A strong strategy needing a broader view
It is good to see the publication of Great British Railway’s (GBR) ‘Rolling Stock and Infrastructure Strategy (RSIS)’ which has much to be commended. This recognises the need for a stable long-term rolling stock investment pipeline of standardised fleets. It also commits to level boarding, moving away from diesel traction, and greater infrastructure monitoring by passenger trains. RSIS also describes how GBR’s new train fleet management function will take an integrated approach to depots and train maintenance.
While these positive aspects must be recognised, the RSIS does not entirely deliver GBR’s expressed commitment to whole system engineering. For example, Battery Electric Multiple Units (BEMUs) are its principal solution for diesel unit replacement.
As explained in our feature on the BEMUs procured for TransPennine Express (TPE), BEMUs have significant additional operational and capital costs. They also require very large batteries if they are to operate at higher speeds at which the power needed by a train is broadly proportional to its speed cubed. Hence, 100mph BEMUs require over twice the power of a 75mph train.
Although BEMUs may be the right solution for TPE, a network-wide approach may well show that full electrification offers the increased capacity and lower whole life cost. This is most likely to be true for routes with InterCity and freight traffic. Scotland’s fleet strategy takes this approach while acknowledging that BEMUs could provide a transitional solution.
The RSIS recognises that there needs to be an expansion of the electrified network while emphasising the need to improve electrification delivery. Yet it doesn’t commit to a rolling programme of electrification which is the best way of doing this.
A significant omission is a strategy to resolve network capacity limitations. Although ETCS’s capacity benefits have been widely promoted, the reality is that on a mixed-traffic railway it only offers minor capacity benefits. This is because, for such routes, ETCS cannot address the far more dominant constraints of infrastructure configuration and a mix of trains with different performance and stopping patterns.
While RSIS expects ETCS to reduce whole-life cost, its implementation is proving to be costly. Though RSIS acknowledges high rolling stock retrofit costs, it does not mention the cost of ETCS fitment to new trains which industry sources advise is around £0.5 million per train. Furthermore, the rebaselining of the East Coast Digital Programme indicates increased expenditure since its £1.9 billion cost was announced in 2024.
On routes with significant freight flows, there are large potential capacity gains from 90mph electrified intermodal freight trains. This is because, from a timetabling perspective, such trains behave like 125mph stopping passenger trains as our ‘Engineering Freight Growth’ feature explains.
In this respect RSIS falls short of a whole-system approach as it is only concerned with passenger trains. Hence this capacity benefit for both passenger and electric freight trains is not considered. Yet, increasing electric freight traction could well be the most cost-effective way of increasing capacity on mixed traffic routes with heavy freight flows.

As Malcolm Dobell describes, the need for whole system thinking was emphasised by the new Chair of the IMechE Railway Division, Matt Prosser, in his Chair’s Address. This includes gauge-clearance and the need to fund adhesion mitigation. He also explains the complexity of battery trains which he considers to be suitable for lower-frequency, non-freight routes. He also stressed the capacity benefits of electric freight trains.
Our feature on Irish rolling stock describes how Irish Rail has the capability for whole-life maintenance, including heavy overhauls, for all its trains. RSIS is considering the option of GBR owning its own trains as well as a fresh approach to train maintenance. It will be interesting to see whether GBR considers this Irish whole-life train stewardship model.
However GBR is organised, within its large complex rail network it will always be difficult for those focused on one part of it to make the best whole system decisions. The Chartered Institution of Railway Operators (CIRO) proposes how this can be addressed in their ‘Locally empowered, nationally coherent’ policy document. Although this paper concerns railway operations, much of it will be applicable throughout GBR.
In respect of signalling, Kevin Chivers considers the safety integrity of staged signalling control transfers from relay interlockings to computer-based interlockings to explain how this can be ensured by a proportional SIL-Allocation Method. Assurance arrangements to ensure systems integrity are part of Paul Darlington’s feature on the potential cause of the recent communications failure at the Manchester Rail Operations Centre which caused massive disruption.
The development and operation of Train Protection and Warning System (TPWS) is considered by David Fenner. He explains that, while TPWS has dramatically reduced instances of signals passed at danger, it has its limitations. Derailments caused by track distortion were also very rare until there were two on consecutive days recently. With ever hotter summers, we consider mitigation for track buckles in hot weather.
As Graeme Bickerdike reports, over a thousand people recently had the chance to walk through the closed Greenside railway tunnel between Leeds and Bradford to demonstrate how this could be part of an active travel route. Putting such historic structures to good use is a great idea. The 1846-built Bridge 42 is certainly put to good use carrying the heritage North Yorkshire Moors Railway. Yet, to continue to do so its arch needed to be propped prior to a permanent repair as Bob Wright describes.
Non-Destructive Testing (NDT) on heritage railways is the subject of a feature by Clive Kessell. This describes the challenges of mandatory steam boiler inspections and novel NDT techniques to reduce their cost and complexity.
The complex interactions between the different work packages undertaken during the recent 22-day Hungerford Bridge blockade are considered by Mark Phillips. His feature explains how the success of this blockade was largely due to the meticulous planning which was the result of the integrated approach taken by the Southern Renewals Enterprise.
We also feature the complex Transpennine Route Upgrade (TRU) programme with an update on its sustainability and environmental achievements. Our report shows how TRU has added social value, funds carbon reduction, is achieving a net gain in biodiversity and spent £405,507 on community projects.
Finally, we remember Don Heath who directed delivery of the seven-year East Coast Main Line (ECML) electrification project almost exactly on time and to budget. The ECML electrification is his legacy. Yet, sadly, the legacy of later poorly-managed schemes was Government not trusting the industry to deliver cost-effective electrification.
With more recent schemes delivered in a cost-effective manner, helped by initiatives to reduce electrification costs. It is to be hoped that trust in the industry’s ability to deliver can be regained.
Image credit: Alstom
BEMUs for TPE
Secretary of State for Transport Heidi Alexander MP visited Alstom’s Litchurch Lane works in Derby on 11 September to announce contracts worth more than £1.2 billion for 29 new five-car Battery Electric Multiple Units (BEMUs) for TransPennine Express (TPE). The trains will be built at Derby and financed by Rock Rail. They will be the UK’s first mainline BEMUs. A key feature is that they will offer level boarding.
These contracts are for a rolling stock order worth approximately £800 million and maintenance agreements worth around £200 million. The cost of these trains is not clear as the rolling stock order includes the provision of charging facilities at Saltburn, Scarborough, and Hull as well as depot facilities. The maintenance contract, which will support over 100 jobs, will run for an initial eight-year period with the potential for a further eight-year extension.
Alstom’s Adessias
These trains will be the first deployment of Alstom’s Adessia Stream platform in the UK. Alstom advises that this is the result of a £35 million three-year development programme to adapt the Adessia platform for the UK.
Alstom’s website describes the Adessia platform as “state-of-the-art high-floor multiple units”. Hence it seems likely that a significant part of this development work was designing a unit with a constant floor height close to the UK standard platform height to provide level boarding at every door. This would have involved repackaging underframe equipment such as transformers and traction equipment. As we describe elsewhere in this issue, the BEMUs that Alstom have built for Dublin’s DART+ offer level boarding and have roof-mounted battery packs.
With a floor height of around 915mm and an extendable ramp, these trains will offer unassisted boarding at 85% of existing UK railway station platforms. To ensure level boarding at all TPE stations the TransPennine Route Upgrade (TRU) is adjusting platform heights at 19 stations.

These five-car units will be 121-metres-long and operate at speeds of up to 110mph. They will provide around 300 seats, including those in the first class area, and will have catering facilities.
Each train will also have three dedicated wheelchair spaces, two accessible toilets, family-friendly areas, and buggy storage. They will offer passengers modern amenities including Wi-Fi, air conditioning, power and USB-C charging at every seat, enhanced luggage provision, real-time passenger information systems, CCTV, dedicated cycle storage, and quieter, more comfortable interiors.
TPE advises that indicative routes for these trains are between Liverpool and Scarborough, Manchester Airport and Saltburn, as well as between Manchester and Hull. They will displace Class 185 Diesel Multiple Units (DMUs). TPE confirms that several of these units will be retained for the Liverpool-Manchester-Sheffield-Doncaster-Grimsby-Cleethorpes route.
The procurement of these trains is great news for Alstom’s Derby Litchurch Lane plant where they will be built. Alstom UK Managing Director, Rob Whyte advises that this investment will safeguard more than 350 highly skilled jobs in Derby and over 5,500 roles across the UK supply chain.
Manufacture of prototype units will commence in 2028. However, series production will not start until these prototypes have been tested and validated. For this reason, it is expected that these trains will not enter service until December 2034. Though some commentators have commented on the length of time it will take to get these trains into service, this programme has clearly taken account of recent difficulties introducing new train fleets.
Whyte reinforces this point by stressing that this approach avoids the rework and retrofits that have caused problems during recent UK fleet introductions. He advises that the programme is well thought out, risk based, and can be accelerated if development and infrastructure commissioning allow.
He advises that another reason for this lengthy programme is that TRU infrastructure upgrades, including electrification, need to be completed for these new trains which should not be parked in fields waiting for the infrastructure to be ready for them.
TRU infrastructure works
The TRU programme will fully electrify 112km of the route between Manchester and York. It has already electrified about 25% of this route between Manchester and Stalybridge and between York and Church Fenton.
TRU’s other work includes the installation of digital signalling, additional passing loops, additional tracks, a grade separated junction at Ravensthorpe, and improvements at 23 stations.
The programme aims to reduce journey times by up to 10 minutes between Manchester and Leeds and up to 14 minutes between Manchester and York, while boosting capacity by about 30% which includes 15 extra freight paths with tunnels gauge-cleared for intermodal trains.
The programme has a current workforce of about 5,000 and is expected to have cost £11.5 billion by its estimated 2034 completion date.
Whole system engineering?
The formation of Great British Railways (GBR) should enable a whole system view to be taken to derive the optimum whole life cost rolling stock / infrastructure solutions. The BEMUs ordered for TPE will run under battery power on non-electrified lines to Saltburn, Scarborough, and Hull for respectively 53, 67, and 67 km.
While the use of battery traction in this way may be appropriate, Rail Engineer was interested to know how the Department for Transport (DfT) has confirmed that battery trains are the optimum solution before authorising this contract for these trains. Hence the DfT press office was asked how the choice of BEMUs rather than electrification was justified.

Its response was that TPE or Network Rail should be contacted for this information. It was then pointed out that the DfT should have this information to justify the £1 billion spend on these units. However, there was no further response from the DfT despite emails and phone calls chasing this up.
In the absence of a response from the DfT, Rail Engineer made an indicative assessment of the costs and benefits of this BEMU procurement and the alternative of EMUs and electrification as shown below.
Estimated maximum cost of new depot and charging infrastructure at three sites from previous contracts to be £200 million. If so, TPE BEMU vehicle cost is 600 / 145 = £4.1 million
Cost of previous EMU order which was in 2024 for 9 x 10-car Class 345 costing £220 million. With allowance for inflation, cost per EMU car = £2.6 million.
Hence TPE BEMU is £1.5 million per car more expensive than Class 345 EMU.
A large part of this additional cost will be batteries and associated traction and cooling systems. Other reasons for additional costs are level boarding, higher quality interior for long distance services, and 110 mph running. Rail Engineer’s informed guess is that 50% of extra costs are battery related with 25% for the batteries themselves.
On this basis associated battery costs are about £0.75 million per car including £0.4 million for the battery. Industry estimates a battery life of 10 years. Hence, total battery cost per car is around £2 million or £290 million for the complete fleet.
There are also additional operational costs from battery weight, say four tonnes per coach, and higher energy costs due to lower battery energy efficiency.
Electrifying the lines to Saltburn, Scarborough, and Hull would require about 400 single track kilometres (stk) of electrification. If delivered by a steady rolling programme as in Scotland this would cost circa £1 billion.
This electrification would not just benefit these TPE BEMUs. Other passenger operators use these routes and there is also significant rail freight traffic to Hull and Teesside on the Saltburn branch. Operating such freight trains with electric locomotives would increase the capacity of these lines.
Is battery best?
Though the above is very much a ‘back of an envelope’ calculation, it demonstrates that the ‘Battery is Best’ message promoted by the DfT does not address the above issues and is too simplistic.
BEMUs are an appropriate solution in some cases, and the TPE BEMU order may be one such case. Yet the DfT’s refusal to justify this option indicates that the BEMU option has been chosen as a matter of policy rather than engineering analysis.

In this respect it is interesting to compare the DfT’s approach to Scotland’s Fleet Transition Strategy. This considers that electrification is the preferred end-state for InterCity and Suburban routes with freight services. However, it considers that BEMUs are appropriate where there is no freight market or as a transitional measure.
In Ireland, Rail Engineer has reported how full electrification is the preferred solution for the Cork Area Commuter Rail programme which will introduce an intensive commuter service and be Ireland’s first 25kV electrification. This is, in part, due to the electrification cost-saving measures developed by Network Rail.
Scotland’s emphasis on Inter City routes acknowledges the laws of physics. Due to aerodynamic resistance, at higher speeds, these require the power needed to move a train to be proportional to the cube of its speed. Hence at 100mph and 125mph a train requires respectively 78% and 278% more power than at 75mph. This explains why BEMUs are not suitable for 125mph services and that if they operate at 100mph, as the TPE BEMUs can, their battery range is significantly reduced.
Though the £1 billion contracts for these TPE BEMUs to be built at Derby is certainly good news, it would seem that a whole system approach has not been taken. This also begs the question of where, in the shadow of GBR, is the engineering focus to ensure that optimum whole system decisions are taken in respect of infrastructure and rolling stock.
Image credit: Alstom
Remembering Donald “Don” Heath OBE
For railway managers of my generation, Don Heath, who died in August aged 86, was an inspirational figure renowned for his management of the East Coast Main Line (ECML) electrification project.
His project responsibilities were much more than electrification for which the authorised budget was £174 million. It included a £132 million rolling stock procurement of 31 x Class 91, 21 x Class 90 electric locomotives, 282 x Mark 4 coaches and 4 x Class 317 EMUs, as well as complex resignalling schemes at York (£16 million) and Newcastle (£27 million).
The authorised cost of electrification and rolling stock was £306.3 million at 1983 prices. The first electric train between King’s Cross and Edinburgh in 1991 marked the completion of this seven-year programme, which was just eight weeks late and over budget by 4.4%. At today’s prices the total cost of the 1,400 single track kilometres (stk) of the ECML electrification was £0.7 billion or £0.5 million per stk at 2026 prices.
Don wrote a Rail Engineer article in 2017, titled ‘Electrification as it used to be’. This explains how the project was controlled and its innovative solutions. He acknowledged that some aspects were easier 40 years ago. For example, the much lower traffic levels enabled headspans to be installed with a four-track line blockage during the day. There was also no requirement for Environmental Statements.

I had the opportunity to speak to Don after he had been asked to advise the Great Western Electrification Programme (GWEP) project. He told me that no one wanted to listen to him as the senior project team did not consider his British Rail (BR) experience to be relevant.
This hubris resulted in the GWEP being delivered three years late at almost three times its original estimate after a large part of the programme had been cut back. Its electrification was delivered at £3.1 million per stk at 2026 prices.
Despite much good work to reduce electrification costs since then, GWEP’s legacy is that many in Government consider electrification to be the wrong technology and / or that the industry cannot be trusted to deliver it at an affordable price.
Don’s first project management role was at BR for the Picc-Vic rail tunnel under Manchester which was ‘shovel ready’ when it was refused Government spending in the 1970s. He also project-managed West Coast Main Line improvements to allow the ill-fated Advanced Passenger Train to run at 140mph.
After the ECML project, he was BR’s lead on what was then known as Crossrail. After specifying and costing the project, the Treasury considered it was unaffordable. However, Don safeguarded this work which became the basis of the project approved 15 years later by Andy Burnham, then chief secretary to the Treasury, to become the highly successful Elizabeth Line.
In 2025, Don and his former colleague John Buxton published ‘Lines of Power: The Electrification of British Railways’. This book was the basis for Rail Engineer’s Railway 200 history of electrification in Issue 217 (Nov-Dec 25) which is, in part, a sad story of postponed and cancelled projects like some of those in Don’s career.
Don was a railway enthusiast. Until 2010 he volunteered as a driver, guard, or signalman on the Talyllyn Railway. He was president of the Retired Railway Officers’ Society in 2008 and was also chairman of the Robert Stephenson Trust when it celebrated the bicentenary of Stephenson’s locomotive works at Newcastle in 2023.
Don’s legacy is the electrified ECML. There were, and still are, lessons to be learnt about how this project was delivered.
Making the most of a major closure
Between Sunday 26 July and Sunday 16 August, a major closure of the Southeastern railway took place to carry out a suite of works between Charing Cross and Waterloo East stations. The work, commissioned by the South Eastern Railway, was delivered by the Southern Renewals Enterprise (SRE).
The South Eastern Railway, a relatively new authority, unites track (Network Rail) and train (Southeastern) under a single leadership team with clear accountability. Key objectives are better train and infrastructure performance, targeting investment where it is most needed.
Southern Renewals Enterprise is a new partnership formed between Network Rail (Southern Region) and four specialist partners (AtkinsRéalis, Octavius, VolkerRail, and VolkerFitzpatrick) to deliver the Southern Region’s renewals portfolio. The Institution of Civil Engineers’ (ICE) Project 13 has been adopted in other UK infrastructure projects in different sectors; nuclear, health, water etc., but Southern Renewals Enterprise is the first Project 13 Enterprise in the rail sector.
The project started life with the need to renew Belvedere Road Junction, located between the south end of Hungerford Bridge and Waterloo East station, and plain line renewal of one track through Waterloo East. Eventually other major works were included such as platform reconstruction at Charing Cross and various other structural works.
Charing Cross platforms
Almost 20 years ago, the three island platforms at Charing Cross had been identified as needing renewal and updating. The opportunity was taken, in the period of much reduced passenger traffic during Covid lockdowns, to deal with those parts of the platforms under the station canopy. The remaining lengths out in the open were to be the subject of this project.

Evidence of subsidence, creating a risk of slips, trips, and falls as well as corrosion to steelwork made the renewal a priority. It was also considered that there was a risk that regulating authorities might order the closure of some parts of the platforms, pending repair, which would seriously reduce the lengths of train boarding/dismounting available to customers.
The option which had all the signs of providing the most efficient way of working and was likely to be the most economical was to go for a 22-day closure of the railway. This would enable the work to be carried out in one continuous operation, without having to reinstate the lines to rail services several times. During the evaluation of the options for possessions to carry out the switch and crossing renewal, the plan evolved to include the platform works.
Such a major closure of the route would be a perfect opportunity to rebuild the platforms. In fact, the concept of one continuous closure possibly suited the platform works even more than the track works. It would obviate the need for temporary reinstatement of platform areas, a hybrid of old, new, and temporary surfacing, on many occasions. The diseconomy of such a stop-start approach to the works is self-evident, as is the increased safety risks of ‘hybrid’ platforms with trains operating.
Line closure alternatives
Because the location of the work would have a very significant effect on passenger transport options in and out of central London, particularly the West End, and for local journeys involving Charing Cross and Waterloo East, Network Rail consulted with Transport for London (TfL). TfL had developed a modelling system which can show the predicted changes in passenger movements, taking account of all travel modes: tube, bus, National Rail, cycle, foot, taxi and private car.
TfL’s system was used to model the likely effects of the 22-day closure. The results of this were pivotal in enabling South Eastern Railway to confirm the decision to proceed with the major one-off closure – a great example of synergy between transport authorities. Services that normally run to Charing Cross would be diverted to Cannon Street, Victoria, or Blackfriars, with some trains terminating at London Bridge. Further out, there would be many minor routing alterations and calling patterns with one or two services having their frequency halved, but overall, the provision of a viable service for travel in and out of London was shown to be manageable.
However, before deciding to opt for the 22-day closure, two other principal options had been considered. These were to use weekend only closures or to use four nine-day closures, centred around Bank Holidays. Either of these options would have caused repeated disruption to customers and businesses spread over anything between as long as a year to 18 months. Using the preferred one-off closure meant avoiding weekend after weekend of disruption with the continual impact on the tourism and leisure economy.
By using the summer dates chosen, when passenger numbers are reduced by 20% during school and commuters’ holidays, the overall cumulative disruptive effect would be lessened. Closure for 22 days also gave sufficient working time for all the multiple work items – track, platforms, bridge repairs, and drainage – to be completed. Furthermore, the complex alterations to train services necessitated by the closure only had to be put in place and explained to customers only once, which was done by a very effective and well publicised awareness campaign leading up to the closure.
Resources and facilities
The Charing Cross and Waterloo East programme was delivered through the Southern Renewals Enterprise model, with VolkerRail delivering the Track and S&C renewals, and VolkerFitzpatrick delivering the reconstruction of Platforms 1-6 at Charing Cross and refurbishment works at Waterloo East. Network Rail’s Works Delivery team delivered structural refurbishment works on Hungerford Bridge, while South Eastern Railway used the closure to undertake additional maintenance and passenger-focused improvements at Charing Cross and Waterloo East stations.
Crucially, these were not treated as separate projects simply taking place at the same time. The teams planned the programme collectively, understanding the interfaces between each workstream and sequencing activities around the track programme and engineering train movements. This integrated approach allowed the different teams to share access, logistics, and resources, and maximise what could be delivered during the 22-day closure and reduce the need for future disruption.
The possession for the whole project was of all running lines between the buffer stops at Charing Cross and the country end of Waterloo East. Occasionally, when it was available on weekend overnight periods, the possession was extended further countrywards to allow access to Jubilee Yard and the Road Rail Access Point. Two available locations played key roles in the successful progress of the works. James Forbes House, near to Metropolitan Junction, normally the depot for the London Bridge Delivery Unit, became the base throughout for the duty blockade managers and the engineering supervisors.

Jubilee Yard, near to Borough Market Junction, was used as a logistics centre, shared by all the contractors involved. This was the principal welfare and messing facility for staff. It was used for delivery and recovery of materials, being especially useful for stockpiling GRP modules for the platforms and pre-assembled S & C panels, in addition to many other individual items, such as loose track components. VolkerFitzpatrick was put in charge of the use and management of Jubilee Yard. It was for their own needs to fulfil their part of the works but was made equally available to the other partners.
This arrangement had several benefits. It was only necessary to provide one team of security staff, mess, and other facilities, rather than each contractor having to provide their own, duplicated, resources. It proved to be a very good working partnership and gave some overall reduction in overhead costs. A separate welfare area for staff working on the platform works was set up in the forecourt of Charing Cross station.
Throughout the closure there would be an average of around 200 staff on site at any time. It had been planned to work an eight-hour shift pattern (nine-hour in practice for overlap purposes). In view of the extreme heat, it was as well that a longer shift had not been planned. Incidentally, daily deliveries of cooled, bottled water were made regularly available to all staff during these unusual working conditions.
Platform works
The replacement platforms are constructed from GRP units, with a supporting steelwork structure. The GRP modules forming the platform surface are of three types. These are the edge units, behind which are placed the tactile surface units and behind those the yellow ‘warning line’ units. All of these units are easily placed, butted up, resting on a framework of GRP I beams. They, in turn, sit on the new steelwork.
The ‘warning line’ units and the edge units come ready coloured with yellow and white strips respectively moulded in the plastic formula, which will avoid the need for regular repainting as with the traditional markings on concrete, tarmac, or paving slab platform surfaces. The manufacturer, DURA, quotes 80-100 years life expectancy for the GRP units. Network Rail will be well pleased if a lifespan similar to that can be achieved in practice.
The method devised for demolition and reconstruction of the platforms is ingenious. The location of the work, on a high viaduct, ‘landlocked’ from any easy means of access for heavy or large volumes of material, required the most practical approach. A few possible solutions were considered. While much of the new materials, particularly the GRP modules, could be loaded onto road-rail vehicles at Jubilee Yard by the use of road mobile crane, removal of the spoil from the demolished old platforms was a different matter.
Delivery and removal of material by engineering trains had to be ruled out because the track renewal works at Belvedere Road Junction would preclude train movements. Transporting materials using barges on the River Thames would severely disrupt road traffic on Victoria Embankment (closing all lanes) and Northumberland Avenue. Moving the material out through the station and to the forecourt/car park area would have to have been done in small quantities using trolleys and wheelbarrows. Also, it would conflict with the use of the forecourt area for the staff welfare site.

So, discounting all those possibilities, the solution adopted was to position two self-erecting cranes below the viaduct and adjacent to the work, one in Villiers Place and the other in Northumberland Avenue. However, the public street areas here are very busy, with many retail businesses, pedestrians, and road traffic. To put this plan into practice required many months of negotiations with all the interested parties which included the local authority, businesses, utility companies, TfL, and even the nearby Playhouse Theatre. Agreement was needed to close off the two streets, one on each side of the viaduct, to create two working compounds to site the cranes, provide storage areas and to allow lorry movements both to and from site.
Many detailed provisions had to be agreed, for instance, misting to reduce nuisance from dust; safety barriers and hoardings; new diversionary routes for pedestrians; and noise reduction measures. Though it should be noted that locals were warned that it would not be possible to eliminate all noise as the work would be 24/7. It is a mark of the success of the agreed arrangements that, despite there being around 70 or 80 affected businesses in the immediate vicinity, Network Rail received only eight complaints during the whole three weeks of work.
Platform demolition proceeded to plan until one of the cranes started to operate much more slowly than was expected and this could not be rectified. This led to the planned removal of spoil falling 40 hours behind programme. Large quantities were accumulating at track level unable to be craned to road level. This was alleviated by deploying engineering trains being used by VolkerRail for the track works alongside and loading the spoil that way to remove it from site by train and not by lorry. This measure achieved resumption of the scheduled programme. Zen Nichols, project director for the works, told Rail Engineer that this intervention was the only significant change that had to be made throughout the whole closure.
Track works
For the renewal of all the switch and crossing work at Belvedere Road Junction, comprising 16 point ends, as much as possible of the S & C and the associated plain line was made up as pre-assembled panels at Hoo Junction in Kent and delivered to Jubilee Yard. The remainder was taken to site as loose components. Fibre-reinforced Foamed Urethane (FFU) bearers were used throughout, and the work was carried out in five main stages. In all, 37 engineering trains were deployed for this work and for the 468-yard plain line renewal of Platform A road at Waterloo East. (There were an additional seven engineering trains for some of the other works within the closure.)
In addition, some drainage work was done and three under track crossings installed.
Within the track layout across Hungerford Bridge, some work was done to replace cleats which secure wheel timbers in place. This work could have been done by VolkerRail, but it was decided to leave it with the locally appointed trackwork contractor, Balfour Beatty.

Further works
The closure was also used to reglaze the footbridge at Waterloo East. This was done by SET staff, with steelwork repairs and repainting, done by VolkerFitzpatrick.
In addition, there is an ongoing four-year project to carry out repairs and repainting of the whole of Hungerford Bridge. This work is now in its second year. Most of the work is being carried out in normal working hours and with trains running because the work areas are screened off. However, this closure gave opportunity for easier access to some work locations. This was all achieved without interference to either the platform works or the track works.
The costs of the various works were roundly £20 million for the track works, £13 million for the Charing Cross platform reconstruction, and £5 million for the work to the footbridge at Waterloo East. There seems no doubt that this project benefitted from the efficiencies of being tackled comprehensively in one major closure using an enterprise approach.
It is clear that the successful outcome was largely attributable to the meticulous and detailed planning that went into the many aspects of a complex operation. This approach may become a template to be used more often in future when the combination of works required, and the geographical situation indicates the appropriateness of a similar closure.
Image credit: iStockphoto.com
Propping an arch: Bridge 42 at Grosmont
During late 2025, accelerating deterioration of North Yorkshire Moors Railway’s (NYMR) Bridge 42 led to concerns over the structure’s ability to safely support operational railway loading. In December, it made the difficult decision to temporarily close this to rail traffic.
The NYMR is a heritage railway between Pickering and Grosmont where it connects to Network Rail’s Eskdale route. Like many others in the UK, it is more than just a tourist attraction – it is a vital heritage, economic, and community asset that boosts the regional economy, protects railway heritage, and supports local livelihoods. A long-term closure to repair the structure during the main tourism season would have had adverse effects, both to the railway and to the local economy.
Long history
The Grade II listed Bridge 42 at Grosmont has carried the railway over the River Murk Esk since 1846, when John Birkenshaw, for the York and North Midland Railway, replaced the earlier bridge that had carried the predecessor horse drawn tramway. The bridge is a single semicircular arch, spanning 18.2 metres. The arch barrel is of brickwork with sandstone radiating voussoirs, spandrels, and parapets. The bridge carries every train on the railway – around 10,000 movements each year – including those continuing to Whitby over Network Rail tracks.
The railway has been aware of the structure’s degeneration, but a detailed investigation by GGP Consult revealed that in the two years since the previous inspection, further deterioration had taken place. Trial holes excavated above the arch revealed significant mortar loss in the extrados and failure of the existing waterproofing, with significant water penetration through the structure. Further detailed examination revealed delamination between rings, water ingress, and historic repairs of varying quality.

GGP’s defect drawings formed the basis for assessing the structure’s capacity and the decision to suspend traffic. Significant structural work will be required to ensure that the bridge remains safe and fit for the future. Restoring it will be a complex and costly engineering project and will include restoring waterproofing and restoring the structural integrity of the masonry, while preserving the historic appearance of the listed structure.
Carrying out these works during the spring and summer would have been undesirable due to the negative economic impacts of lost income of a long-term closure during the main tourism period. The decision was therefore made to embark on a complex two-stage project to refurbish the structure, firstly to install under-arch propping to guarantee safety and operational reliability and so allow trains to use the bridge during the summer operating season, to be followed by permanent repairs next winter.
“Propping Bridge 42 was a carefully considered solution that keeps the bridge fully operational for the upcoming season,” says Phil Sash, director of civils at NYMR.
“It also gives us the time needed to develop a detailed repair programme, which will be implemented over the winter months to secure the long-term safety and performance of this important structure”.
Complex solution
CML Civil Engineering and structural support specialists, Mabey Hire, were engaged to design and install a support structure, at a cost of around £520,000. This was not a straightforward project, with very challenging access, and supports to be created within the sensitive environment of the riverbed without restricting or contaminating the flow.
The unplanned cost of the project as a whole has been a challenge for the NYMR. As a registered charity it relies on the generosity of supporters to fund projects of this scale. The railway launched its Bridge 42 Appeal, which has so far raised around £400,000. The North York Moors National Park made a £50,000 contribution for this regionally significant project from its s106 Landscape and Ecology fund under its Restoration of Degraded Heritage Assets scheme.
Works began in mid-April. To open access to the site, CML Civil Engineering created a temporary access along the rail tracks from the level crossing 100 metres to the north. This would be used by its 110-tonne crane which would lower plant and materials to river level. For personnel access, a scaffold tower was suspended from the bridge’s parapets down to the riverbank below.
Designers GGP Consult developed an unusual solution to forming a foundation in the riverbed that could be installed without risk of contamination. This was to form a timber crib on each side of the river. This met the Environment Agency’s concerns regarding contamination and restricting flow through the bridge opening, which might have accelerated flow and brought a risk of foundation scour. Fortunately, the arch’s span is wider than the local width of the river’s channel, and so even with 1-in-100-year flow modelling, the restriction was minimal.

On the northern side, the crib was constructed on the bank. To install the crib on the south side a temporary dam was constructed along the abutment face, creating a controlled working area. A small excavator was lowered into this for each shift to prepare the stream bed and to place materials. One thousand reclaimed untreated Ekki sleepers were used to create a multi-layer crib. Ekki is an extremely dense, strong hardwood which resists water absorption. These were bedded on a layer of SoluForm underwater concrete bagwork. These bags are designed for hand placement in watercourses, and hydrate in situ without releasing cement fines. At the end of the project the timbers will be recovered and be available for further use.
Mabey Hire designed the steel supporting structure in conjunction with GGP Consult and NYMR. This comprises three pairs of MU Truss panels bearing on Superprop beams fastened to the timber cribs. Each of the trusses weighed 6.5 tonnes. These were assembled on top of the bridge and then lowered by the crane onto the beams and hauled through the arch by winches.
Once all three trusses were secured in place, transverse Mass 25 beams were placed across these and a network of props and bearers was installed following the profile of the arch as closely as possible. Above these, timber lagging and ply sheeting was placed against the arch intrados and props tightened to take up the load. The supporting structure steelwork bears primarily on the timber cribs but also imparts horizontal thrust into the abutment face.
Once the complete propping was installed, the structure was initially visually checked every day to monitor and confirm its condition and for tightness of bearing against the structure. This has since reduced to a weekly inspection. Additional inspections will follow any flood events.
Raj Sharma, contracts manager at CML Civil Engineering explained: “It was a tight programme on a difficult site: a listed arch over a river, with very little room to work. So how we worked mattered as much as what we built. Everything came in along the track by crane, and each truss had to be winched through the arch.
“Careful planning with all stakeholders and our supply chain meant trains were back running over Bridge 42 on 1st June, in time for the summer season on one of the UK’s busiest heritage railways.”
As a result, NYMR was once again able to run trains over its full 24-mile route through the North Yorkshire Moors National Park, with LMS Stanier Black 5, No. 44806 hauling the first train from Whitby through to Pickering. Until the permanent works are complete, a single train operating restriction on this double track bridge will be in place to reduce loading affects.
Future work

The permanent repairs to the bridge will be carried out in winter, from mid-November 2026 until early March 2027, the likely cost of this being around £350,000. The repair philosophy for the works is for minimum intervention, maximum retention of original fabric, reversible strengthening solutions where possible, and the preservation of the bridge’s historic appearance. All works have been agreed with and will be monitored by Historic England.
The full extent of the repairs will not be certain until the deterioration is exposed, but the worst case has been defined by GGP Consult, used in planning and designing the works, and in the Invitation to Tender to contractors. The exact scope will be identified on site by GGP and NYMR. The first phase will be works to the top of the structure. Track and ballast will be removed from the bridge and minor brickwork and lime mortar repairs carried out to the extrados. Some local stitching and pressure grouting will also be carried out to the brickwork, before the whole is waterproofed using welded DPM sheets. French drains will be installed to each side of the bridge to direct water away from the structure, which has been a contributory cause of deterioration.
Once these works have been completed, the propping will be removed, leaving the trusses as an access platform. Brickwork will be broken out in small areas, as far as the third ring in places, and rebuilt in traditional manner and stitched into the adjacent masonry. About 60% of the soffit has delaminated joints, indicated by drummy brickwork. In these areas stainless steel HeliBar reinforcement will be installed through the 700mm thick arch.
Locations will be determined on site as Historic England wishes to restrict the number of bars inserted into the listed structure. Low pressure grouting of the whole arch with polyester grout will complete the strengthening works. The large sandstone voussoirs will be tied back into the arch barrel. Unusually, to avoid damage to the outer faces, these ties will be installed from the brickwork into the back of the voussoirs to provide invisible support.
This unusual project represents one of NYMR’s most significant infrastructure challenges. The temporary propping works have successfully stabilised the structure and enabled continued railway operation, and the permanent repairs later this year will see this historic structure’s long-term future assured.
Image credit: Andrew Jeffrey
Crowds venture into the abyss
September was a month in which heritage was celebrated, with two weekends of open days at sites across the length and breadth of Britain. Those whose interests include railway structures were catered for in West Yorkshire – or rather under it – thanks to the efforts of a community group and National Highways, custodians of the Department for Transport’s Historical Railways Estate, which opened the gates on the disused Greenside Tunnel, extending for 618 yards between Leeds and Bradford.
The organisers could not reasonably have foreseen locals’ response to social media posts advertising the event. At its peak, the queue extended out of the muddy approach cutting, under an attractive skewed bridge and onto one of the country’s highest railway embankments (also disused). Over four hours across two afternoons, more than 1,300 people – accompanied by numerous dogs – were guided through the passageway by volunteers steeped in its features and history.
Victorian enterprise
In 1882, the Great Northern Railway (GN) entered into an agreement with the Lancashire & Yorkshire Railway to build a collection of short connecting lines which, together with a mutual assignment of running powers, allowed the companies to offer improved services. Among these schemes was the relaying of the Pudsey Greenside branch to provide two tracks and an extension westward to meet the Tingley-Laisterdyke route. It became known as the Pudsey Loop.
Responsible for the line’s engineering was William Myers-Beswick who, by this time, was the only surviving partner of John Fraser & Sons, long-time collaborators with the GN. Awarded the construction contract was Charles Barker & Sons.
Navvies arrived in Pudsey in January 1890, ahead of the first sod being cut on the fifteenth of the month. The ceremony took place at Westroyd Hill, the site of Greenside Tunnel’s western construction shaft which was subsequently retained for ventilation purposes. A second, temporary shaft was sunk 200 yards further east on land acquired from the owners of Pudsey Brickworks.
By springtime, a workforce of around 200 was employed on site. At the tunnel’s west end, a Jubilee steam navvy – which could do the work of 20 or 30 men – assisted with excavation of the cutting, while progress was made around-the-clock with the heading, following an S-shaped alignment. On 16 January 1892, after two years of effort in unimaginable conditions, the job was done.

Catalogue of mishaps
Accidents occurred with sickening regularity – a function of the risks involved and difficulties mitigating them. A jury at Bradford County Court awarded miner James Reaver £200 in damages for injuries sustained on 15 June 1891 when he thrust a steel rod into a hole within which a charge had errantly been left. A sudden explosion followed, causing one of his arms to be shattered, as well as severe injuries to his head and other arm. The contractor admitted liability.
In August 1891, a navvy was descending a ladder into the tunnel when his foot slipped, resulting in a fall of about 30 feet and serious injuries being sustained, including a broken back. He was removed to his lodgings at Hill Top where Dr Hunter attended to him. And on 9 March 1892, an 18-year-old engaged in shunting operations at the east end of the tunnel was crushed between the buffers of two wagons. He survived for just 20 minutes.
Scandal attended on the night of 3 January 1892 when Fred Smith – known on the works as ‘the gallant tunnel man’ – eloped with Mrs Jackson. The local newspaper reported that “Not the slightest trace has been discovered as to the direction in which they have gone.” Mr Jackson was said to be “disconsolate”.
Light at the end?
Major Yorke inspected the new railway for the Board of Trade on 24 October 1893 and trains started running a few days later. Formal closure of the Pudsey Loop came on 6 July 1964 as the retrenchment of Britain’s railway network gathered pace, having retained its operational status for barely 70 years. The tunnel has tolerated enforced redundancy ever since, except as a venue for exploits of an unofficial nature.
Andy Wilson’s family moved to Pudsey in 1968 and he recalls discovering the line’s abandoned infrastructure at the end of his road:
“I remember thinking ‘this is incredible’; what a flipping waste. And as years went by, we ended up strolling further and eventually found this [the tunnel] and I can remember coming through here when I was maybe about seven, with my sister, as a big dare. Going through Greenside Tunnel was like the rite of passage to every youngster in Pudsey.”
Andy was among a group of locals who came together in 2017 to promote the idea of developing a 3.5-mile active travel route between Tyersal and the Bradford-Leeds Cycle Superhighway – through the middle of town, via the tunnel. “It’s our special landmark,” he asserts and points to a collection of “forward-thinking” councils who’ve invested money in repurposing disused railway structures and trackbeds for social, health and connectivity benefits. “How would you like somewhere safe for your kids to ride?” is the question he poses to Pudsey’s parents, seeking their support. “What a wasted asset this is.”
For the masses?
But others have their eyes on the tunnel too. Leeds is a thriving regional centre and the largest city in western Europe not to have trams or light rail. Back in 1993, royal assent was granted for a Supertram system, but Chancellor Alastair Darling pulled the plug 11 years later when projected costs hit £487 million. A trolleybus proposal then emerged; that collapsed too.
Following the abandonment of HS2’s eastern leg, West Yorkshire Combined Authority was awarded the consolation prize of funding to examine prospects for a mass transit system. With a price-tag estimated at £2 billion, it also looks prone to the vagaries of political decision-making and timescales are now uncertain. What’s beyond doubt, however, is that one line on the map of options incorporates Greenside Tunnel.
Mayor Tracy Brabin has big mass transit aspirations, with the eventual aim to reach the whole of West Yorkshire. Phase One would head south from central Leeds to the White Rose commercial and retail area, as well as pushing west to Bradford. The latter has three alignment possibilities through two corridors converging at Pudsey, with B2 and B3 largely following the old railway, heading underground through the tunnel.
All of which means that the greenway proposal is now paused, prompting campaigners to seek assurances from both WYCA and Whitehall that its full proposed course will be “protected from development until a final route decision is made.” And so it should be. The Strategic Outline Case – an early stage in the government’s business case process – is due to be submitted later this year.

Dripping nostalgia
Gary Lemal is pragmatic. As current chair of the Greenside Greenway group, he accepts that “it’s above our pay grade. If it’s going to happen, it’s going to happen and we’d like to work with them to incorporate the cycle route.” Bikes and trams can safely share the same space, as they do elsewhere.
In the meantime, “England’s largest festival of history and culture” – so claims the Heritage Open Days website – offered a chance to repurpose the tunnel, if only for one weekend. Gary applauded the Historical Railways Estate team within National Highways who were “brilliant and supportive all the way”.
And so on the afternoons of 12 – 13 September, a hi-vis-clad team guided a hugely varied demographic through the darkness to the other end, looking out into the eastern approach cutting where – thanks to an act of planning blindness – a partial infilling scheme was approved in 2017 on the back of an adjacent housing development. Vehicular access to the portal for maintenance purposes is now impractical.
Mary served as our escort for the 25-minute tour, pointing out the refuges to which platelayers used to scuttle when a train approached, in an era predating health and safety. We looked up the shaft to the concrete beams which cap it and enjoyed a shower where water from the hidden construction shaft penetrates the lining. The quality of stonework in the sidewalls – each block crafted by a mason’s hand – was a frequent subject of admiration, as was the courage of the navvies who drove the tunnel without any of the mechanical and technological advantages bestowed on 21st century engineers.
For many, it was a revelation and painted smiles on faces. Today’s youngsters – prevented from enjoying the kind of childhood adventures that helped to shape Andy – embraced an opportunity they’re unlikely to have again.
“The rumour, the noise, the history of the tunnel. So many kids went through and these kids are now in their 40s, 50s, 60s, 70s and beyond”, Gary reflects. “This is the experience dad had; this is where mum left a bottle of cider. These are the things people want to pass on; this is a bit of everybody’s history.”
Image credit: Four by Three
Feeling the Heat
Record-breaking spells of hot weather across Europe had a significant impact on rail infrastructure this summer, highlighting the importance of climate adaptation measures. While the high-profile derailments at Lewes, West Sussex, and Wickford, Essex made the biggest headlines, they were part of a bigger problem characterised by cancellations, delays, and discomfort to passengers.
There is no easy solution to these problems, and the most common short-term mitigation is to send inspectors to look for signs of distress, or more often to impose critical rail temperature speed restrictions or even temporary closures.
The development of a growing range of remote monitoring technologies offers further options that can reduce the risk of derailments or the need for costly restrictions on train operators. Engineers and product developers at remote monitoring specialist Senceive (part of Eddyfi Technologies) are acutely aware of the impact of climate conditions on the railway network.
Having worked closely with Network Rail and other asset owners for more than 20 years, the team that developed InfraGuard, the UK’s most widely used landslip detection system, is busy on new challenges. Some of these technologies can help keep trains moving when the mercury rises to uncomfortable levels.
Hot weather impact on the track
Even short periods of high temperatures can heat steel rails close to their critical rail temperature, potentially resulting in vertical or lateral movement. Research has shown that rail temperature can be 20 degrees higher than ambient. The Senceive temperature sensor provides continuous measurement of the actual rail temperature. Used as part of a wireless monitoring system, the associated wireless node sends near real-time updates and automated alerts to remote stakeholders via the cellular network or satellite comms.
Where permanent way engineers are concerned about lateral rail movement (buckle) they can use other wireless sensors such the Optical Displacement Sensor (ODS). This combines a laser for precise measurement of displacement between two surfaces, a tilt sensor, and similar wireless connectivity to the temperature sensor. It can be deployed in various ways, but a common scenario is to mount the ODS on a structure such as a gantry and direct the laser at the rail web. Lateral movement is reported to sub-millimetre accuracy. Deploying a number of sensors along a critical length of track such as a high-speed curve provides continuous monitoring data and immediate alerts if pre-set thresholds are breached.

Deeper ground movement
Prolonged hot dry weather can also cause deeper problems below the trackbed associated with uneven ground movement, particularly in the reactive highly plastic clays found across southern England. These soils are prone to severe volume changes leading to desiccation (shrinkage and volume loss) causing differential subgrade settlement. This can contribute to track geometry problems such as crosslevel anomalies, twist faults, and track settlement.
Remote monitoring
Most of these problems can be monitored using tilt sensors such as the Senceive Nano Macro which has a High G variant for extended use in high vibration track conditions. In most applications sensors are fixed to sleepers and assumptions made about the relationship between sleeper and rail displacement. This approach has been proven for parameters such as crosslevel and twist but is problematic for monitoring settlement without well-established control points.
The recently developed Senceive rail-mounted tilt meter provides a means of monitoring movement of the rail rather than the sleeper and has been tested on heavy freight railroads in the USA. Findings of independent research have demonstrated great improvement in the accuracy of vertical movement monitoring.
We may have seen the back of the European heatwaves this year, but we know they will return, and practical, cost-effective monitoring solutions look set to be part of any package of measures to manage risk.
Image credit: Senceive
Heat related derailments
Over the past 10 years there have been around 23 passenger train derailments, of which five resulted in injuries and two in fatalities. These have been the result of a wide range of causes with five derailments, 22% of the total, being due to track defects. Of these five, three were slow speed derailments on wide gauge track, and two were due to kinks in the track. These last two derailments occurred on two consecutive days this year – 13 and 14 August.
As described in our rail safety feature in Issue 221 (Jul-Aug 2026), there has been a significant reduction in passenger fatalities, though the risk of certain types of accidents has increased. Though passengers came to no harm in most of these derailments, with an average of just over two a year, there is the potential for a serious accident.
Lewes
At around 15:54 on 13 August 2026, a train formed of two four-car Class 387 electric multiple units (EMUs) became derailed 1.6km north of Lewes station. It was the rear three vehicles that derailed and subsequently overturned, coming to rest on their sides.

There were around 150 people on the train when it derailed of whom 20 people required hospital treatment, some for serious injuries. There were no fatalities. Significant damage was also caused to the train and to railway infrastructure.
Preliminary analysis of OTDR data obtained from the front vehicle shows that the train was travelling at around 65mph (105km/h) as it approached the point of derailment. Preliminary OTDR data analysis also shows that the driver applied the train’s brakes as it passed the point of derailment, and that the train had started to decelerate.
Rail Accident Investigation Board (RAIB) inspectors observed marks on the rails indicating that the wheels of the derailed rear vehicles had climbed over the rails. CCTV images from the derailed train and another previous train showed that, prior to the accident, there was a track geometry irregularity before the point of derailment. Indications of previous nearby track maintenance activity adjacent to this irregularity were also noted. In addition, RAIB had received several reports of rough riding at the location of the derailment from passengers on other trains.
The weather on the day of the accident was hot and sunny, with little wind. The ambient air temperature at the time of the derailment was recorded as being around 27°C by the nearest weather station to the accident. The accident took place during a sustained period of hot and dry weather.
The railway embankment at this location consists of clay and sits on deposits of loose clay, silt, sand, and gravel. Both these layers are sensitive to variations in water content and may undergo movement as moisture levels change. Although RAIB inspectors saw no evidence of a significant embankment slip before the derailment, there was also evidence of some previous movement.
The above information is included in RAIB’s initial report on the accident which was published on 19 August.
Wickford
At around 14:08 on 14 August, a passenger train formed of two five-car Class 720 electric multiple units travelling at 124km/h became derailed 3.4km south-east of Wickford station. The rear vehicle was the only one that derailed. Its wheels then ran on the sleepers and ballast for around 2.4km. The train remained upright throughout and there were no reported injuries to the 62 people estimated to be on board.
The driver reported seeing a kink in the track which rocked the driving cab. This was confirmed by the train’s forward-facing CCTV which shows track misalignment at the point of derailment.
The train driver was reporting this track defect when an emergency call from another train passing in the opposite direction was received after that train’s driver had seen ballast flying from underneath the derailed train. The driver of the derailed train then applied the train’s brakes.
The derailed train sustained damage and the other train received minor damage from flying ballast. There was significant damage caused to the track, signalling, and overhead electrification equipment.
The above information was in RAIB’s initial report on the accident which was published on 19 August.

Increasingly hot summers
Until July this year, derailments resulting from kinks or buckles were extremely rare. Indeed, as far as Rail Engineer can ascertain, the last such derailment that caused passenger injuries was at Motherwell in June 1986. In this case the buckle occurred between two sets of points which had been laid in cold weather and not restressed.
Forty years later, the next two such derailments occurred on consecutive days in August. It is difficult to accept that two such incidents in two days can be a coincidence especially as the common factor is hot days after a sustained period of hot and dry weather.
Up to 2024, the four hottest summers on record were separated by just 0.05°C, then 2025 beat the previous record by 0.34°C and 2026 has beaten that by another 0.40°C. Hence, after years with tiny increases in record temperatures, in just two summers the record has been raised by 0.74°C. A further indication is that this year saw temperatures of 30°C or more on 40 days. The previous record was 34 days, set in 1995.
In 2022, the Seasonal Challenge Steering Group published the ‘GB Rail Industry Approach to Hot Weather Management’. Its foreword notes that the very hot summer of 2022 was the first time that UK temperatures over 40°C were recorded. Yet the Met Office advise that this year’s summer has been the hottest on record by a significant amount.
Network Rail’s 2024 Climate Change Adaption Plan (CCAP) notes that the impact of cold and snow-related railway impacts is reducing, while flooding, heat, and subsidence impacts are increasing. For example, in 2022/23 heat accounted for 646,000 delay minutes and there was a further 498,000 delay minutes from summer embankment shrinkage followed by autumn rainfall. In comparison, in 2023/24 storms accounted for 1.3 million delay minutes.
The CCAP also contains Network Rail’s Integrated Climate Change Risk Assessment (ICCRA). This considers five categories of risk as shown in the table below.
As temperature presents such a high risk, one of the CCAP’s actions was independent extreme heat reviews into engineering, operations, weather forecasting, and customer experience to improve understanding of extreme heat risks. The engineering review was led by Sir Douglas Oakervee and considered the impact of heat on track, overhead line equipment, and distribution infrastructure affecting S&T systems.
Extreme track temperatures
Where jointed track is used, 60ft (18.3m) lengths of rails are joined by fishplates where, at moderate temperatures, there were gaps of 5mm to allow for thermal expansion of the rails. This results in joint impact loads and a heavy maintenance workload with the inspection and maintenance of 176 fishplates per mile.
From the mid-1960s, jointed track was progressively replaced on most lines with the Continuous Welded Rail (CWR). Unlike jointed track, CWR does not allow rails to expand as they are firmly fixed to the tracked. This is generally done by track fastenings onto heavy concrete sleepers which are fixed in a thick layer of ballast with ballast shoulders preventing lateral movement. In some cases, such as switches and crossings (S&C) and bridges, CWR is laid on wooden sleepers.

A critical aspect of the management of CWR is ensuring that it is stress free at 27°C which is the currently specified stress-free temperature (SFT). This balances the compressive force in the rail at high temperatures as it tries to expand with the tensile force at low temperatures. This respectively controls the risk of track buckling and rail breaks during high and low temperatures.
When rails are laid below the SFT, they are put in tension by pulling them by the required amount before being welded and fixed in place. This amount depends on the length of rail and difference between ambient temperature and SFT. As an example, a 300-metre length rail laid at 11°C would need to be stretched by 55mm.
Regions are also required to have a critical rail temperature (CRT) register for each CWR track section. For CWR track in perfect condition, the CRT is generally 56°C. The CRT needs to be reduced to take account of anything that might reduce fixity of the rails, for example: wooden sleepers, poor ballast shoulders, and adjacent construction work. It should be noted that on hot days, rail temperatures can be 20°C above the ambient air temperature.
The Oakervee report
The Extreme Heat Taskforce report led by Sir Douglas Oakervee was published in 2023. In respect of track, it found that 23 buckles were reported in 2022 of which 13 had occurred on two consecutive days of extreme heat. Of these incidents, 18 were sites that were not on the CRT register and 15 were at, or within 100 metres, of S&C.
The report noted that heat alone is not the only factor that causes buckles, and listed a range of factors that need to be considered together with the primary deficiencies that caused the 23 reported buckles. These factors included:
- Ballast condition, consolidation, and profiles.
- Drainage.
- Sleeper condition.
- Track clips and pads.
- Transition zones on run off from fixed assets e.g. bridges and level crossings.
- Wooden S&C bearers, shallow depth switches with shortage of ballast.
- Low SFT.

The report made 25 recommendations which concerns improving record keeping, ensuring that lessons are learnt from the 23 buckle incidents, a programme to remove risk at low CRT sites, detailed inspections of S&C with line speed above 60 mph, reviewing competencies of all personnel concerned, consistency of national and hot weather preparedness strategies, and delivering a policy of zero unmitigated track buckles.
It also suggested that there may be a case for increasing SFT to 30°C if there is sufficient mitigation for the risk of broken rails at low temperatures.
Hot weather mitigation
Although the principles of CWR temperature management have been known since the mid 1960s, with ever hotter summers the risk of heat-related derailments has increased. As the CCAP and Oakervee reports show, this has been recognised for some time. As a result, additional mitigation for extreme heat has been specified.
Within hours of the Wickford derailment, Secretary of State for Transport Heidi Alexander spoke to senior officials at Network Rail and the Office of Rail and Road (ORR) to ask if any blanket action need be taken following the derailments at Lewes and Wickford. It seems likely that she was assured that no such action was necessary as a result of these extreme heat mitigations.
RAIB’s investigations into the Lewes and Wickford derailments will consider: (i) the effectiveness of any mitigation measures to address the risk of operating trains in hot weather; (ii) the status of the track at this location and how it was maintained; (iii) the actions of those involved and the factors that may have influenced them; (iv) the condition of the embankment at Lewes; and (v) and how it was inspected and maintained as well as weather conditions in the area on the day of the accident, and in the weeks and months preceding it
In effect, RAIB will be assessing the effectiveness of the mitigation measures specified in the ICCRA and Oakervee reports.
Speaking at a press briefing on 19 August, Rail Minister Lord Hendy noted that it is quite clear that there is significant climate change. He advised that Network Rail’s expenditure on climate resilience for earthworks and drainage in Control Period 7 (CP7) from 2024-2029 was five times that of CP6. He had no doubt that CP8 will have increased spending for extreme weather mitigation.
Lord Hendy also noted that the industry must wait for the RAIB report which will determine causes of the Lewes and Wickford derailments and make appropriate recommendations.
Of the £2.8 billion allocated for Climate resilience projects in CP7, 78% is for drainage and earthworks and only 2% is on track. It will be interesting whether, as a result of the required hot weather mitigations, including RAIB recommendations, there will be a significant increase in track expenditure in CP8.
Image credit: RAIB
TRU sustainability and environment update
Rail Engineer has featured the Transpennine Route Upgrade (TRU) a number of times and two years ago reported on the programme’s sustainability strategy. This issue, with a focus on rail sustainability and environmental impact, provides an update on what has been achieved so far and is planned by the programme to further improve the lives of those living on the route.
TRU is a multi-billion-pound, transformative programme to improve connectivity for both passenger and freight services between Manchester and York, and to support economic growth. The programme is impressive and will provide a greener, more reliable, faster electric railway with a reduced carbon footprint and improved air quality.
The programme is also committed to providing other benefits to society, detailed in its sustainable development strategy – ‘Our Guiding Compass’ – which aims to improve sustainability and the environment along the route. A large rail programme like TRU can impact neighbourhoods and communities during construction, but the programme’s objective is to also contribute positively to local businesses, communities, the local environment, and to leave a net positive impact.
Table 1 details the programme’s social value targets, showing progress achieved when Rail Engineer first met with TRU two years ago alongside an updated position for 2026.
The numbers are very impressive, but the programme also recognises that it can be easy to focus just on hitting the numbers and that it is important to look at the outcomes. The programme has undertaken socio-economic impact assessments to direct its approach to address this. Apprenticeships, for example, must deliver the right experience and skills for the apprentices to deliver rail programmes such as TRU and other work in the future.
Ninety-three percent of the apprentices live within 40 miles of the TRU route and this programme will leave a lasting legacy, amounting to over £26 million in value to society, according to the Rail Social Value Tool. The apprentices are working in various disciplines across TRU, including civil engineering, project management, quantity surveying, and ecology. Many TRU apprentices also have formal education built into their apprenticeships, taking one or two days a week off work to study.

Carbon reduction
TRU has a carbon reduction fund of £30 million for projects to draw on if they have a carbon reduction initiative, which may cost more than a traditional higher carbon solution. Engineers and managers in the programme have been trained on carbon reduction techniques and are now able to apply to the fund to finance carbon reduction elements of their works. Low carbon concrete is one example, which is being trialled in low-risk locations and, if successful, could be used elsewhere on the network.
The programme has also now electrified 25% of the route (Manchester Victoria to Stalybridge and York to Colton Junction). This allows hybrid rolling stock to operate along the route and deliver carbon reduction in advance of the complete scheme and new electric traction rolling stock.
Community fund
TRU has a Community Fund, giving local community groups, schools, and charities the opportunity to apply for funding to improve and encourage the use of local spaces and services along the route in areas of high social need. A key element of the fund is that it is for local communities to decide what they need, rather than the TRU programme or central government deciding what to provide.
The funding for 2024/2025 was a total of £155,000. For 2025/2026 it was £250,000, and this is being further increased to a total of £270,000 for 2026/2027. Community projects close to the TRU route are eligible to receive the funding to help to provide real, long-term, sustainability benefits in the areas the programme is operating in.
Projects typically consist of enhancing indoor or outdoor community spaces, creating opportunities for skills, education, and employment, and to support disadvantaged, under-represented or marginalised groups. In the 2026/2027 funding there will also be a greater focus on supporting projects that are creating opportunities.
Some of the projects funded and completed to date include the following:
Manchester
- Cede Foundation, conversion of a former church into welcoming community hubs.
- Key Changes, improvements to a portable recording studio, supporting mental health patients at North Manchester General Hospital.
- Family Unit Trust, refurbishment of an unused unit into a Family Support & Wellbeing Hub for families affected by cancer & illness.

Oldham
- Local Food First CIC (Community Interest Company): transformation of a disused building into a Community Food Hub with a teaching kitchen.
- Bee Together Community Centre & Garden: Expansion of a community food growing programme, including installation of new planting beds and pollinator flowers.
- Pennine Mencap: a community garden project teaching gardening and cooking skills to adults with disabilities and autism.
Bradford
- Making Sedbergh Sustainable: an upgraded community space at Sedbergh Youth & Community Centre.
- A Place to Connect, Share and Thrive: a fully equipped community kitchen serving people experiencing homelessness & hardship in West Bowling.
- Northcliffe Environmental Enterprises Team: an accessible outdoor space for therapeutic gardening and wellbeing.
Leeds
- Junior Sports Hub: New toilets and an improved outdoor green space.
- Friends of Farsley Rehoboth Burial Ground: Accessibility, re-wilding and sustainability improvements.
- United Hebrew Congregation: Development of a sensory garden and raised growing bed.
York
- Make Space York: multifunctional climbing and seating structures in Rowntree Park, as part of an initiative to make York’s parks more inclusive for teenage girls.
- Haxby Ethel Ward Sports Courts: Refurbishment of the playing fields into a multi-purpose community sports facility.
- Huntington Library, development of an accessible, sensory community garden.
Altogether, a total of 63 projects has so far been funded with a total value of £405,507, and TRU was awarded ‘Highly Commended’ at the Spotlight Rail Awards 2026 for the Community Fund initiative.
The third round of the Community Fund opened for applications at the end of September. Organisations were able to apply for £5,000, with the option to request up to £10,000 where this would help deliver greater benefit.

Any group or organisation with a clear social purpose and located within 5km of the TRU or within 5km of the Shipley Traincare Centre, was eligible to apply for the funding, including registered charities and CICs; community groups, community centres, and local organisations; schools, not-for-profit nurseries, and family centres; and universities, provided they are linked to a registered charitable organisation or community group with a clear social purpose.
The fund is being independently managed on behalf of TRU by Neighbourly Ltd, a limited company specialising in administering grant funds, to ensure impartiality and good value for money. It will oversee the management and distribution of the fund, with a governance approach independent from TRU, who will only be involved to support strategic alignment.
TRU still acts as the client and a scorecard has been created for projects to be assessed using the core objectives of TRU’s ‘Our Guiding Compass’, to ensure the fund is used in a way that aligns to TRU, as well as benefiting the railway and community, and for projects considered to be good value for public money.
Biodiversity net gain
TRU has committed to achieving a 10% Biodiversity Net Gain (BNG) across the programme. BNG aims to ensure that habitats for wildlife are left in a measurably better condition than they were before development began.
As part of its BNG commitment, TRU has recently invested in long-term habitat enhancement works near to the route at Barnbow Wood and Barnbow Hall Wood, an area of 8.32 hectares – over 11 football pitches. The woodlands are owned by Leeds City Council and will be managed by Leeds Habitat Company, a dedicated habitat banking vehicle established by Leeds City Council.
This utilises council-owned public green spaces, ensuring the environmental offsetting benefits the local communities. It is the second largest investment of this kind made by Network Rail and the largest single investment that Leeds Habitat Company has received.
The site is located east of Crossgates and just over 500 metres from the TRU works. The woodland was chosen as it is a community asset, which is accessible through a series of public footpaths. The work will directly benefit the local communities impacted by the TRU programme through improved access to nature, with educational and associated mental health benefits.
The current woodland is species poor and most of the trees are of a similar age, which creates a dense canopy shading out wildflowers. This long-term commitment will result in notable improvements in species richness and abundance, as the work includes enhancing the woodlands by improving structural and species diversity over a 30-year period.
A well-functioning woodland with healthy soils can also sequester more carbon to help fight against climate change. The roots stabilise soil and absorb large amounts of water, which can reduce the volume and speed of surface runoff, helping to alleviate downstream flooding. Woodlands also act as natural bio-filters as leaves trap particulate matter and pollutants from the air, while forest soils filter excess nutrients from groundwater before reaching streams and rivers.
The works started in May 2025 and will continue until at least 2055. The initial works include targeted felling, enrichment planting, tree veteranisation (deliberate wounding of ‘younger’ trees to improve the microhabitats of larger, older trees), new habitat piles to create deadwood features, and litter collection. Subsequent years will include rotational felling, coppicing, and planting and natural regeneration to improve the structural and species diversity of the woodlands.

TRU is also making sure that the railway areas it works on are left in a measurably better state than they were before, leaving an improved natural habitat for wildlife.
Environmental Performance Index
In order to instil a culture of environmental protection and to reduce incidents, an Environmental Performance Index (EPI) score has been introduced for use throughout the supply chain.
As an example, senior managers who normally undertake safety tours will be additionally looking at environmental performance, and high-risk sites are prioritised for site inspections. The objective is to incentivise environmental protection awareness and culture and for it to become the proactive norm, rather than a reactive measure which is only considered when prompted. EPI has already made a difference, and TRU believes its success makes it something that other programmes and projects may also wish to adopt.
Programmes such as TRU which are delivering huge improvements to rail can be disruptive to local communities if not managed appropriately. We also sometimes hear of rail projects which don’t deliver what was promised, and which cost more and take far longer to deliver. It is therefore great to report on the many positive TRU initiatives which will leave a lasting legacy to wellbeing, in addition to the many benefits of its rail improvements.
It is essential that major programmes factor sustainability and social value into their work, as TRU has done. Major rail programmes must not just build for today as, if managed correctly, they can enhance local communities and the lineside environment, leaving a legacy for future generations that is safe, maintainable, and sustainable.

