on-site treatment of wounds, abrasions and sprains is important. Aero Healthcare supplies everything from first-aid kits to AEDs (automated external defibrillators), even the lightweight stretchers used for medical evacuations, and used Railworx to showcase its first-aid solutions for the rail industry.
Into the rain
Outdoors, it really was soggy. Those exhibitors who had trailers or cabins were sheltering visitors, like Dual Inventive, whose trailer displayed their workforce safety and railway sensing technology.
James Fisher Prolec had a Quattro road-rail excavator siting on a length of track outside the (crowded) hospitality cabin. The reason it was there was to show off PMX. Combining two well-established technologies – excavator hazard mitigation and geolocation – PMX helps prevent plant equipment from striking pre-defined hazards and increases machine efficiency by up to 30 per cent when compared with existing systems, so the manufacturer claims.
Suited for a wide range of high-risk sectors, including civil construction, highways and rail, PMX is the first system of its kind to receive accreditation from Network Rail for Any Line Open (ALO) projects.
Also on show, and combining rated capacity limiter (RCL) and movement limiting devices (MLD) technology into a robust, safety-critical solution, was James Fisher Prolec’s TrackPilot™ – a next-generation hazard mitigation solution for ALO on-track operations that has been specifically designed for excavator rail-road vehicles (RRVs) and, apparently, can achieve ten times faster processing and functionality speeds than any other solution on the market.
Fenix Signalling was making a noble effort, demonstrating its latest Pintsch Tiefenbach points machine, on a working set of points, under an umbrella. Well done, Sir! After all, points have to work in all weathers, don’t they?
Ilecsys, manufacturer of GRP location cases and walkways – and anything else you care to order – had a trailer, and Peter Dickson and the team kept snug in that.
Geismar weren’t so lucky, except their open-fronted tent was right opposite the Rail Media trailer, where hot coffee and pork pie was available. Network Rail track director Steve Featherstone visited as well, so Richard Cradock was a happy man despite it all. He also commented that Railworx was the place to be going forward, so hopefully he’ll be back for the next one.
Gramm Barrier Systems was demonstrating how to apply its SilentRail coating, which it claims reduces rail noise and helps prenvent buckling.
Taylor Construction Plant (TCP) powers its lighting towers by hydrogen using fuel cells. So its all green, with zero emissions.
It was also the best-lit stand on an otherwise gloomy day!
Better Wednesday
Sheltering in cabins was not so necessary on day two, as the pouring rain gave way to a light drizzle. Some, however, chose to sit indoors for part of the day and attend the Get Set conference, which looked at skills and skill shortages. Joe Guy, group HR director for integrated talent solutions at Network Rail; Trudy Layden-Freeman, lead HR business partner for rail at Costain; Clair Mowbray, chief executive of the National College for High Speed Rail; Mohanad Ismail, senior systems consultant, Young Rail Professionals and Neil Franklin, head of skills intelligence at the National Skills Academy for Rail (NSAR), spoke on this important topic.
Outside, things were looking up.
Network Rail was open for business while Bollé, manufacturer of safety glasses, had opened its doors and looked inviting. The company had run a competition before Railworx, giving 20 pairs of Tryon Tryoflash safety glasses to registered visitors to the show.
Well done, Bollé!
Colin Burnikell’s team at Hilti emerged into the (weak) sunlight and demonstrated their powerful tools and specialist drilling equipment, the distinctive red equipment being put through its paces.
Gioconda were managing to keep their electronics dry and were in good spirits.
Santon Switchgear, which both supplies new circuit breakers and also upgrades old ones to give them a new lease of life, and Duvine/DMS Technologies, which “has a long experience working with Network Rail engineers designing and manufacturing rugged battery systems for trackside installations, operating in all weathers”, displayed their wares.
The team from Marshalls CPM displayed their Redi-Rock modular walling system, which is ideal for protecting the rail line against erosion, landslips and rock falls.
Mixamate’s giant concrete mix-and-pump trucks and Van Elle’s piling rigs were immune to the troublesome weather, though their operators were not, and Van Elle was another company to report real commercial results from the Railworx show.
Exhibitors around the event reported solid interest, Kinshofer received lots of interest in their tiltrotator, ballast tamper and sleeper changer attachments, whilst Nijhuis Engineering, from the Netherlands, reported overwhelming interest in their BE-AR rail system.
Thomson Engineering Design also had some big kit, a TXM road-rail excavator fitted with a manipulator which waved a large pole – it looked like an OLE structure or a signal post – around the sky throughout the show.
And there’s more
Tools and equipment hire specialist A-Plant was in amongst the construction exhibitors. So too was Wacker Neuson, whose compactors are used extensively in track renewals to flatten and compact the trackbed before track is laid.
Force One, which specialises in the vacuum excavation of aggregates and earth – and ballast around track and S&C – has developed a three unit ‘train’ to work on track. The front unit is a road-rail excavator fitted with the suction head and hose. It’s coupled to a storage trailer, that can hold up to 15 tonnes of spoil, and that in turn is connected to the vacuum fan unit which provides the suck. It’s still under development, with a conveyor unloader system planned for the spoil truck, but should be working out on the rail network next year.
GreenMech, which Rail Engineer visited years ago, was also at Plantworx. The latest Sure-Trak self-propelled chipper now can cope with uneven ground as well as steep slopes. An interesting demonstration had the machine climbing over unequal ramps – a good simulation of conditions out on a railway cutting face or embankment. Apparently, Network Rail has recently placed an order.
Mecalac, a sponsor of the show, won the award for best live demonstration. The way its compact equipment moved around the muddy compound was fascinating to watch, and must have taken lots of planning.
Further features
Throughout the three days of the show, one large indoor area
was converted into the Drone Zone. Here, around a dozen suppliers had small
stands, showing off unmanned aerial vehicles (drones) and what can be done with
them for surveying and photography, while the bulk of the area, behind a safety
net, was used for flying demonstrations.
In a flat, enclosed space, even one as large as 2,300 square metres, it was difficult to show what drones can do in terms of surveying the underside of viaduct arches and pinpointing track layouts, but the skill of the pilots was certainly on show as they landed their buzzing devices on predetermined targets.
COMIT (Construction Opportunities for Mobile IT), the
organisation that aims to improve understanding between the construction and
technology industries and speed up the adoption of mobile IT within the
construction sector, had helped stage the Drone Zone.
Tony Shooter, COMIT’s chair for drone technology, commented: “What better way to showcase today’s drone technology in the construction sector, than at Plantworx, where there is a strong focus on innovation and leading technologies. This event is probably one of the most important developments in advancing drones in the construction sector.”
Joanna Oliver, CEA’s director of global programmes, agreed:
“Drones are already changing the way the construction industry operates and is
growing at a rapid rate. Plantworx is delighted to showcase this advanced drone
technology to our visitors.”
Plantforce sponsored the Simulation Zone, located at one end of the indoor exhibition. Here, six state-of the-art simulators replicated a ‘real working construction site’ – but in a virtual world. Each of the simulators was linked and represented an individual construction machine – an excavator, wheel loader, tower crane, dozer or an articulated dump truck – as examples. Visitors to the zone were invited to work together on the simulators in the virtual world to complete tasks on a construction site. Spectators were also offered oculus rift headsets, allowing them to join the virtual world as bystanders and offer encouragement and support to the participants!
In another Plantworx initiative, students from schools in
the Peterborough area came to the show on the third day. They looked around the
exhibits and also took part in specially organised activities, aimed at
encouraging them to see construction and engineering as good career options for
the future.
Particularly popular amongst the students was Diggerland.
The theme park, part of HE Services, “world leaders in digger hire”, which was
exhibiting at the show, brought some of its equipment for young people to try.
There were mini-versions of excavators that the students could use to dig
holes, others with converted arms that could play ten-pin bowling or ‘hook a
duck’, and even small dumpers to drive around an oval track. Great fun, and at
least one Rail Engineer staff member was spotted hooking ducks!
So, was Plantworx/Railworx wet?
It certainly was.
But was it a washout? No way! With almost 500 exhibitors’
displays spread out over 140,000 square metres of the East of England Arena,
there was something for everyone, and too much to see in a day.
One Railworx exhibitor, for example, commented that,
although the rain had held some visitors back, he had six really worthwhile meetings
over the three days, which he said made it all worthwhile.
And there will be even more to look at and discuss in 2021!
Hopefully the weather will be better but, in any case, it will be an event not
to be missed.
The Institution of Mechanical Engineers recently held the
latest in a series of roughly biennial seminars highlighting railway
electrification, with the emphasis being mainly on the United Kingdom although
it did also look at other countries.
The current state of electrification design and construction
in the country is in rather a contrast to the optimism of the first seminars.
At that time, electrification was very much in active progression, although,
following mobilisation, there had been some hesitations along the way. These
hesitations were followed by a pause and then the current English and Welsh
limited stop. However; as will be seen, Transport Scotland has taken a
different path, with electrification delivery proceeding apace, to the extent
that there are now five electrified routes between the two principal Scottish
cities of Glasgow and Edinburgh.
With the institution sharing concerns with the industry, and
in partnership with the Railway Industry Association, the latest seminar was
organised in the light of the need to demonstrate the ability of the industry
to achieve commercially acceptable progress and show that electrification will
form the core preference for the decarbonisation of rail transport, as guided by
national government targets.
There has recently been considerable study of possible
alternatives to conventional electrification and the Institution’s conference
and seminars organising committee felt strongly that there should be an
analysis and discussion of some of these alternatives, as well as of the issues
that have driven electrification costs upwards and caused timescales to be
extended.
Scottish success
A broad cross-section of industry and associated
professionals were invited to present and help to achieve a method of
demonstrating to the country that electrification was the solution to traction
power for most of the core railway system.
Ian Flynn, as chairman of the organising panel, opened the
seminar on behalf of the IMechE and the RIA, stating that the industry was
ready to prove it could deliver electrification projects at an optimum rate and
economic cost.
Setting the scene on a positive note, the keynote address
was by Bill Reeve, commercial director of Transport Scotland, with his subject
“Success in Scotland – A rolling Programme of Electrification”. Delegates were
treated to a brief history of recent construction in Scotland with the emphasis
all the way through on keeping a rolling programme with a continuity of
workload.
The central belt of the country has a significant
concentration of the country’s population and has a well-used rail network.
Some parts of the network had been closed during the ‘Beeching’ period, and a
strategically positive view had already been taken to reopen those sections of
the system. There had been challenges all the way but lessons had been learned
and as the programme ‘rolled out’, these lessons learned were taken on board to
add success to the next phase of installation.
The Scottish programme showed how positive application of electrification could succeed and provided a beacon for the rest of Britain – that very positive story then set the pattern for the day.
Learning for the future
Next, the assembled audience heard from Phil Doughty, professional head of contact systems at Network Rail. Phil had presented at previous seminars and, on the basis of the current situation, decided this time to concentrate on a headline of “Doing it better next time – reflecting on recent experience”. A very pragmatic view of where the industry was given – costs had been too high – we could do better but didn’t and there was an awareness that there were “No more second chances!”
This presentation looked, in particular, at international comparisons, particularly within Europe and the costs and progress made. There was a contrasting attitude to traction on the mainland of Europe, with a more consistent workload and a correspondingly lower cost per single track kilometre, in striking comparison with the UK.
Work flow, however, was not the only issue, and Network Rail
had been studying closely the questions of standards, staff qualifications,
technical files and lessons learned within the UK again. Phil pointed out that
the currently de-scoped Midland main line electrification delivered, in fact, a
good news story with positive progress in areas which had caused excessive
costs for the Great Western programme, such as piling designs and positions and
structure spacing for example. This was already showing significant savings and
could be a potential route to the desired level of electrification cost per
single track kilometre appropriate to system delivery.
Silver bullet
With the seminar having looked at the technical issues, Stephen Kent, research fellow at the University of Birmingham, followed on with his element titled “Electrification, the Silver Bullet”. This looked at how much power and energy trains needed and the different sources of power available related to their respective carbon emissions. He also looked at the practicality of different power options for different train types.
The subject of decarbonisation centred well within Stephen’s
talk and he clarified some of the practical challenges around the provision of
traction energy – in the case of hydrogen, this was notably storage capacity
and refuelling methodology.
Studies have shown that overhead wires are the most
efficient way of powering a train – the technology is proven and has lower
operating costs than diesel. His robust, and it seemed inescapable, conclusion was
that there was no other solution for high-speed, high-performance or freight
lines than electrification. However, he did comment that bi-mode trains could
use new wires as soon as they were up!
David Clark, technical director of conference sponsor the Railway
Industry Association, gave a forthright delivery on the subject of “Making
Electrification Economically Viable.” He reflected on the 2007 electrification
strategy and how the industry had reacted to its output. From the arising
national electrification programme, what did we learn? And how much should
electrification cost?
The history was one of significant optimism through emerging
high costs to a ‘pause’ by government, followed by the stopping of much of the
proposed works. David reviewed how the industry had reacted and moved towards
the Electrification Cost Challenge report; all in the light of the government’s
own challenge to remove all diesel-only trains by 2040, but not including
electrification as the solution.
The purpose of the report was to assist industry and
government decision-making on rail electrification; restore government
confidence in the rail industry and deliver electrification schemes at an
affordable cost – on time and to budget. The approach would be to highlight
evidence that electrification can be, and is being, delivered for 33-50 per
cent of the Great Western scheme costs, using examples from around the United
Kingdom and internationally.
We need to identify good practice and effect a significant
change across the industry in the way projects are delivered, from initial
business case to energisation. The delivery proposals would call for a minimum
ten-year rolling programme of electrification to enable the industry to deliver
schemes at significantly lower cost, retain learning skills and incentivise
investment.
The industry must heed a health warning that this is not a blame game, accept that the whole industry is culpable in the cost escalation seen in some recent projects, and remember that many projects have been successfully delivered. David ran through the story of how electrification ran and came to where we are. Now, those lessons learned need to be acted upon so the industry can go forward with a revived railway traction philosophy.
Delivering the projects
Next came a report from the ‘front line’. Brian Sweeney is a
senior project engineer within the Scottish delivery team and he gave a most
valuable account of the construction of the various schemes north of the
border. He showed how expertise was gained as installation progressed and
methods were refined, culminating in the very effective delivery of the latest
stage from Stirling to Dunblane.
He was confident that the abilities so developed could be
applied further afield and looked for new work packages to attack.
The seminar then moved to the views of a delivery
contractor. Within the session entitled “Confidence in Electrification
Delivery”, we were given a very positive presentation from Steve Cox, Alstom’s
engineering and technical director, accompanied by his colleague Livia
Serafini, operations director for systems and infrastructure. The session
illustrated how the industry was willing and able to innovate and draw
experience from successful projects within and outside the UK.
Alstom has a very important development and innovation plant
in Italy, contributing to the company’s continuous product development, and has
multiple capabilities. It produces a modular OLE system (overhead line
equipment, called OCS on the continent – overhead contact system), which can be
used for maintenance replacement in situations where heritage UK-designed
equipment is to be replaced, and it also has a maintenance and
high-productivity construction process.
Steve and Livia summed up their presentation by emphasising the need to maintain competence right across Europe and develop the maintenance capability. There was a real drive to refine the method of delivery so that, when electrification returns to favour, innovative solutions can be delivered. The threat is that expertise is lost with any hesitation, and Alstom are keen to retain resources in the UK, possibly as part of a multi-skilling process.
Bi-modes, bridges and hybrids
Much has been made of the possibilities of bi-mode trains
and a presentation from Mark Hopwood, director of Great Western Railway,
continued that discussion.
He has been with the company since 2008 and has watched and
lived the electrification and its various scope and form changes. He was able
to illustrate the current situation with the audience and give a personally
experienced view of the current solution of mixed electrified and
non-electrified routes, together with the challenges mounted by timescales not
emerging as originally predicted and integration with Crossrail works onto the
Western infrastructure.
Mark left a powerful message that, in his view, a series of
overly risk-averse standards had been imposed on the Great Western programme
based on experiences from the past – twenty years had passed since the last
major high-speed-route electrification.
Although electrification brings benefits, it also brings a
level of disruption in the delivery and he did voice a view that large-scale
improvement work might be better served by the application of a transport and
works act process.
Richard Stainton delivered a general electrical engineering
view from the Network Rail angle. Having had wide and varied experience of
electrification power systems, including the conversion of the West Coast route
to auto transformer mode, he was able to demonstrate how standards could be
safely developed in line with modern risk-based practices to allow what may be
very large savings in electrification costs, particularly the ability to take
an optimum view of clearance needs. He highlighted, as an example, the significant
saving in costs through the intersection bridge at Cardiff, which a
well-thought process of risk management and developed design had enabled.
The final paper was delivered by Helen Simpson and Stephen Gossling from Porterbrook and Ricardo. As there will always be a need to deal with stretches of railway that may not necessarily deliver a robust case to justify full electrification, the construction of hybrid trains was discussed and shown to be a very viable option in those circumstances. In particular was the ability to re-engineer and re-equip older electric-only rolling stock, showing what could be achieved with class 319 EMUs displaced from the South.
Back to basics
The main presentations over, the conference gave way to a
‘Brains Trust’ session, where speakers were invited to give short modules on
electrification-related subjects. Several useful outputs were delivered with
plenty of food for thought!
Finally, the seminar was closed by the keynote speaker Mary
Hewitt, strategy and policy director of Arriva. Mary took the audience back to
basics, to remind them what railways are for and the role played by
electrification and other power systems. Mary delivered a most enlivening item
in what had been a very educational day for all concerned.
Overall the audience was convinced that electrification was
the only real traction solution for high-speed, high-density and freight rail
and that, while other traction options were relevant, they could not provide
the core performance the modern railway needs. The government’s targets for the
reduction of pollution and CO2 are on the horizon, and yet rail performance
needs to be maintained and to be able to deliver its best.
The industry wants to deliver electrification and is determined to show politicians and the nation that electrification can provide the desired traction solution at an appropriate cost and at an optimum pace. The seminar noted that the most effective results came where there had been a rolling programme of delivery, without the significant peaks and troughs of the past.
Thanks to colleagues in the Institution of Mechanical
Engineers and the Railway Industry Association for their work in organising
this conference and getting the message across that railway electrification can
succeed – the will and capability is certainly there.
Barnard’s Lock is a rail underbridge structure spanning the river Kennet, located 3.7km west of the centre of Newbury, West Berkshire. The underbridge carries the Berks and Hants iine (BHL) between Hungerford and Newbury, a section of the Reading to Taunton line, which is a major branch of the Great Western main line.
Barnard’s Lock underbridge is located in a saturated, wooded area with the nearest road access about 2km away. The area is a Site of Special Scientific Interest, often referred to as a “triple SI”. The location would attract the attention of the Environment Agency if any form of engineering work were to be proposed due to special concerns for the local population of otters, water voles and other forms of wild life in the area.
The bridge comprises three wrought-iron half-through girders
with intermediate wrought-iron cross girders supporting a timber decking. It
has two spans, is 40 metres in length and is skewed at an angle of 57 degrees
to the channel of the river Kennet, so the brick bridge abutments are aligned
with the direction of the river flow. The clearance between the bridge deck and
the river is very small, so the bridge has the capacity to become a barrier to
the river flow after heavy rainfall.
Significant deterioration
Well over fifteen years ago, structural inspections and assessment of the underbridge, carried out by JBA Consulting, identified significant deterioration of the timber deck and section loss of the main and cross girders throughout the structure. As a consequence, the structure was considered to be life expired and required renewal.
However, subsequent load monitoring of the structure has
enabled Network Rail to maintain the bridge to ensure trains are able to run at
line speed, which is 110 mph, in line with its ‘Putting Passengers First’
policy, but they knew that this could not last. The timber deck continued to
deteriorate, ballast was being lost and, with the advent of electrification,
and new rolling stock with different breaking and accelerating characteristics,
the forces on the superstructure were becoming unacceptable. It was decided
that the bridge needed to be replaced.
Tony Gee and Partners was invited by Network Rail to develop options for replacing the bridge. An emerging initial plan was to construct a new culvert structure within the railway embankment to the west of the underbridge. A new river channel would then have to be excavated, offering a permanent diversion of the river away from the current underbridge, under the new culvert.
The new river channel would be approximately 135 metres in length and would take water from the existing channel, at a point approximately 50 metres upstream of the current underbridge, and convey it northwards through the new culvert and then eastwards before connecting back into the existing river channel immediately downstream of the underbridge. This would then enable the underbridge to be demolished, and the railway embankment filled in.
Environmental concerns
It was a good plan, but close scrutiny by the Environment Agency
raised serious concerns about changing the flow of the river as it could lead
to a change in the flood plain which could affect local communities and also
local wildlife habitats. There were too many unknowns, and the estimated cost
of the work also exceeded budget allocation, so, eventually, the proposal was
dropped.
Therefore, it was agreed that the old bridge would have to
be replaced insitu. However, the location with its restricted access points,
woodland copses and sodden spongy ground, the length of bridge spans involved,
as well as the radius for lifts required, adjacent to the bridge, meant that
engineers had to get their thinking caps on. Network Rail’s project engineer
Matthew Roberts and programme manager Scott Pillinger told Rail Engineer what
happened next.
A new plan and design emerged and the principal contractor appointed for the £4 million contract. They had sixteen weeks to get the site ready, as the essential work to replace the bridge was planned to start at 00:10 on Saturday 4 May and finish at 05:10 on Tuesday 7 May 2019. It was decided that the bridge had to be assembled on site in four sections. Tony Gee and Partners designed eight Z-type steel main girders plus cross girders, and the decking would be a reinforced concrete design.
The steelwork was fabricated in Wigan by Time DMG. This included manufacturing 1.5-metre-deep Z type girders and associated cross girders that would be transported to site and spliced together to form the four deck structures that were up to 34 metres in length. But how would they get the steelwork to site and how would they create enough space and solid ground to construct the four decks? As Matthew pointed out the “problems kept snowballing”.
160 elephants
Once the four elements of the superstructure were
constructed on site, they would need to be lifted into position. It was
calculated that the biggest lift would exceed 105 tonnes and the radius would
be more than 60 metres. This was not work for a normal crane and they
eventually sourced a Sarens Gottwald 1,200 tonne crane, apparently capable of
lifting 160 elephants!
How would they get this crane to site and how would they
ensure that it did not sink into the spongy, sodden ground adjacent to the
river? Well, firstly they had to create a 2km haul road using more than 10,000
tonnes of fill material. They were able to source much of this material from
three other Network Rail sites and Scott explained that the intention is for
the material used to be passed on to a school project in the vicinity. Recycling
at its best!
Once the crane was on site and the four superstructures
constructed and ready to be lifted in place, how would they ensure that the
crane would be stable when the lift commenced? To do that, they had to
construct four sheet-piled cofferdams, ten metres deep and six metres square in
section, and fill them with engineering fill. These cofferdams would be placed
so that the load from the outriggers would be transferred to stable ground.
Whilst the cofferdams were being constructed, a substantial amount of woodland needed to be cleared to create the workspace for the bridge superstructure construction and for the site offices and accommodation, and the sixteen weeks were ticking away.
Traction forces
At the design stage, Tony Gee and Partners became concerned about the ability of the breaking and traction forces of the trains to transfer through to the deck to the supporting abutments. Their solution was to include fifty-six 100mm diameter, four-metre-long dowels into the design. These dowels would need to be placed into holes in the precast sill beams and then drilled into the brick abutment during the possession, after the old decks had been removed.
Matthew had calculated that it would take two hours using a
diamond drill for each dowel. In a 76-hour possession, this was a significant
undertaking and the golden rule was that there must not be an overrun –
‘Putting Passengers First’.
The team prepared contingency plans which would involve
additional temporary speed restrictions, dependent on the number of dowels in
position. They carried out trials and adjusted the resources with the intention
of completing all the drilling within the possession.
The contractors would also need to have access to both sides
of the river when the old superstructure was removed, so a floating pontoon,
made up of interlocking plastic units, was positioned across the river. This
created a walkway, working platform and support for temporary troughing for the
signalling cables and other equipment.
Wind and water
A ‘Go/No-Go’ plan was drafted before the possession started. Weather forecasts were analysed for potential heavy rain. There were sluice gates that could regulate the water flow, but that could also cause problems, as outlined earlier. Wind was a fairly critical factor. The crane would only attempt the lifts required if the wind was less than 35mph. If this was exceeded, work would have to stop.
Fortunately, the weather was kind with no rain and little
wind throughout the possession. The line was handed back to traffic on time
with a 50mph speed restriction.
The track was reinstated by local track engineers,
underpinning another Network Rail policy known as the ‘Orange Pound’. In the
past, contractors have been responsible for reinstating the track after such
work. Now, the view within Network Rail is that this work should be done
in-house, using engineers who know the area and can maintain it on a daily
basis, ensuring that not only the track is maintained properly but also the
speed restriction boards, track magnets and temporary track crossings are also
looked after.
Many readers would identify this approach with a similar one
adopted some time ago.
So, the new bridge is in place, the myriad of engineering
challenges addressed and the local environment left in peace with the water
voles now admiring the new structure that has emerged from this sodden, watery
part of the Berks & Hants main line.
The Shepperton branch line in the south west of London and
north Surrey, which is part of the Feltham signal box area, connects to the
Kingston loop by a triangular junction between Strawberry Hill and Teddington
stations. The line opened on 1 November 1864 and was briefly named the Thames
Valley Railway, with access only from the Twickenham direction. The line was
electrified using 630VDC third rail on 30 January 1916.
Demand and population in the area rapidly increased after
the railway’s relatively late introduction to the network, and today Hampton
station is the line’s busiest, with more than 1.2 million journeys, up from 0.7
million only ten years ago.
Feltham signal box is a large route relay-interlocking
system dating from 1974 and it was high-time that it was replaced –
resignalling had already been deferred and the asset condition was such that
further deferment was not an option. The Shepperton branch was selected as the
first stage of the renewal of Feltham signal box, with full renewal taking
place in six stages over several years, such is the complexity of the Feltham
signalling area.
The task of resignalling was to be delivered using ‘future signalling systems by Atkins’- a strategic programme to change the way signalling projects are delivered in the UK. The system involves 11 separate product acceptance approvals and uses a wide range of products and components to deliver a full train control, signalling and power system – from interlockings to level crossings, barrier arms, power supplies and cables.
Over the weekend of the 22/23 June, Atkins recommissioned
the Shepperton branch – the first use of its first ElectroLogIXS electronic
interlocking and level crossing controller system on the main line railway.
ElectroLogIXS is a proven programmable logic controller
licensed to Atkins, exclusively for UK rail use. It is the first all-new type
of interlocking to be introduced onto the railway for some time, so the
commissioning was a significant milestone in the introduction of modern state
of the art signalling interlocking systems to the UK, together with new
innovative ways of providing signalling infrastructure which have been
developed by Atkins. All this will deliver many benefits to railways and the
travelling public.
Initially, the Shepperton branch will be controlled from a
single workstation located at Feltham signal box before being transferred to
Basingstoke rail operating centre (ROC) in a later stage within the overall Feltham
resignalling. A maintenance training facility has been provided at the ROC,
which will allow technicians to familiarise themselves with the
state-of-the-art signalling equipment. The training facility will provide the
ability to generate physical and virtual faults, to practise equipment repair
and reconfiguration – essential for modern IP networked assets in an
off-network environment.
The recent Atkins commissioning followed the successful
introduction of the ElectroLogIXS system at Old Oak Common depot in 2018. This
was the first installation to use the ElectroLogIXS digital interlocking, which
is now performing well as part of the validated signalling system for this
vital Crossrail depot.
The new signalling system is not just about new equipment
though, as Atkins has successfully introduced innovative production methods to
deliver a flexible, future-proof, digital-signalling-compatible solution. Its
approach is technology agnostic – Atkins has considerable expertise in a wide
range of signalling products and is not tied to any one product, being able to
choose and work with the best equipment available. This knowledge and
experience of all types of signalling also means that Atkins is ideally placed
to manage the interface requirements with other types of signalling, often the
most difficult and risky part of any signalling scheme.
Ladder logic
The ElectroLogIXS interlocking is a flexible, ‘ladder logic’
driven device that deploys software written using the Atkins Signalling Method
(ASM). The introduction of this interlocking in the UK is intended to remove
reliance on existing interlocking products and solutions, with the system
enabling the rationalisation and reduction in the quantity of trackside
cabling, along with many other benefits.
Ladder logic was originally a manufacturing industry and
process control method to document the design and construction of relay racks.
Each device in the relay rack would be represented by a symbol on the ladder
diagram, with connections between devices shown. Other items external to the
relay rack, such as pumps and heaters, would also be shown on the ladder
diagram. It then evolved into a programming language based on the circuit
diagram relay logic hardware.
Ladder logic is now widely used in other industries to
develop software for programmable logic controllers (PLCs) that are being used
in industrial control applications. Ladder diagrams were once the only
available notation for recording programmable controller programs, but today
other forms are standardised in IEC 61131-3, the international standard for
PLCs that is over 20 years old and is accepted in many industries.
Less equipment
The standardisation of equipment and a reduced number of trackside equipment location cases is a major benefit, which will deliver significant capital and operating savings. There will also be no reliance on bespoke software languages used in previous electronic interlocking technologies, with the system designed to be future proof, scalable and ETCS compatible.
Atkins has calculated that resignalling all of the Feltham
signalling project area using conventional SSI would have required in the order
of 3,000 relays and 450 lineside equipment locations. Using the new future
signalling system, this will reduce to approximately 130 relays and 220
lineside equipment locations, a reduction that will bring with it a step change
in reliability.
The solution developed by Atkins is based on a design using
more readily available non-discipline-specific software engineers, rather than
scarce signalling designers, allowing the signalling engineers to focus on the
core functional signalling requirements.
With traditional SSI interlockings, there was also a large
number of data errors leading to failures resulting in significant resources required
to resolve. So, Atkins has identified new methods of data production and
testing, using modelling techniques and empirical processes as part of their
new way of working.
The design and testing of electronic interlocking data was
also taking too long, so one requirement for the new way of working was for
repeatable data modules, designed and tested once and then used many times.
Some current interlocking technology (SSI trackside
functional modules, for example) are reaching the end of their life, so new
equipment solutions are also required. An interlocking capable of communicating
with a Radio Block Centre (RBC) was essential to enable a future, easy upgrade
to ETCS, once compatible rolling stock is available on a route.
Network Rail’s technology strategy requires new interlocking technology to comply with the EN 50128 functional safety standard (Railway applications – Communication, signalling and processing systems – Software for railway control and protection systems), so the ElectroLogIXS interlocking creates a new solution that is designed from the start using EN 50126 (Railway Applications – The Specification and Demonstration of Reliability, Availability, Maintainability and Safety), EN 50128 and EN 50129 (Railway applications – Communication, signalling and processing systems – Safety-related electronic systems for signalling standards).
The ElectroLogIXS hardware is manufactured by Alstom
(formally GE) and is a vital logic controller (VLC), using internet protocol
(IP) communications and advanced diagnostics via a scalable remote condition
monitoring system and a common hardware platform for both trackside and control
parts of the system. Its chassis-to-chassis communication uses RP2009 (SIL4)
protocol with no safety reliance on the network. The equipment’s product
acceptance has been developed to cover both ‘interlocking’ and ‘level crossing
controller’ applications, both of which have been used on the Shepperton branch
commissioning.
Compliance with EN 50128 is considered a step change improvement
in safety when compared to SSI data software, with the automation of the design
process along with the production of the ladder logic. This enables far more
testing to be carried out automatically, delivering consistency and reliability
in results. High levels of automated testing will save time to commission
projects, while reducing the dependency on scarce testing resources required
and the associated risks.
The interlocking is provided in three sizes, with either a
one, four or nine slot capacity. New input/output cards have been designed for
the UK that are ‘hot swappable’, with personality modules provided to ensure
their correct location in the chassis.
The hardware is designed to work reliably between -40°C and
+70°C. Its power supply requirements are only 70W, with an internal 5V supply
derived from a 12V external feed. The processor is a two-out-of-two arrangement
that can handle 10,000 vital equations extremely reliably. Up to 32
interlockings can be multi-dropped together if required, making it truly
scalable.
With the new Atkins system, all trackside equipment is
contained in a smaller number of location cubicles with no equipment buildings
required, thus saving both cost, access and space. The actual ElectroLogIXS
interlocking is contained on a very small circuit board within one equipment
location housing – a relay interlocking to deliver the same functionality would
have required a room the size of a garage.
It can be very costly and time consuming to erect bases for
lineside buildings, which may also require several line blockages to install.
Once in place, power is required for lighting and heating, and the buildings
create a maintenance liability for the life of the signalling project. Atkins
has now eliminated all this risk, with all the signalling equipment located in
low-cost, smaller lineside equipment cubicles.
The lineside digital communications network consists of
Layer 2 network switches (housed within each signalling location case), while
the control centre network uses Layer 3 switches (housed within each cubicle).
The Network Rail Fixed Telecom Network (FTN) is used to ‘bridge the gap’
between the lineside and control centre elements of the network.
A 24-fibre optic cable to NR/PS/TEL00014 between FTN access nodes forms a sub access layer to the telecoms network. This is supplemented with a two-fibre pre-terminated cable to connect the lineside equipment.
Atkins Signalling Method
A significant change in approach to the design of a scheme
has been the introduction of the Atkins Signalling Method (ASM). This is
intended to maximise overall efficiency across the design (including
interdisciplinary design interfaces), procurement, installation, testing and
commissioning.
Deviations from the ASM are prohibited without the formal
agreement of the ElectroLogIXS Technical Authority Group, to avoid changes that
appear to give a benefit (such as a reduction in materials) but actually cause
inefficiency on a scheme. The ASM also allows the use of another programmable
logic controller (PLC) hardware platform in the future far more easily than was
the case with previous bespoke designs.
Level Crossing in a Box
The ‘Level Crossing in a Box’ (LCiaB) concept arose from the
idea of delivering a complete crossing in a container ready for installation.
This has now evolved to an element of ‘just in time’ delivery, but the concept
of a complete and ready to install crossing. In the Shepperton scheme, the
solution has been provided at Hampton MCB-CCTV (manually controlled barriers
with closed circuit television) crossing.
Currently, LCiaB is specified for MCB-CCTV, but it has been
designed so that is can easily be configured for other types of MCB and as a
miniature stop light (MSL) crossing. The crossing solution consists of two or
four barriers. It can be deployed either as a standalone installation or part
of an Atkins ASM signalling system. Up to six sets of traffic signals
(wig-wags) and four ‘Standing Red Man’ signals can be supported.
The barrier machine, supplied by Newgate, is also new to the
UK signalling market and is 110V AC powered, with the boom driven by a
three-phase inverter and motor through a gearbox. Angular detection of the
barrier is by factory-set rotary blades detected by proximity sensors. There
are a pair of industrial safety switches which mechanically detect the drive
spindle when it is in the lowered position.
A small safety controller (PLC) provides machine control via
a set of 24V DC control and indication lines connected to the level crossing
controller (LXC) case. Manual operation is achieved with a small hydraulic pump
and cylinder system. A machine has already completed in excess of 3,000,000
fault-free operating cycles in the factory.
Going forward
The benefits of this new signalling system include both safety, reliability, programme, scalability and cost. Atkins believes that, once the solution is fully accepted, it can deliver an overall saving of 20 per cent in capital cost compared to other solutions and a 65 per cent saving in whole life costs over 35 years. In terms of programme, Atkins estimates an 18-week improvement over conventional signalling should be achievable, with more to come.
The June commissioning of the Shepperton branch Feltham will be followed by the re-signalling of the Norwich – Yarmouth – Lowestoft routes, also using the ‘future signalling systems by Atkins’, with interfaces to existing signalling at Norwich and to the East Suffolk line at Oulton Broad. The area will be controlled from Colchester ROC.
Other schemes using the new system should include phase two
of East West Rail – the Bicester to Bletchley section – using the system to
provide both interlocking and level crossing controls controlled from Thames
Valley ROC.
The system is compatible with several RBCs (radio block
controllers) for ETCS deployment, while further innovative Atkins enhancements
to the system may include integration with intelligent infrastructure,
IP-enabled barrier machines, IP-enabled signals, integration with ETCS and
level crossings, VoIP telephony, replacing ElectroLogIXS VLC with a
commercial-off-the-shelf (COTS) PLC product and radio-based communications
between lineside ‘objects’.
Rail Engineer naturally looks forward to returning to report the complete renewal of the Feltham signalling area with the ‘future signalling systems by Atkins’. If the scheme goes to plan, completion will be achieved by 2024, when the whole complex area will be under the control of Basingstoke ROC.
Thanks to Nicky Brunker, James Sykes and Matt Phillips of Atkins and Tim Weston of Network Rail for their assistance with this article.
A railway must be supported with a safe and reliable power system for signals, points, interlockings and communications. This power system must be tolerant against failure and provide a constant, stable supply in order for the control and communications equipment to operate correctly.
Often either taken for granted or overlooked, power systems
for railways can be difficult to provide, given that the infrastructure is long
and narrow and not always close to an external power source. In addition, the
earthing arrangements differ from domestic, industrial and commercial
electrical systems, a situation that has caused compliance issues with safety
requirements.
The signalling power supply must always be available, with a
continuity of supply similar to other safety-critical applications, for example
airport ground lighting or hospital operating theatres. So, it is not
acceptable to turn everything off when a fault arises, which has been a
traditional electrical engineering solution for such hazards.
The power system must be safe, both for maintenance staff
and for members of the public, when the equipment is located on platforms or at
level crossings, even should faults occur that result in accessible metal
becoming live.
Railways have invested a lot of time, effort and money in
providing reliable power supplies with multiple sources of energy, but, in some
cases, they have neglected the power distribution network that moves the power
to the current-using equipment. However, over the last few years, new maintenance
processes and the introduction of Class II equipment have improved matters,
after a lot of effort by both signalling and power engineers in Network Rail
and the supply industry.
Principal Supply Point
A signalling power supply comes onto the rail infrastructure from a Distribution Network Operator (DNO) network via a Principal Supply Point (PSP). DNOs are companies licensed to distribute electricity in the United Kingdom. At the PSP, the incoming supply is converted to the distribution voltage of, typically, 650V. The incoming supply is usually 400V, but can be other voltages.
To maintain continuity of supply, PSPs use additional
sources in addition to the 400V DNO supply, including the railway’s own
three-phase high voltage traction-power system and standby generators.
A PSP for an important route may also have an
uninterruptible power supply (UPS), so that the supply is maintained during the
changeover between the two sources. In simple terms, a UPS is a big battery
fitted with an inverter that converts the battery’s DC output to AC. It may
also provide insulation monitoring equipment.
Functional Supply Point
The major elements of a railway signalling power system are
the power sources, the distribution network and electrical loads (sometimes
referred to as current-using equipment). The power supply voltage is often
transformed down to a lower voltage to minimise voltage drop when distributed
over longer distances. Historically, a two-wire 650V AC distribution system has
been used for railway signalling power in the UK.
Within a trackside case, equipment known as the Functional
Supply Point (FSP) normally converts the 650V AC to 110V AC using
transformer(s). The FSP contains transformers and rectifiers to convert the
power distribution voltage to the AC and DC voltages used by the track-side
train control system equipment. It may also accommodate lockable switchgear, to
allow for safe working practices on the power distribution and train control
equipment.
Location Cases (Locs) accommodate railway signalling
equipment to detect the location of trains, control the trackside signals and
switch the points. Locs and FSPs can be the same physical asset, containing
both power equipment and train control equipment. The equipment may typically
use both AC and DC voltages less than 110V, so transformers and rectifiers are
required to obtain the correct voltage from the incoming supply.
Class I and Class II protection
Protection arrangements in power distribution networks are generally Class I or Class II. In Class I, exposed metal parts must be connected together and connected to electrical earth by a separate earth conductor (coloured green/yellow in the UK). The basic requirement is that no single fault can result in dangerous voltage becoming accessible so that it might cause an electric shock and that, if a fault occurs, the supply will be automatically disconnected. Traditionally, railway signalling power supply distribution systems have been based on Class I individual earth designs, which require an effective earth arrangement.
Class II, or double-insulated, electrical equipment is
designed in such a way that it does not require a safety connection to
electrical earth. The basic requirement is that no single fault can result in
dangerous voltage becoming accessible so that it might cause an electric shock,
and is achieved without relying on an earthed metal casing. This is usually met
by having at least two layers of insulating material between live parts and the
user, or by using reinforced insulation. Not only is there a safety benefit
with Class II, but the availability is far greater as the supply is not tripped
due to a cable fault.
In domestic situations, Class II power supplies (such as
laptop chargers) will have a two-wire power cord as opposed to a three-wire
power cord with a safety earth connection. Products designed with Class II
insulation are often labelled as “Class II” or “double insulated” or will have
a concentric square safety label symbol.
Earthing
BS 7671 (the IET Wiring Regulations – informally called “the
regs” by some) covers the primary types of power system earthing arrangement
called TN, TT or IT. These use the French terms for Terre (earth), Neute
(neutral) and Isolé (isolated).
The first letter indicates the connection between earth and
the power-supply equipment, so ‘T’ indicates a direct connection of a point
with earth (Terre) while ‘I’ means that no point is connected with earth
(Isolé).
The second letter indicates the connection between earth or
network and the electrical device being supplied, so ‘T’ corresponds to an
earth connection by a local direct connection to earth (Terre) or ‘N’ shows
that the neutral connection is supplied by the electricity supply network
(Neutre).
The traditional way of distributing the power trackside
along the railway for signalling has been using the IT earthing system. The
output of the source transformer is isolated from earth, whilst all exposed
conductive parts of the installation are connected to earth.
The source transformer output is isolated from earth, although the system will be still earthed by the stray capacitances of the cables. Should there be a fault with the cable insulation or FSP equipment, creating a direct short circuit to earth, there is no return path for the earth fault current with the equipment remaining operational.
The trackside cables are usually, but not always, two-core,
and each FSP is individually earthed using an electrode formed of one or more
buried earth rods. An appreciable earth fault current may flow, but the length
and resistance of the feeder circuit conductor to the fault locations, as well
as the resistance of the Loc connection to earth, can result in a fault current
that is insufficient to cause automatic operation of the protective device in
an acceptable time.
The general mass of earth can be variable, which makes the
magnitude of earth fault current difficult to predict.
The problem is that this arrangement is not compliant with
the Electricity at Work Regulations 1989, nor BS 7671 (Wiring Regulations). The
highest permitted accessible voltage is 50V (BS7671) or 60V (EN 50122-1). This
may be exceeded on some large legacy power distribution 650V networks.
An even bigger problem on a system with an IT Earthing
arrangement is with a second earth fault situation, as an accessible harmful
voltage is very likely to be present for an unacceptable duration. The ratio of
the two earth fault resistances will determine how much of the 650V system
voltage appears on each faulty equipment case.
It is believed that the non-compliance with BS 7671 may have
arisen because there is an exemption for ‘railway signalling equipment’ in the
standard, which railways relied upon for many years. However, the Office of
Rail and Road (ORR) took the view that the exemption to the regulations is only
for the ‘signalling equipment’ itself and not the electrical distribution
networks feeding signalling equipment. In any case, the Electricity at Work
Regulations 1989 are applicable, so non-compliance is not an option.
Improvement Notice
The legacy design, and, in particular, the hazard from
exposed conductive parts of signalling equipment in public areas, resulted in
the ORR issuing Network Rail with an Improvement Notice on 19 November 2013. In
the notice, the ORR stated: “650V power distribution networks used to supply
power to track-side signalling equipment at various locations on Network Rail
managed infrastructure are not constructed to prevent, so far as is reasonably
practicable, danger. Signal location cases, to which members of the public have
access, are not adequately earthed and bonded to prevent danger should exposed
conductive parts become charged at dangerous voltages”.
The scope of the notice applied to all of the 650V power
distribution networks across Network Rail managed infrastructure, and the ORR
considered that the situation contravened the statutory provisions contained in
Section 3(1) of the Health and Safety at Work Act 1974 and regulations 4(1),
4(2) and 8 of the Electricity at Work Regulations 1989.
Network Rail was required to undertake a review of 650V power distribution networks to which members of the public have access, to:
Identify assets with exposed conductive parts
that are not adequately earthed and bonded to prevent danger, should they
become charged at dangerous voltages;
Subject to the findings of 1) above, undertake
suitable remedial works, prioritised on the basis of risk, to ensure that 650V
signal location cases which may reasonably foreseeably become charged as a
result of an electrical fault are earthed and bonded;
Devise and implement inspection and maintenance
arrangements for ensuring that 650V signal location cases to which members of
the public have access are maintained to prevent, so far as is reasonably
practicable, danger;
Implement any other equally effective means of
achieving compliance with the notice.
Compliance strategy
A number of solutions were identified by Network Rail to
comply with the Improvement Notice. These are linked and need to be combined in
addressing the risks to the signalling power distribution problem.
A suite of Class II-based power system equipment and designs were developed and approved. Signal power network insulation monitoring and fault location equipment have been introduced, based on risk. The design and installation of signal power network earthing arrangements have been revised, together with a much-improved signalling power system inspection and maintenance regime.
Competences and training have been reviewed and greatly
improved, both for signalling power system inspection, testing and maintenance,
together with improved safe working practices for work on or near signalling
power equipment.
The inspection and maintenance regimes have also been
improved. Responsibility and accountabilities are clearly defined and include a
requirement to inspect and take action based on risk. A consistent national
method of classifying defects by codes and the required response, and by whom,
has been implemented.
Additional resources, where required for the inspection and implementation of identified control measures, have been authorised, which includes the required competencies. Where a hazard is identified, a feasibility design, based on risk and the ground resistance, may require a Class II system to be installed retrospectively, should an improved earth electrode not be sufficient.
Traditionally, feeder insulation monitoring equipment can
identify that a fault has occurred, but not where the fault is located. The
fault could be anywhere on the power network, which can total more than 30km in
a large signal box area, requiring time-consuming inspection and testing to
locate the fault. Network Rail is currently trialling ‘smarter’ insulation
monitoring equipment, which is able to trace the location of any fault better.
The equipment is based on designs used in the offshore oil and gas industries,
and the results are encouraging. Full approval is expected soon.
The Class I collective earthing system (which complies with
the regulations) was not specifically identified as part of the improvement
notice response, but such systems had been used selectively around the network
for a number of years, such as on the Mickle Trafford resignalling in 2006 and
Crewe-Winsford remodelling in 2008. With the Class l collective earthed system,
a three-core armoured cable is used rather than a two-core 650V supply cable.
The third core and armour are used together in parallel as a circuit protective
conductor (CPC) to bond all the equipment together equipotentially. The bond ensures
that, in a second fault situation, there is a low impedance path present.
The problem with this arrangement is a financial and
environmental one, as it requires 50 per cent more conductor than the Class 1
individually earthed arrangement, increasing not only cost but also the risk of
theft.
Class II power supply design
Class II was selected, not just as a means of eliminating
safety risk arising from second earth faults, but also as a means of
eliminating harmful voltage on accessible conductive parts with first earth
faults. An effective local electrical safety earth electrode is no longer
required at an FSP on a Class II power distribution network.
Using Class II for railway signalling power distribution
satisfies the requirements of BS 7671 regulation 410.3.3 by utilising double or
reinforced insulation instead of the traditional automatic disconnection of the
supply as protection against electrical shock. This also has the benefit of
lower capital cost. However, effective continuous monitoring of the
distribution system insulation remains an essential safety feature of any
Class II power distribution network.
A Class II-based design solution has been identified for
new-build signalling power distribution systems and the renewal of legacy
signalling power distribution systems, using two-core unarmoured cables. A
number of resignalling schemes have already been installed using Class II and,
over the next two years, a significant amount of signalling power system
renewals will replace Class I with Class II. This includes the West Coast power
signal boxes north of Crewe.
Location case and equipment buildings will be provided with
Class II switchgear housings and Class II signalling transformers, with
approved conduit and fittings, will be used to provide supplementary insulation
and protection to wiring between the items of Class II equipment. Distribution
equipment can be connected by either two-core enhanced unarmoured cable or
two-core armoured solid-bonded cable, provided that the armour is not allowed
to traverse the Class II-fitted functional supply points. However, extensive
testing identified that an enhanced unarmoured cable option presents the
highest overall level of safety.
The overall Class II strategy will result in improvements to
personnel safety, compliance with standards, greater tolerability to DC
corrosion, simplified earthing and bonding in AC electrified areas, along with
reduced capital costs, better reliability, less maintenance and the ability to
integrate into legacy systems.
To support the strategy, Network Rail has issued a range of
new standards. The key standards are issued as both signalling and
electrification/plant (SIGELP) standards, are designed to be user friendly and
to inform the right person what they need to do to control the risk.
The strategy was accepted by the ORR and the Improvement Notice was closed down on 22 August 2017, with the ORR monitoring the situation.
Thanks to Graeme Christmas, Martin O’Connor and especially Graeme Beale, of Network Rail, for their help with this article.
The challenge of implementation…
In history, there are often moments or circumstances that turn necessary actions into unforeseen opportunities. As a result of the improvement notice, the introduction and roll out of retrofittable Class II as a compliance strategy now provides Network Rail with the tools and the methodology to deliver widespread enhancements to all signalling power supplies, with minimal disruption. As with most new systems and technology, one key challenge is its implementation within the existing infrastructure. This challenge is one of understanding and joined-up process driven by survey, integrated design, option selection and efficient deployment. It has been discovered that, over the past four to five years, this package of works is ideally suited to support Network Rail’s existing route delivery teams. An example of this efficient process can be seen above.
New technology born out of change! Maintenance of the existing signalling power network places a high demand on existing human resources. Routine testing and the assessment of the existing 650V signalling power cable presents existing maintenance teams with both safety and logistical challenges. Cable and system monitoring technology offers a significant improvement in the management of these assets. Insulation monitoring and fault location devices enable rapid response and proactive maintenance regimes to be implemented. The key success of the roll out of this technology is the ability to deploy alongside the Class II retrofitting process, thereby leaving the asset in both a fully compliant and digital-ready state. There have already been several examples of significant infrastructure reliability improvements as a result of Class II deployment. One is the elimination of low insulation monitoring values as a result of prescribed Class II retrofits, a second is confirmation of potential cost savings in unnecessary cable replacement across a large section of the Thameslink Route.
Funded by the Strategic Freight Network, with a contribution
from Hutchinson Ports UK (HP-UK), a £60.4 million investment to create a new
1.4km loop on the Felixstowe branch line in Suffolk was successfully brought
into service on 29 May 2019, on time and on budget. It facilitates an increase
from 33 to 47 freight train paths a day in each direction on this key artery,
carrying the highest freight tonnage in the country and serving the largest
container port in the UK.
With each train taking the equivalent of up to 76 lorries off
the roads, the strategically important Felixstowe to Nuneaton Freight Corridor
(F2N) has seen considerable investment in recent years. This has included gauge
clearance for W10 ‘High Gauge’ containers and capacity improvement including
the Ipswich Bacon Factory Chord (issue115, May 2014), Ely Freight loops, and
Nuneaton north chord.
As built in 1875, the 12-mile branch was single track with a passing place at Orwell, roughly mid-way. In 1891, two more passing loops were added, at Derby Road and Trimley. The original loop at Orwell closed with the station in 1959, leaving an eight-mile single-track section. In 1999, the passing loop at Derby Road was extended to accommodate container trains and the whole line was resignalled and controlled from Colchester Power Signal Box (PSB).
The Trimley loop scheme
Following on from a 2005 GRIP 4 (single option development) study undertaken by HP-UK for doubling the branch between Orwell and Trimley for 4.5 miles, subsequent extensive option development work concluded that a 1.4 km loop at Trimley with bi-directional signalling at Derby Road would facilitate the aspiration to operate the additional paths, with a maximum train length of 775 metres – a Network Rail standard, although HP-UK currently operates trains around 600 metres long.
The scheme will allow pent up demand to be realised from the
December 2019 timetable change, giving operators a few months to familiarise
themselves with the new signalling.
It will also improve the reliability of the hourly passenger
train shuttle between Ipswich and Felixstowe, shortly to be upgraded with the
introduction of new Stadler Class 755 bi-mode units later this year.
This infrastructure improvement project is being delivered
within the Network Rail Anglia Route CP5 multi-functional framework contract,
which was awarded to VolkerFitzpatrick. The collaboration to deliver these
works is known as the Anglia Route Collaboration (ARC).
Rail Engineer was recently invited to meet VolkerFitzpatrick
project manager Dan Smith at the Trimley project offices and to see some of the
work at first hand.
The scope of the project includes:
1.4km of additional track at Trimley;
Closure of six pedestrian crossings;
Construction of a bridleway bridge;
Re-alignment of the existing public rights of
way network;
Replacement of three Automatic Half-Barrier
(AHBC) level crossings with Manually Controlled Barriers with Obstacle
Detection (MCB-OD);
Replacement of one AHBC level crossing with
MCB-CCTV;
A new signalling workstation;
A new signal interlocking;
New lineside signalling on the branch line as
required;
Bi-directional signalling on both lines at Derby
Road;
Installation of a new 650V DC Class II
signalling power supply;
Installing a diverse Fixed Telecommunications
Network (FTNx) system and associated infrastructure.
Such a diverse project required an equally varied group of
contractors and suppliers to complete, and these are listed nearby.
Public rights of way
A network of footpaths and narrow lanes criss-crosses the
railway along the stretch that has been doubled, necessitating detailed level
crossing risk assessments. The study identified significant increase in risk to
crossing users on the duelled stretch of line:
Double track creates a particular hazard for
‘Stop, look and listen’ crossings;
New loop exit signals could cause waiting trains
to obscure the view of an approaching train;
Trains could be held at signals, thereby
blocking footpath crossings;
Trains could be held at signals and cause
existing AHBCs to ‘time-out’;
Log of many incidents /near misses.
Accordingly, the report recommended the closure of six pedestrian crossings and conversion of the AHBCs to MCBs. As there were 10 objections to the Level Crossing Closure Order, a public enquiry was convened. The Inspector found in favour of Network Rail and the order was duly endorsed by the Secretary of State for Transport.
The project worked closely with Suffolk County Council to
devise alternative provision for the six footpaths being closed, the
centrepiece of which is a new bridleway/footbridge across the line near Gun
Lane. New footpaths are being created alongside the railway, connecting
existing rights of way with the new bridge, which has equestrian ramps at the
Trimley end and footpath steps at the Ipswich end.
With advice from the British Horse Society, the Network Rail standard holly green ramped footbridge design has been expanded to fit the scale needed for horses with 3.5 metre width. Stablesoft equestrian flooring is fitted on the deck, and mounting blocks at the start of the ramps encourage horse riders to dismount and walk the horse over. The bridge is due to open at the end of July.
The three new MCBs, at Morston Hall, Thorpe and Levington,
utilise Obstacle Detection (OD) technology comprising radar primary obstacle
detection (POD) – the safety-critical component required to detect objects that
would be a danger, such as vehicles, people or large animals – and Light
Detection and Ranging system (LiDAR) as the complementary obstacle detection
(COD), to reduce the risk of an object in the crossing area below 500mm from
the road surface remaining undetected.
In short, the COD uses infra-red technology to detect
objects such as prone bodies and small children in the space below that covered
by the POD’s radar, which is mainly looking for large objects.
The conversion of the existing Westerfield AHBC is outside
the immediate area of the new loop but will be affected by the increase in
freight traffic. Increased road traffic resulting from a new Ipswich Garden
Suburb Development of 3,500 new homes in the vicinity of Westerfield clinches
the need for conversion to MCB. The configuration of the crossing in relation
to footpath ramps to the platforms means that OD may not operate reliably, so
this crossing will be MCB-CCTV.
The conversion of this crossing will benefit Up East Suffolk
trains. Hitherto, most Lowestoft to Ipswich trains that are not scheduled to
stop at Westerfield have to pause in the platform due to the lack of
‘non-stopping’ provision in the controls of the existing AHBC. This will, of
course, be rectified with separate ‘stopping/non-stopping’ strike-in points for
the new MCB.
However, the ‘Auto Lower’ control (provided as standard with
‘Auto Raise’ at all of the new MCB crossings) at Westerfield will not initially
be used, as there have been a number of incidents including blocking back over
the crossing. Red light violation cameras, already in place at Westerfield,
have been installed at all the new AHBC crossings.
Colchester PSB
The signalling was controlled from the Entrance-Exit (NX)
Ipswich panel. However, with the addition of the Bacon Factory curve in 1999,
the increase in freight traffic, and an increase in passenger train frequency
in recent years on the main line and East Suffolk lines, the workload threshold
has been exceeded.
Operating Ipswich station can be challenging if trains
arrive out of sequence and upset the planned platform sharing. Perturbation of
passenger traffic here can react onto the Felixstowe branch. Similarly, trains
using the single-line sections on the branch have to run to path in order to
avoid reactionary delays elsewhere. All this gives the signaller little or no
thinking time when things go awry.
With the upcoming further increase in traffic on the branch, it was decided to provide a new Alstom Modular Control System (MCS) workstation. This is positioned right in front of the Ipswich NX panel, with VDU screens low on the desk to allow the Felixstowe signaller to view trains approaching from Ipswich station/yard and coming around the chord from the north.
The Felixstowe branch hasn’t been completely expunged from
the NX panel. Basic indications and train descriptions alert the Ipswich
signaller to the approach of traffic from the Felixstowe and East Suffolk
directions.
A new Smartlock 400 interlocking has been provided to
replace the previous Alstom MkIIIA Solid State Interlocking (SSI) and this
aligns with the jurisdiction of the new workstation from the mid-point between
Boss Hall junction and Westerfield, through to the branch. Saxmundham signal
box MCS already controls the East Suffolk line north of Westerfield. The
Smartlock central interlocking processor (CIXL) contains two virtual
interlockings (VIXL), with a geographical split between Derby Road and Trimley.
The CIXL is connected via a new FTNx link utilising Keymile
first-line multiplexers and Cisco routers, interfacing the field long distance
terminals (LDT) at a new location at Westerfield. Here, the SSI data passes
onto the existing SSI trackside data links.
Diverse routing was originally provided by renting BT
private circuits. This has been replaced by the installation of a new, small,
green-sheathed, double insulated, super armoured cable (DISAC) 24-fibre cable,
designed to be laid on the surface, running the length of the branch. SSI track
function modules (TFM) interface the data link via optical data link modules.
Signalling
On the ground, the signalling modifications and additions
were extensive. In summary:
Cutting the existing SSI data links into the new
location areas to bring them onto the existing data stream;
86 location equipment cabinets have been
affected (59 altered, five abolished, 22 new);
Existing signals re-allocated with new
identities relating to the new Felixstowe workstation rather than Colchester
prefix;
25 new lightweight LED signals (21 main aspects,
four three-state banner repeaters but with only ON/GREEN used, two additional
route indicators either side of Derby Road);
Recovery of SPAD indicator signals (surplus
since the provision of TPWS);
24 new AWS (Automatic Warning System);
35 new TPWS (Trains Protection and Warning
System);
Five new In-bearer Clamp Lock (IBCL) point ends;
Eight existing point ends re-controlled and
re-numbered;
Four new MCB level crossings;
Existing Felixstowe Beach and Trimley MCB-CCTV
crossings and associated Time Division Multiplex (TDM) systems re-controlled to
new workstation;
Alterations to insulated block joint (IBJ)
positions to extend or reduce the length of existing track circuits;
Provision of new standard-issue AC-immune DC
track circuits to BR 867 track feed sets.
Electrical & Power (E&P)
E&P teams installed a new 650V DC signalling power
supply feeder throughout the branch comprising a new power supply point (PSP)
at Westerfield, upgrade and modifications to other existing PSPs, the
installation of 42 functional supply points (FSP) and installation of 45km of
new cabling.
The works also covers the installation of direct power and
lineside power supplies for a number of level crossings, as well as new
level-crossing lighting.
In addition, three points heating cubicles (PHCC) were
supplied and installed along with points heating supplies, transformers and
heating strips for point ends.
Permanent way
Track panels and switches and crossings (S&C) were
brought in by road, rather than the more usual unloading from tilting rail
wagons, due to limitations of the single line. There are two new modular
crossovers and a single turnout. Switches are type CEN56 EVS.
Redundant trap points were removed from Trimley.
Thankfully, the line was originally well built, with a well-drained and stable formation including embankments and cuttings, well able to support the heavy pounding from today’s freight tonnage.
Staging the project
Work on the ground commenced in April 2018. The port runs no
trains between Saturday evening to Monday morning, so it was possible to
schedule complete possessions during this time for most weekends through to May
2019. During these possessions, stone, sleepers, rails and track panels were
run out for the loop, new signals erected, new 650V DC signalling supply cables
run out, SSI data links cut into the new locations, and the steel sections of
the equestrian bridge (pre-fabricated at Doncaster), craned in over four
weekends using a 750T crane.
A blockade over the Christmas 2018 holiday period saw the all new loop S&C installed into the existing running line using a Kirow crane. Point ends were detected and cut into the track circuit, such that a point failure would show up as a track circuit failure, a scenario covered by a special signal box instruction. The new 650V supply system was fully commissioned.
A further possession during the 2019 spring bank holiday saw
the signalling system put through ‘out and back’ rehearsal testing. All the
external equipment and data links were connected for testing to the new
Smartlock & MCS. New signals, TPWS and AWS were correspondence tested and
the existing equipment through tested, before being switched back to the
original system, giving a few days for outstanding issues to be resolved.
The final commissioning of the new signalling workstation
took place overnight on 28/29 May. On this night, the systems were changed over
to final and assets tested that were not picked up on rehearsal were
correspondence tested. Signalling data was 90 per cent factory tested in a
simulation, just leaving any outstanding principles testing and those elements
that couldn’t be done in the factory, such as the fringe to Saxmundham SSI and
Ipswich Bacon Factory Curve Route Relay Interlocking (RRI), which can’t be
simulated on the workstation. Some train-detection alterations could not be
implemented prior to this commissioning.
With the signalling up and running, the installation and
testing resources moved to bring the MCBs into service, one at a time, in the
order Morston Hall, Thorpe, Levington and finally Westerfield, due for
completion in the middle of July. During the main commissioning, level crossing
indications were strapped out to fool the interlocking into thinking the
barriers are down. At each stage, as a new barrier is brought into service, the
temporary wiring is recovered, with barrier control inputs and outputs working
live thereafter.
Inevitably, the scheme has involved temporary road closures,
for which Network Rail devised a strategy in conjunction with local councils.
For example, Thorpe and Morston Hall didn’t have diversion routes, so the plan
was to close one and use the other as a diversion, then swap around.
The future
The current project effectively uses up all the existing
freight network capacity. Pinch points elsewhere, including the single line
from Soham to Ely, Ely North single lead junctions, and Syston junctions, will
need to be addressed before embarking upon further capacity upgrades on the
branch itself.
The vision of entrepreneur George Tomline, who built the docks and railway back in 1875, and the subsequent commitment of port and railway owners, has assured the continuing growth of this booming port.
Thanks to Dan Smith of VolkerFitzpatrick, Tom Fitzgerald of Pod-Trak, Darren Welch of VolkerRail, and Martin Spencer, Arun Jacobs and Ian Martin of Network Rail for their help in preparing this report.
Contractors and suppliers
Contractors:
VolkerFitzpatrick – Principal contractor; Volker Rail – sub contractor for signalling, level crossings, signalling design including the scheme plan; Atkins (part of the SNC-Lavalin Group) – design for GRIP stages 3&4, TWAO support; Mott Macdonald- GRIP 5 detailed design track, Civils, E&P, telecoms and level crossing ground plans; Pod-Trak – Permanent way, earthworks; Global Rail Construction- E&P – 650V signalling supply and points heating, ancillary works including under track crossings, ancillary civils; Network Rail Telecoms (NRT) Anglia Route – telecoms testing and commissioning; PLS Civil Engineering – LX civil engineering, pedestal bases, highway works, white lining; Alstom – Smartlock 400 interlocking, MCS workstation and Vital Harmon Logic Controllers (VHLC) for MCBs; Sotera Risk Solutions – GRIP 3 level crossing risk assessments; Carver Engineering Services – bridleway bridge, steel work pre-fabricated at Doncaster and craned in over four weekends using a 750-tonne crane.
Suppliers:
Progress Rail – Switches & Crossings Unipart Rail – Barrier lights Honeywell – Level-crossing radar Collis Engineering – Lightweight signals SPX Rail Systems – Barrier machines L B Foster Telecoms – Red light violation ANPR (automatic number-plate recognition) cameras CISCO – routers Keymile – first line multiplexers Kestrel Telecom – Hawk telephone concentrator.
Network Rail’s supply chain recognised at the Rail
Partnership Awards
The Rail Partnership Awards, in which Network Rail shows
appreciation and recognises its supply chain for its achievements over the
previous year, took place in Birmingham in June. First held in 2009, when 11
awards were presented and Balfour Beatty won the coveted Supplier of the Year
trophy, the 2019 version saw a total of fifteen categories on the list.
Thirteen of these could be entered by the suppliers. 214
nominations were received from organisations both large and small, all hoping
to win an award for categories as varied as collaboration, diversity and
inclusion, safety and putting passengers first.
The fourteenth category was for the Standards Challenge. To
increase innovation and creativity, and to reduce costs, Network Rail
introduced a new process at the end of March 2018 to enable suppliers and other
stakeholders to raise a challenge to a standard where they considered it to be
incorrect, to not enable the application of best practice, or to drive increased
cost without comparable benefit.
The best challenges were put forward for this year’s special
award.
Then, of course, there is the fifteenth award – the Supplier
of the Year – which would be chosen from the fourteen individual winners.
This year, every category had two judges, one from Network Rail and one from the industry. Between them, they would whittle shortlists of six to eight entries down into a winner and, if they felt the standard was high enough, one or two ‘highly commended’.
Hello and Welcome
Network Rail chief executive Andrew Haines (pictured)
welcomed guests on the evening. He spoke of the work that the industry and
supply chain does, throughout the year.
“It’s right that we take times like this, not to slap
ourselves on the back, but to recognise the really fantastic work that’s done
by such a diverse group of people.
“This is a brilliant, brilliant opportunity to recognise
just how diverse the railway family is, a partnership that does brilliant
things, day in, day out.”
He then spoke of the money that was being spent on the
railway over the next five years. “£42 billion that could have been spent on
schools, hospitals, defence, policing,” he said, “so we have to fight to make
that case and that we’re value for money.”
Andrew’s ‘catchphrase’ is Putting Passengers First – it was
on the front of the booklet in front of every diner, replacing 2018’s “A better
railway for a better Britain”.
“I make no apologies for being unremittingly relentless
talking about putting passengers first,” he exclaimed, “because I believe it is
absolutely where our future lies.
“All too often, we talk about the system as being congested,
and the system being nearly full, as if it’s a bad thing. But is it? How many
of you would choose to carry a significant amount of spare capacity? Earning
nothing for you, month after month, because your assets are not sufficiently
reliable or because your maintenance practices weren’t up to scratch, or
because your systems and skills were not fit for purpose? And if you did, what
would your shareholders make of it?
“We must stop talking about the railway being full as a bad
thing. It is actually a fantastic thing. It’s an indication of the long-term
economic growth that actually underpins the economy of our country and it’s
what we do. And, as colleagues would have heard me say, I passionately believe
that trend of growth will continue to be strong over the next few generations.”
Safety is another big topic, and Andrew remarked on the
industry’s significant change to worker safety since he has left and come back
to rail: “In the years that I’ve been out of the industry, I’ve seen a complete
transformation in the approach to that, the significant reduction in worker
injuries and fatalities as a consequence. We can do it when we put our minds to
it and, frankly, the supply chain is leading ahead of us in many ways.”
“If we can do it on safety, we can do it on reliability.”
Which brought him back to serving the customer, and Putting Passengers First.
Your host for the evening
One of television’s most experienced, and versatile presenters, Julia Bradbury (pictured below) was the host for the evening. A former presenter of both Watchdog and Countryfile, Julia can currently be seen in her new series ‘Australia with Julia Bradbury’ on ITV, in which she travels 12,500km from the western coast of this giant continent across to the east.
Outside of her presenting duties, she is the current
President of the Camping and Caravanning Club.
“It is wonderful to see you all here tonight, gathered in the
heart of the country, at this amazing venue, to celebrate your achievements,”
she told the audience. She then joked with Andrew Haines, who claimed that,
since he joined Network Rail in August 2018, he had done more public speaking
than she had!
Following dinner, and plenty of conversation between the
audience that filled the room at the NEC’s Vox conference centre, Julia
returned to the stage.
She then spoke about her career in television, where she is
perhaps best known for Countryfile. “Countryfile was an amazing show to work
on,” she said, “and there are too many highlights to recount here – travelling
up and down the country to some of the most beautiful locations, covering such
diverse stories, from county shows to the plight of our crayfish populations in
the UK, under threat because of a ‘crayfish plague’ (carried by the American
signal crayfish).”
Earlier, she presented the consumer show Watchdog on BBC1
for five years with Nicky Campbell, and it was during that time that she became
involved in a four-part series on Alfred Wainwright, and his famous walks
around the Lake District. That spawned a second series, of six episodes this
time, and then Railway Walks.
“The walks followed Britain’s lost rail empire,” she said.
“The first episode explored a route in the heart of Derbyshire – the Monsal
Trail. (This runs along the former Midland Railway line for 8.5 miles between
Blackwell Mill, in Chee Dale, and Coombs Road, at Bakewell.)
“We also went to Cornwall where tin and copper once made the
area around Redruth the richest patch of land in the country. They inspired
great engineering feats and pioneering tramways, the forebears of the rail
empire. I crossed an entire county, winding past Cornwall’s crumbling engine
houses and following a railway that has not operated for 140 years.
“The Railway Walks series inspired many people to head out
walking, and every day we get people heading to my website, The Outdoor Guide,
and downloading the routes. We’re all passionate about getting people into the
great outdoors, sharing outdoor adventures, getting some green therapy.”
All too soon, it was time for Julia’s fascinating
reminiscences to end and for the awards to start.
Sponsors
This year, the evening was sponsored by five organisations, without whom the evening would not have been possible.
Atkins, a member of the SNC-Lavalin Group, is one of the
world’s most respected design, engineering and project management
consultancies. One of very few firms to provide clients with comprehensive
end-to-end project solutions, including financing & asset management,
consulting & advisory, digital & artificial intelligence, design &
engineering, procurement, construction & project management, operations
& maintenance and sustaining capital, Atkins was “delighted to share an
evening with Network Rail, Rail Media and supply chain teams to celebrate the
very best of 2018’s achievements in the rail industry”.
Colas Rail is fully committed to the continual maintenance
and upgrading of the UK’s rail network. Thinking, investing and operating at
the forefront of the industry trends ensures the company has the capabilities
to meet the future demands of its customers. Ian Anderson, managing director of
Colas Rail Urban, said: “Our leadership in this industry is directly linked to
our attention to our customers’ needs, executing effective solutions to meet
and exceed expectations and our talented staff’s dedication to achieving
success.”
RSSB helps the industry work together to deliver a better,
safer railway, so celebrating successful partnerships is something it values
very highly. The next five years are set to be a transformative time for rail,
and RSSB wants to ensure the supply chain can do business with rail unhindered,
but also safely. This is where supplier assurance comes in. The organisation’s
work includes managing industry schemes that provide supplier assurance
services, including RISQS – the Railway Industry Supplier Qualification Scheme.
Total Rail Solutions is investing in the future. The
on-track plant hire specialist was the subject of a management buy-out last
November and, under new CEO Paul Bateman, is continuing to invest heavily in
the three areas which it considers its operational enablers – its plant, its
people and its processes. “The focus for the next six to 12 months is to be
looking at the business and professionalise things,” Paul Bateman explained.
“That means introducing new systems to enable us to upscale, with a big push on
recruitment too, but all while trying not to lose the company ethos that has
got us to where we are today.”
VolkerWessels UK is a leading multidisciplinary contractor
that delivers innovative engineering solutions across the civil engineering and
construction sectors, including rail. The skilled teams in its VolkerRail and
VolkerFitzpatrick businesses are recognised as sector leaders, delivering high
quality projects through a safety conscious and collaborative approach.
VolkerWessels UK said it was proud to sponsor the Rail Partnership Awards,
highlighting its commitment and contribution to the industry, and recognising
the efforts of those who dedicate their career to improving the national
network.
Best Collaboration
Jo Kaye, who is managing director of Network Rail’s System
Operator, joined Julia on stage for the first award. She had judged the
category alongside James Brewer, head of rail supply chains at the Department
for Business, Energy & Industry Strategy.
Between them, they had selected the Buckingham Group Contracting as the winner for its work on the Liverpool Lime Street station upgrade.
Delivered by a fully integrated team, applying ISO44001
principles and working from a bespoke co-located project office, the
£148-million Liverpool Lime Street upgrade project provided increased platform
capacity by reconfiguring and improving asset condition within the 1.5-mile
approach and 24-metre deep footprint of this Grade 2 listed station.
The project was a key regulatory milestone for the Northern
Hub and Great North Rail Project programmes, that was undertaken whilst
ensuring Liverpool was ‘kept open for business’.
Collaboration was key to the successful delivery of the works, with all parties working as one team to deliver the project under a hub and spoke arrangement. The ‘hub’ was led by Network Rail IP Signalling (The Client). The key stakeholders were Buckingham Group (principal contractor under CDM), Buckingham Group (civil engineering contractor), IP Northern Programmes (programme management), S&C North Alliance (track and OLE contractor) and Siemens (signalling contractor).
Amey, Atkins and Siemens, on behalf of the Rail Supply
Group, were highly commended for the Rail Sector Deal – launched by government
as a process to create partnerships between the government and industry on
sector-specific issues that can create significant opportunities to boost
productivity, employment, innovation and skills.
So too were Siemens Mobility and Galliford Try for the Derby
Area Remodelling Project, a major £200 million enhancement and renewal
programme that was successfully commissioned on 8 October 2018, following the
completion of a 79-day partial closure – the longest continuous partial closure
ever undertaken in the UK.
Investing in People
Alison Rumsey, group HR director of Network Rail and
attending the event on her last day working for the company, came on stage to
make the award for Investing in People. Her fellow judge, San Johal, HR
director of Highways England, has also recently changed jobs.
This category recognises suppliers that have created an environment that promotes accountability, opportunity and diversity. In the judges’ opinion, Story Contracting’s Fit4Future business strategy was the best example from the entries.
When the company was founded 30 years ago by Fred Story, he
had just three colleagues working with him on a variety of projects in and
around Carlisle. Today, the company employs over 700 local people across the
UK, delivering a wide range of rail, civils, housing and manufacturing
projects.
Story Contracting recognises that it is successful because
of the skills, commitment and professionalism of its people, who define its
uniqueness and ability to deliver the high level of service and quality
demanded by its growing customer base. As the business expands further in
Cumbria, Yorkshire, Birmingham, Manchester and Scotland, investing in people,
and encouraging them to achieve their full potential, is a critical part of the
company’s Fit4Future business strategy to keep this growth going.
GB Railfreight was highly commended for its Seat to Seat
training programme. Four trainee drivers, with no previous experience in the
railway industry, underwent training at the company’s recently renovated
Peterborough facility, which houses three high tech classrooms and, in 2018
alone, delivered 60 trainee drivers. Once trained, they would be driving in the
London area, based out of GB Railfreight’s Willesden facility in North
London.
Diversity and Inclusion
Recognising suppliers that can evidence success in
initiatives which recognise and respect differences between people whilst valuing
the contribution everyone can make to the rail industry, winners in this
category had to demonstrate inclusion and evidence safe and welcoming
workplaces and fair cultures that encourage innovative and fresh ways of
thinking.
Once again, Alison Rumsey judged this category for Network Rail, joined this time by Chloe Chambraud, gender equality director for Business in the Community.
Babcock’s ‘Being Babcock’ training programme was developed
to help the company understand some of the cultures and behaviours within its
business and the actions that can be taken, as individuals as well as a
business, to address diversity bias and discrimination in the workplace.
Employees were invited to complete e-learning training and
attend a half day workshop to address the subject of Respect, with a particular
focus on a zero-tolerance approach to inappropriate behaviours and the end to
discrimination in the workplace. The judges were impressed by this initiative
and gave it the Diversity and Inclusion Award.
Capita was highly commended for its 20by20 campaign, to help
Network Rail employ 20 per cent more women by 2020. To do this, Capita’s aim in
2018 was to change people’s attitudes and perceptions towards working within
railway and infrastructure and to communicate the opportunities and benefits of
working within the sector, and in particular with Network Rail.
Babcock had a second success in this category, being highly commended for its Workplace Equality project. In a bid to end mental health discrimination in the workplace, Babcock engaged once again with the Scottish mental health charity ‘SeeMe’ to pilot a project designed to create a more inclusive, stigma-free working environment focused on proactively managing the mental health of all employees.
Safety
Chief engineer Jon Shaw stepped on stage to present the
Safety award. The judges for the category had been Allan Spence head of public
and passenger safety with Network Rail and Johnny Schute, chief operating
officer of RSSB.
Safety should never be taken for granted, and this award highlighted organisations that showed a continuous improvement towards safety within the workplace and on or near the railway.
Colas Rail set about creating a means to gain robust and
constructive feedback from the business on how to improve safety and
sustainability within the industry. From this, the Safety and Sustainability
Challenge was born.
To do this, Colas needed to embed a culture of continuous
improvement and empowerment within graduates and apprentices and instil the
message that their voices are powerful and that they can make a positive change
in improving the safety and sustainability within the rail industry.
The project takes place across all three of Colas’ divisions and spans every office and depot within the organisation. It includes all individuals on Early Careers programmes, including graduates and apprentices.
A consortium of ABB and UK Power Networks Services was
highly commended for having managed to maintain a Lost Time Injury free record
while delivering 27 sub-stations across a 140-mile area, from Berkshire to
South Wales, and working 1,200,000 hours. This is an outstanding accomplishment
considering the nature of the environment in which the consortium’s employees –
the ‘best of the best’ from both companies – work.
Balfour Beatty, principal contractor delivering the
Angerstein signalling renewals project, working closely with Siemens and its
subcontractors, is responsible for managing the interfaces which this
collaboration brings, especially the safety of all those involved. Realising a
clear opportunity to continuously improve on project performance, learning and
embedding lessons learnt during earlier projects, the Angerstein project was
successfully commissioned in April 2019, on time, to budget and without injury
at any point – achieving Zero Harm and sending Everyone Home Safe Every Day. A
result that was well worthy of a Highly Commended certificate.
Community Engagement
Network Rail’s Caroline Murdoch, director of communications, was the next judge invited by Julia Bradbury to make her presentation. Aided by ACoRP chief executive Jools Townsend, Caroline had decided that Story Contracting, which has been working hard to remove the stigma of mental health, would be a worthy winner of the award.
The driver was simple – no-one should have to face a mental
health problem alone. To gain buy-in from staff, Story held workshops with
employees from all levels of its business to identify ways this could best be
achieved. It had to be something sustainable, that would first of all make a
tangible difference to people in the local area, and it needed to be a
long-term commitment to employee wellbeing.
To enable this, Story set up a strategic partnership with
MIND, the mental health charity, which provides advice and support to empower
anyone experiencing a mental health problem. MIND also campaigns to improve
services, raise awareness and promote understanding of mental health.
The project to remove the stigma of mental health at Story
was hugely successful. Wellbeing sessions, which were delivered in-house by the
occupational health team, created a wellbeing calendar, created a network of
mental health first aiders and launch a promotional campaign. The result has
been a palpable change in people’s attitudes towards mental health and sickness
absence reduced by 600 days, equivalent to one day per full-time employee per
year.
Enhancing Lives, a programme delivered by BAM Nuttall in
conjunction with Network Rail, Mott MacDonald and B Keogh Construction, is part
of BAM’s sustainability agenda, led by the culture and diversity team. It
includes education support, working with charities and community groups, work
placements, employment support and training, and helping local businesses and
SMEs to grow. It was also Highly Commended by the judges.
VolkerFitzpatrick was similarly commended for having
volunteered its services to ensure the creation of an extraordinary and
emotionally moving art installation at Aerospace Bristol and the Queen
Elizabeth Olympic Park, Stratford, marking the centenary of the end of the
First World War. The Shrouds of the Somme memorial, designed by artist Rob
Heard, took five years to complete and is a graphic representation of loss and
remembrance for the commonwealth servicemen who fell at the Battle of the Somme
and whose bodies still lie beneath the battlefields in France. For both events,
VolkerFitzpatrick donated, supplied and installed the viewing platforms,
temporary walkways, fencing and marquees needed for visitors. The team also
provided construction advice, planning and the full development of the events’
design layout, ensuring each shroud would be placed with precision.
Preserving History
The category for Preserving the History of the Railway was
judged by two noted heritage enthusiasts, Network Rail chairman Sir Peter Hendy
and Andy Savage, executive director of the Railway Heritage Trust.
Sadly, neither could attend the dinner so it fell to Andrew McLean, head curator of the National Railway Museum, to present the award. To the Ferryhill Railway Heritage Trust.
Working with Network Rail and Babcock Rail, the trust has
recently restored the 70’ Ransomes and Rapier turntable, built in 1906 and
located near Aberdeen, to full working order. Apart from restoring the
turntable, the works included a substantial de-vegetation operation,
replacement of the main-line access railway track to the turntable, replacement
of two sets of points, and general clearance and tidying of the site.
Provision was made for public access (including disabled access)
by the construction of a new footpath to the site, funded by the Common Good
Fund of Aberdeen City Council. The turntable restoration was funded by Historic
Scotland (40 per cent), the Railway Heritage Trust (40 per cent) and the
Association for Industrial Archaeology (20 per cent). The upgrade of the
trackwork was funded by Network Rail.
To date, steam locomotives hauling three charter trains have
been turned. Fourteen more charter trains have been planned for 2019 and 2020.
The public have been able to safely observe the coaling and turning operations,
with a dedicated viewing area being protected by crowd control barriers.
Buckingham Group Contracting was highly commended for its
work on the three-span Runcorn Railway Bridge, also known as the Queen
Ethelfleda Bridge, which was first opened in 1868 and carries the West Coast
main line over the River Mersey and the Manchester Ship Canal. Now grade II*
listed, it required extensive maintenance after 150 years of service. The
project designer, Arcadis, highlighted the deteriorating condition of the
structure plus concerns over the articulation of the structure, caused by the
bearings all being seized so that articulation was made through flexure of the
piers, which had cracked and flexed seasonally as the temperature varied.
Buckingham refurbished the bridge, using both recovered and remade parts, and
replaced the bearings so that the bridge should be safeguarded for the next 100
years.
The other team highly commended was Construction Marine,
working with Arcadis, David France and Metalock Engineering. Following
examination and inspection by Network Rail’s LNE Structures Route Asset
Management team, the footbridge at Thickley Wood, Shildon, was deemed weak in
several key structural areas and without intervention would have had to close.
The multi-span listed structure carries pedestrian traffic over the Darlington
to Eaglescliffe railway as well as the redundant sidings that, when laid down
in 1875 had a total length of 27 miles, making them the largest in the world at
that time. While refurbishing/remodelling the bridge in compliance with its
listed status, close liaison was required with Durham Council and the adjacent
rail museum ‘Locomotion’ in designing and planning the works to achieve the
required outcome.
SME
To recognise the work of its smaller suppliers, often in second or third-tier roles, this award recognises outstanding SME suppliers with annual turnovers of less than £25 million. It was judged by Eoin O’Neill, Network Rail’s commercial and development director, who also presented the award, and Darren Caplan, chief executive of the Railway Industry Association.
The Award went to Senceive, a company of around 30 people
specialising in wireless solutions for geotechnical and structural monitoring,
which has launched two major products/services in the past year. The first is
the Optical Displacement Sensor (ODS) with in-built triaxial tilt meter. This
ODS uses a highly accurate laser to measure sub-mm sliding movements up to 150m
range, whilst at the same time measuring rotation using a triaxial sensor. This
highly precise and reliable device is completely wireless and has a battery
life of approximately 10-12 years.
An even bigger advancement is the launch of GeoWAN, a
wireless platform that offers long-range monitoring at up to 15km range. This
complements the existing FlatMesh system, which is used for dense sensor
distributions. The new GeoWAN platform allows clients to have even more remote
locations, such as those in Australia, and also has the ability to penetrate
through buildings, which is ideal for urban environments and buried equipment
geotechnical sensors.
ATL Transformers was highly commended for supporting Network
Rail in its copper-elimination, Class II safety and sustainability charter
initiatives to reduce carbon emissions. ATL engaged with the industry to define
the requirements specific to magnetics, to find a solution and to deliver that
solution to Network Rail while, at the same time, further beneficial
enhancements that could be engineered into the product solutions presented.
Driving Efficiencies
This category recognises companies that have made strides in designing and delivering work more efficiently, to generate cost savings and value for money to create a more efficient railway. Network Rail chief financial officer Jeremy Westlake and Graham Richards, director of planning and performance for the Office of Rail and Road, were the judges for this one.
They decided to recognise Great Western Railway in this
category, supported by Network Rail, Oxford University, Incremental Solutions
and Icomera. Although electrified railways offer huge customer experience,
operational and environmental benefits, the costs and challenges of operating
and maintaining them can be significant, particularly when things go wrong.
As an example, the Schedule 8 cost of OLE and pantograph
incidents on Network Rail’s Western route for the last 12 months was £5.5
million, with 750 trains failing to arrive within the allotted time. To address
this, OLErt is a ground-breaking project that exploits imaging from the cameras
that are fitted as standard to all new electric trains to enable early
interception of potential faults. Based on cutting-edge research by Oxford
University, developed through collaboration between Great Western Railway (GWR)
and Network Rail, this new technology helps to avoid potential disruption to
the train service and will benefit passengers, train operators, infrastructure
managers and the tax payer.
Currently deployed on a Class 387 unit running in the Thames Valley, OLErt has successfully demonstrated how image recognition technology can be used to monitor the OLE and pantograph interface, enabling the early intervention that prevents potential faults turning into failures.
Staying with an electrification theme, Alstom was highly
commended for its work to reduce the cost of rail electrification projects and
increase efficiency. This initiative looked at developing the optimum solution
for installing 25kV overhead line contact and catenary systems, using efficient
equipment and processes, within an operational possession regime, to achieve
unrivalled production rates in UK electrification, showing the rail industry
that electrification can be undertaken cost effectively and efficiently, and so
removing the stigma around the cost of electrification.
Also highly commended was the way in which VolkerRail and
Unipart Rail have transformed overhead line electrification by developing new,
innovative solutions around pre-fabrication build, facilities and tracking of
over 250,000 multi-assets. A step-change in material fabrication, installation,
delivery and traceability capability was needed to ensure the successful
installation of over 1,100 overhead line structures and over 200km of overhead
line cable between Preston and Blackpool within an 18-month period, and the
complete overhead electrification installation needed at Blackpool depot.
Together, VolkerRail and Unipart Rail used existing systems and dedicated
facility solutions from previous projects to develop a plan to open a
pre-fabrication facility in Crewe, which would house all materials and
pre-fabrication requirements.
Technology
Aidan Hancock, chief information officer for Network Rail, presented the award for Best Use of Technology, judged by Route Services managing director Susan Cooklin and Professor Phil Blythe, the chief scientific adviser to the Department for Transport.
The award went to the Cambridge Centre for Smart
Infrastructure and Construction, along with AECOM, Network Rail and the Alan
Turing Institute, for the development of innovative Structural Health
Monitoring (SHM) systems that combine high-end sensing technologies with ‘big
data’ analytics, providing effective asset management tools for better
maintenance, protection, and operation of ageing railway bridges.
Roughly 50 per cent of bridge stock is ageing masonry arch
bridges, most built over a century ago, before the enforcement of building
codes, and their condition continues to deteriorate with time. Working on two
bridges in Yorkshire, the team was able to test and compare new smart-sensing
technologies and explore optimum configurations. Over time, these can be
developed into structural alert systems, moving towards a digitised railway
with smart infrastructure.
Great Western’s OLErt system, already a winner in the
Driving Efficiencies category, was highly commended for best use of technology.
Also highly commended was WSP, which worked with fixed-wing
UAV (drone) specialist SenSat to survey an area of rail, road, crossings,
greenfield and urban spaces. Due to the complexity of the site, and to
compressed timescales, a conventional survey would have taken too long.
However, this novel use of UAV technology reduced to two months the delivery of
a survey that would typically have taken five.
Major project – over £50 million
Mike Putnam, a non-executive director of Network Rail, joined Julia Bradbury on stage to present the first of two project awards, this one for projects valued at over £50 million. Mike had judged the closely competitive entry with Alasdair Reisner, the chief executive of the Civil Engineering Contractors Association (CECA).
The winner was Siemens Mobility for the Derby Station Area
Remodelling Project, a £200 million scheme that included a 79-day partial
blockade of Derby station, the longest continuous partial closure ever
undertaken in the UK.
The project represented a ‘once in a generation’ opportunity
to replace and upgrade the life-expired infrastructure and bring enhancements
and improvements both to the station and its approaches. It is already
delivering a range of significant benefits to passengers, train operators and
the infrastructure owners and maintainers.
Highly commended was the Brighton Main Line Improvement
Project – an extensive £67 million engineering programme, carried out in
partnership by Network Rail, the UK Government and Govia Thameslink Railway
(GTR), to improve the reliability of the railway as part of the Thameslink
Resilience Programme. The work took place between September 2018 and May 2019
and focused on an area at the southern end of the Brighton main line, from
Three Bridges to Brighton/Lewes, where four Victorian tunnels (Balcombe,
Haywards Heath, Clayton and Patcham), ageing track and signalling systems were causing
almost half of all delays experienced on trains entering the southern end of
the Thameslink Core.
Despite its bad press, also highly commended were the teams
working on Great Western Electrification. The Amey, Amey Inabensa and Network
Rail teams, working with Keltbray Aspire and Lundy Projects, have delivered
transformational improvements to rail service capacity and performance between
Maidenhead and Westerleigh junction and Reading to Newbury. A staggering 134
track miles of OLE installation has been constructed across a number of
distinct programmes in an array of disciplines.
Smaller project – under £50 million
The same judges had reviewed the entries for projects under
£50 million, which can sometimes be overshadowed by their bigger siblings but
are nevertheless still vital to the railway’s wellbeing.
Eoin O’Neill, Network Rail’s commercial and development director, had the job of opening the envelope to reveal that BAM Nuttall had scooped this one for the upgrade of the Highland main line.
A programme of infrastructure improvements, undertaken in
2012 during phase one of the project, increased the number of services from
nine to 11 trains per day in each direction.
BAM Nuttall was awarded a £10.3 million contract, as part of
Phase Two of the scheme, to deliver enhancements at Aviemore and Pitlochry
stations. These enhancements will deliver an hourly service with average
journey times reduced by around 10 minutes, alongside other timetable
improvements.
In simple terms, the project benefits are delivered through
three strands: station and track enhancements delivered by BAM Nuttall, an
overhauled signalling system delivered by Siemens and ScotRail’s revised
timetable that brings more trains through Pitlochry and Aviemore than ever
before.
Atkins’ Cornwall capacity enabling scheme was highly
commended. It provided an additional 10 signal sections (21 new signals and
associated signalling equipment), and seven level crossing upgrades, to enable
the Department for Transport and Cornwall Council (a project funding partner)
to meet their aspiration to run an additional hourly train service from
Plymouth to Penzance from May 2019.
Highly commended, too, was Morgan Sindall’s involvement with
the Stirling-Dunblane-Alloa (SDA) project that formed part of a wider Scottish
Government rolling programme of electrification works being delivered by
Network Rail. Under SDA, Morgan Sindall’s rail and electrification team in
Scotland undertook a £37 million package of works on a route that spanned 50km,
starting at Falkirk in central Scotland and up to Dunblane in Stirling and
Alloa in Clackmannanshire.
Sustainable Excellence
Jon Shaw, Network Rail’s chief engineer, and Professor Miles Tight of the University of Birmingham collaborated to come up with a winner of the Sustainable Excellence award, which is open to organisations that can clearly demonstrate sustainable and responsible ways of working. It can cover anything from working effectively with lineside neighbours through to carbon off-setting and reduced waste and recycling innovations.
The award went to AmeySersa and the S&C North Alliance,
which are working on improving freight routes in Scotland. Combining their
expertise and knowledge, they improved collaboration and joint accountability
by developing innovative solutions, adopting engineering excellence, sharing
best practice and common policy on key strategies, all while successfully
tackling the most complex projects.
In Scotland, that means working closely with Transport
Scotland’s strategy to deliver a safe, efficient, effective and sustainable
transport system, for both passengers and freight, supporting sustainable
economic growth and by transporting products and materials in a greener way.
Buckingham Group Contracting continued its excellent record
for the night by being highly commended for extending the Up Relief Sidings at
Buxton, allowing 525-metre-long freight trains to undertake the run around
manoeuvre required to egress to the Peak Forest Line. This required extending
the sidings through a disused unlicensed council tip, which dates back to the
1970s, and into privately owned farmland.
Skanska’s Sustainability Performance Tracker, which it is
using on its ONW (on-network works) contract for HS2 enabling works at Euston,
was also highly commended. Skanska is working with Network Rail and other
stakeholders to ensure Euston station is ready for the arrival of HS2. To
ensure that sustainability excellence has been considered and achieved across
all of the work packages from the design through to construction, a team of
engineers and sustainability professionals produced a tracker which, to date,
has identified over 41 sustainable initiatives.
Standards Challenge
This year’s new award, for entries into Network Rail’s Standards Challenge, was judged by Jon Shaw and HS2 technical director Andrew McNaughton.
The winner was British Steel, a company which has had its
problems recently, for its challenge to the standards for OLE mast design. This
identified that some current overhead line mast standard designs are
fabrication intensive, may use higher cost products and may require structural
steel that is not produced / stocked domestically within the UK.
An industry workshop was held in December 2018, with British
Steel and other suppliers, to discuss potential changes to standard designs
resulting in the identification of short, medium and long-term proposals. The
short-term proposals have been progressed into new standard designs. In the
case of Twin Track Cantilever masts the new design will reduce the cost by
around seven per cent.
Two other challenges were highly commended. Kwik-Step
submitted three challenges, all relating to the standard for Lineside
Facilities for Personnel Safety, which dates back to 2005, and the need for
improved clarity relating to a number of requirements. Kwik-Step has provided
excellent input on how this standard can be improved.
Train operator Grand Central has challenged the controls
that are applied to trains following measurement of forces at Wheel Impact Load
Detection (WILD) sites. In response to this challenge, Network Rail conducted a
detailed technical study and the resulting technical report is currently being
peer reviewed. It may enable the speed restrictions that are imposed for
certain train types following a Level 2 alarm to be raised to a higher speed,
benefitting train operators and improving the consequential impact on train
performance.
Putting Passengers First
Andrew Haines’ catchphrase has become a Partnership Award
category, judged by Network Rail’s managing director of transformation, Becky
Lumlock, and Paul Plummer, chief executive of the Rail Delivery Group.
This award was established to celebrate suppliers who have put the needs of rail passengers at the heart of what they do and can demonstrate that they are genuinely putting passengers first.
Buckingham Group Contracting’s name came out of the hat
again, this time for the Liverpool Lime Street station upgrade. This £148
million project was wholly about putting passengers first, from the main
driver, which was to increase capacity to enable the doubling of passenger
numbers to more than 32 million per annum by 2043, to enhancing the passenger
experience through improved concourses plus new and extended platforms to
facilitate more frequent reliable services and longer trains.
People using Lime Street were 93.8 per cent satisfied,
according to the National Rail Passenger Survey published in January 2019,
putting the Liverpool station ahead of both St Pancras (93.6 per cent) and
King’s Cross (92.9 per cent).
Amery Sersa and the S&C North Alliance also did well,
highly commended for high-speed handbacks. A collaboration between Network
Rail, Amey and Rhomberg Sersa, the S&C North Alliance has spearheaded the
initiative to hand back at line speed following major track renewal
interventions. Work sites have been handed back at speeds of up to 125mph, a
world first. Crucial to this achievement are various techniques to fully
consolidate the track during construction, which means it no longer requires
the passage of trains to do this.
Osborne received the second Highly Commended certificate for
its use of virtual reality (VR) at stakeholder events. Combined Building
Information Modelling (BIM) technology with Virtual Reality equipment makes
design solutions accessible to a wider range of stakeholders, helping those who
would never have usually commented on a scheme see how it would impact them,
and offer their opinions on the solution.
Supplier of the Year
So that was it for the individual categories. All that
remained was the big prize, the coveted Supplier of the Year Award, to be
presented by chief executive Andrew Haines.
He joined Julia on stage to announce the winner. Everyone present was a winner in some way – they were all on the short list, many had won or been commended for their work in the individual categories, and together they represented the cream of Network Rail’s suppliers.
So, without further ado, and without too much of a shock
considering the results of the other categories, Andrew Haines announced that
Network Rail’s Supplier of the Year was Buckingham Group Contracting.
Two category wins and one highly commended had sealed it,
and it was an impressive performance from a company that had won the same
overall award in 2015.
Fergal Kiernan, senior project manager at Buckingham, said
afterwards: “Buckingham Group, for the last two years, has been top of the
charts with regards to the KPI performance. That’s down to the dedication of
the teams and a number of people who are assigned to manage and coordinate the
KPI process for us, and that was testament to the excellent job they’ve done.
“Buckingham has, over the last two to three years, delivered
a huge amount of work for IP Signalling and for the various rail contractors,
and I think receiving the award is a really, really pleasant surprise. Our rail
director Simon Walkley, who couldn’t be here tonight, will be absolutely
chuffed.”
Although a number of new train fleets have been introduced
onto the British rail network in recent years, with more still to come, they
haven’t all met with universal passenger approval. Some have described the
seats as “ironing boards”, a reference to their comparative hardness. Others
have observed that the initial impressions might lead one to think that the
seats are hard, but in fact they remain comfortable after a long journey.
After a safe and punctual train, seats are probably the most
important customer requirement, but, with people coming in all shapes and
sizes, and journeys being for a variety of purposes, customer requirements for
seats would not come into the category of “one size fits all”.
In days gone by, the importance of seats would be inferred
by a requirement that seat comfort be judged by the managing director and his
(in those days it was inevitably a man) directors – a process that survived
until at least the 1990s.
More recently, enlightened project directors have organised
customer clinics and provided the seats that the customers liked most.
Less-enlightened project directors have bought the cheapest seats compliant
with the various requirements (that do not include comfort).
Then there must be a special mention for project directors
who organise a customer clinic but then buy the cheapest compliant seat,
irrespective of the result of the clinic.
Compliance is everything, and modern trains must comply with
the interoperability regulations. In the case of seats, train buyers have to
ensure that the seats meet some pretty basic ergonomic requirements, show they
are strong enough in service and in a crash, and meet stringent fire safety
requirements.
Moreover, a train operator’s franchise agreement might require
a particular number of seats to be operated into and out of key nodal points at
specified times. Comfort might be an objective, but without means of
measurement.
Claims have been made that compliance with fire safety
standards leads to hard seats, others disagree.
The result has been a large number of complaints about
so-called “ironing board” seats, and recent customer satisfaction scores show
seats (at 67 per cent) fall a long way short of overall passenger satisfaction
(at 83 per cent).
All this led to RSSB commissioning research into seat comfort, with the aim of producing objective criteria for assessing seat comfort and, hopefully a standard against which compliance may be measured. If customers dislike the seats on a new train when this process is in use, it will be easy to see whether the specifier has been too undemanding or whether the seat supplier has failed to comply.
Comfort factors
RSSB Research Project T1140 “Defining the requirements of a seat comfort selection process” was initiated in February 2018 and the final report was delivered in May 2019. The work was carried out by Arup and the Furniture Industry Research Association (FIRA).
The report highlights that “quantifying seat comfort is a complex area that depends on the human, the product and the environment…comfort can be defined as ‘an absence of discomfort’ and so discomfort is sometimes easier to quantify”. Putting this into a mouthful of other words, the different shapes and sizes of passengers, and the activities they perform whilst sat in the seat, together with the shapes and sizes of seats, seat pad compression, variations in journey length and train vibration, can and do affect feelings of comfort.
The project set out with a literature review which was used
to help define minimum seat comfort requirements, to develop a seat comfort
test methodology and seat comfort scoring system and, finally, to test and
validate the proposals.
The report identified ten factors; seat dimensions,
passenger anthropometry, passenger activity, train seat arrangements, static,
dynamic and temporal factors of comfort, psychosocial factors of seat comfort,
seat durability, international best practices regarding seating, seat
‘accessories’ such as folding tablets, power sockets, and ancillary items that
effect the passenger seating area and legroom such as tables, possible future
train seat design scenarios which, together with Arup’s and FIRA’s background
knowledge and experience, were used in the subsequent stages.
The project team worked on the four key factors that
influence seat comfort. Firstly, the journey type, as passengers expect
different comfort levels on different types of journey. For example, people may
tolerate a lower level of comfort on a short journey compared with a long one.
Secondly, the dimensions and weight of people with the
objective of determining minimum dimensions suitable for the majority of the
population from large to small.
Thirdly the seat pad, as most of the complaints about seat
hardness come about when people first sit in the seat and find the seat pad to
be unyielding. The pad thickness, hardness and durability are important
factors. Indeed, if a seat pad looks reasonably thick but feels hard the
impression of discomfort might be increased. For a comfortable seat the pad
must provide enough compression for lighter people and enough support to
prevent the pad “bottoming out” (sorry!) for heavier people.
Finally, seat accessories such as armrests and tables are
valued by customers and were included in the process.
Results
As people and their journeys vary so much the report
recommends a number of seat factors be evaluated for each category of journey
defined.
Journey types
Four types of journey were identified – metro, regional,
inter-city and first class/very high speed. For each journey type, a comfort
rating scale was proposed, made up of four attributes; seat dimensions, seat
pad requirements, seat attractiveness and seat accessories. Each of these
attributes is described in turn.
Seat dimensions
The report proposes minimum seat comfort dimensions to ensure that a seat’s features such as seat depth and legroom will fit the majority of the UK population. People’s sizes were defined from “BS EN ISO 7250-2:2013 Basic human body measurements for technological design, part 2: Statistical summaries of body measurements from national populations” and a test method was designed using a weighted chair measurement device, to be used in accordance with “ISO TR 24496:2017 – Office furniture – Office work chairs – Methods for the determination of dimensions”.
A number of dimensions were specified; either pass/fail or
varied by type of journey. These included seat height, depth and width,
backrest width and armrest height, the position of the headrest, legroom and
the angle of the seat itself. Figure 1 shows the dimensions and scores for the
four journey types.
Seat Pad Requirements
For the seat and back pads, the following attributes were
specified – seat pad minimum thickness, seat back minimum thickness, seat pad
hardness with 500N load, seat pad hardness with 1100N load and long-term seat
durability. Figure 2 shows the full table.
Although there are only five requirements, this is probably
the most difficult set to deliver a good score, as an appropriately ‘soft’ seat
that scores highly on the compression test might not perform so well on the
durability test.
Seat Attractiveness
This attribute takes account of the complex nature of determining comfort. It is a qualitative, survey-based measure, and is intended to help a train operator decide which seat to choose from candidates that have passed the dimension and compression tests. The three attributes are:
How comfortable does the seat look?
How attractive is the seat?
How comfortable is the seat to sit in?
What does this all mean in practice?
There is a total of sixteen objective measures and three
qualitative measures. Minimum requirements are listed in figure 3. For the
eleven seat dimensions alone, the fail criteria and the maximum scores for each
of the four journey types are shown in figure 4.
As an example, the maximum score for a Regional train is
25.5 and, as part of the evaluation, three sample seat types were compared,
shown in figure 5. It is interesting that one seat is a clear winner, but even
this good seat might still fail if the seat pad requirements were not delivered
or it was disliked in the qualitative assessment.
Neither spacious seats with poor padding, nor well padded but cramped seats are acceptable.
Conclusion
When this project was commissioned, its objectives were to:
Define minimum (baseline) requirements for train
seat comfort;
Create a seat comfort test methodology with
scoring system that allows TOCs, ROSCOs, seat manufacturers and seat suppliers
to test and score a range of seats for comfort;
Test and validate the requirements;
Improve seat comfort on UK trains.
In addition, the seat comfort specifications, testing and
scoring methodology had to be robust and credible and to be accepted by the
rail and train seating industry. The requirement is not intended to be a
barrier to new innovative seating solutions, but to promote it.
Many were sceptical that objective criteria for seat comfort
could be set, and it is laudable that a practical system has been developed in
a little under over a year. It remains to be seen how well this works in
practice, but any reasonable review of the requirements shows that some
significant improvements will be made if the requirements are indeed
incorporated into the Key Train Requirements document and hence into contracts.
Your writer wonders, however, whether any operator would
have the courage to specify seat comfort values at the bottom end of the ranges
suggested for the various duties and, indeed, whether some of the minimum
dimensions specified spell the end of 3+2 seating on future UK size rolling
stock?
Further, do these requirements help resolve the situation
where legroom is compromised because body side heaters encroach into the space
of window seats?