Home Blog Page 226

Carmuirs Canal Clearance

Britain’s canals formed the country’s first high-capacity transport network. In their day, the raw materials they carried laid the foundations for the industrial revolution.

In some places, they also transformed passenger travel. Hundreds of thousands of passengers took the eight-hour Swiftboat journey between Edinburgh and Glasgow, hauled by galloping horses on Scotland’s lowland canals.

The alternative was a slower, bone-jarring stagecoach over the rough roads of the time.

Railway canal crossings

Canal engineers faced significant challenges but at least had the advantage of a country almost free from man-made obstructions. Roads carried minimal traffic and could be crossed by simple swing bridges. For this reason, the Forth and Clyde (F&C) canal was able to carry tall-masted ships bound from Glasgow to European North Sea ports across the centre of Scotland. Opened in 1790, this canal was the world’s first sea-to-sea canal.

Railway builders had the canals to contend with. In London, the need to cross the Union Canal resulted in a steep descent from Camden into Euston, a tunnel under the canal before Kings Cross and an elevated station at St. Pancras. The tall ships of Scotland’s F&C canal required railways to pass under it unless a railway swing bridge was provided. When the Scottish Central Railway to Perth was opened in 1850, its passage under the canal at Carmuirs required cuttings and two 40 metre long single-bore tunnels.

The F&C canal was closed in 1963 and re-opened in 2001 as part of a Millennium project which also re-opened the Union canal to Edinburgh and connected the two canals by the Falkirk Wheel which is adjacent to Carmuirs. Unfortunately, in 2002, shortly after the Wheel and its canal basin were opened, there was a slope failure, depositing tonnes of rubble which almost blocked the mouth of the tunnel. This was due to saturated ground and resulted in the line being blocked for 16 days.

Replacing the tunnel

EGIP, the Edinburgh Glasgow Improvement Project, will electrify the Edinburgh to Glasgow route and associated lines, a total of 220 route miles. As with all electrification projects, this requires route clearance to replace or modify large numbers of historic structures well in advance of the electrification works.

In December 2011, BAM Nuttall was awarded a £27 million contract for EGIP clearance works. Since then, it has undertaken route clearance work on 41 structures, including some heavily used road bridges such as the five-span Shore Road for which the company received a commendation at the 2014 Saltire Civil Engineering Awards. Carmuirs is the last EGIP clearance job and presents quite different challenges.

Unlike double-track tunnels that have centre space which can normally provide room for overhead line equipment, the single bore tunnels at Carmuirs do not have sufficient electrification clearance. For this reason, the solution originally proposed in the 2007 GRIP 1 report was to lower the track by 150 to 200 mm and provide slab track.

It was later decided to replace the tunnels with a canal aqueduct. This avoided drainage problems and also the need for slab track. Together with clearance work at eleven other structures, this will achieve W12 gauge on the line and allow freight trains to carry ‘big box’ containers to and from Grangemouth docks.

The aqueduct consists of 36 portal units placed on five cill units on each of the original tunnel abutment walls with wingwalls built in-situ over new bases. These units form a deck over which 34 key wall units are laid to form the canal channel. There is some dead space over this deck as the canal crosses the railway at a 50° angle. To minimise the loading, foam concrete is used for infill behind the portal frame. Outside the wall units, class 6N granular fill provides the base for the towpath and landscaped slopes. On either side of the canal, ducts are provided for existing and future services.

With the new structure and its increased electrification clearance, it is no longer possible to provide a one-metre thickness of puddle clay as required by Scottish Canals. To maintain the required 2.1 metres draft over the portal units, the aqueduct’s canal channel has a waterproof membrane bonded to the concrete face on which there is 400 mm of puddle clay laid on top of a Bentomat sheet.

Getting ready to start

BAM Nuttall’s senior site agent John Edelsten explained that a significant amount of work had to be done before work could start on the aqueduct.

Two site compounds were required. One, of around 4,000 square metres, immediately adjacent to the canal crossing, includes the base for cranes of up to 1,200 tonnes. The other, 150 metres from the canal, is of around 20,000 square metres. John advised that there was initially some doubt that a compound of this size was required.

Christmas day tunnel demolition [online]

However, it was proved to be necessary with the requirement for trial assembly of portal units on the cill beams and storage of general demolition material, removed masonry and puddle clay as well as site accommodation and parking.

The first key milestone was the provision of a temporary footbridge. This was put in place by a 450 tonne crane in August last year as a replacement for the canal towpath during the works. This bridge also carries high voltage (HV) and low voltage (LV) electrical cables that have been temporarily diverted from the towpath. Also diverted were BSkyB’s fibre-optic cables although, as a permanent diversion was possible, these were not routed over this bridge.

An earth dam had initially been considered as a way of blocking the canal on either side of the tunnel – the same type of dam which had been used to block the canal for the repairs in 2002. However, with a much longer four-month canal blockage, it was felt that a more robust solution was required so dams formed of sheet piles were used. These are a cantilever design with eight metre deep piles that requires six metres of undisturbed canal bed on the dry side of the dam.

When the canal is re-filled, the piles will be extracted by a vibro-remover with no requirement to repair the canal bed as the puddle clay layer is self-healing.

The canal’s catchment is such that, at Carmuirs, there is a significant flow of water from its summit pond to the sea. Once the canal was blocked, this flow was something else for the temporary bridge to carry. Pipes and pumps were provided for a maximum flow of 400 litres per second – the actual flow at any time is regulated according to weather and Scottish Canal’s requirements.

Fish rescue

Works of this scale required the normal environmental mitigation. As de-vegetation was carried out within the bird-nesting season, it was done in stages and subject to a watching brief by environmental specialists. The tunnel was surveyed for bats and, although none were found, cavities were filled in to prevent nesting immediately prior to the works. No badgers were found during the survey that had been undertaken.

For a railway project, an unusual requirement was the need to rescue fish trapped in the canal once it had been dammed either side of the tunnel. This was undertaken by EcoFish consultants, using a combination of electrofishing and netting under licence issued by Marine Scotland. This was done from a boat that was lowered into the blocked canal section by a heavy-duty fork lift.

As a result, approximately 750 fish, mainly roach, perch and pike, were rescued from the drained 120 metre long section of the canal and released downstream. A further mitigation measure is the fish mesh system on the temporary pumps that maintain the canal water flow.

Immediately north of the compound are thought to be the remains of a temporary construction camp for the nearby Roman Antonine Wall. There are no visible remains of this camp which required no archaeological mitigation measures as the project did not excavate any previously undisturbed ground.

Demolition

After months of planning, the stage was set for the tunnel demolition. John advised that, amongst many other things, risk readiness reviews had identified the requirement for a trial assembly of the portal unit /cill beams and the provision of extra pumps to prevent protective mats floating away in the event of flooding. This possibility was raised as there are known to be existing drainage problems at this location.

The staged demolition sequence had been assessed on the basis of a finite element analysis of the tunnel undertaken by MHB Consultants – designers of the temporary works associated with the tunnels replacement. Demolition contractor was S Evans and Son from Widnes.

Prior to the demolition, the headwalls and towpath had been removed as well as the overburden to within 300mm of the tunnel barrels. This represented around 8,000 tonnes of material, about 35% of the total.

Demolition took place during a 54 hour possession on 25 and 26 December. After the last train on Christmas Eve, a signal north of the tunnel was removed and protective mats laid over the track. During Christmas Day, the tunnel arches and wingwalls were demolished and all spoil removed to expose the tunnel barrels which were demolished overnight with the lower tunnel walls left in place. These formed the abutments on which a total of 10 cill beams were placed on 26 December. After all material had been removed from the track bed and the signal by the tunnel reconnected and tested, the possession was given up ready for the first train on the following day.

The tunnel demolition was a carefully choreographed operation involving around six excavators. As well as demolishing the structure, these machines passed the 16,000 tonnes of excavated spoil to tippers for transport to temporary storage at the adjacent larger compound as landfill sites were not open over the Christmas holidays. This spoil included sandstone masonry from the tunnel portal which is to be re-used by the local landowner.

One legacy from the 2002 cutting failure was that, as part of the tunnel repair, the cutting retaining wall north-east of the tunnel was of reinforced concrete.

As a result, this required much more effort to remove than the other masonry retaining walls.

8th January [online]

Construction

The possession over 1 / 2 January required a 1,200 tonne road crane, one of the largest in Europe, supplied by Mammoet. It was used to install the lower wing wall bases and numbers 36 portal units, each weighing between 25 and 40 tonnes. As the smaller compound by the canal was not large enough to accommodate them all, most of the units were placed in the larger compound where a 200 tonne crane lifted them onto lorries for transport to the 1,200 tonne crane.

The precast concrete units were supplied by Macrete of Northern Ireland which had also supplied units for many of the EGIP project’s reconstructed bridges. Delivery of the 46 large heavy units was arranged to a tight possession timeframe over the Christmas and New Year period – an achievement in itself.

After the New Year possession, work was double-shifted due to poor weather and the amount of work required to ensure that the canal would be re-opened on 27 March. Before then, around 1,000 cubic metres of foam concrete backfill was put in place, wing walls were constructed in- situ, the canal walls units installed and waterproofing undertaken. During the weekend of 21/22 February, Mammoet’s 1,200 tonne crane again returned to site to install the 33 key wall units to form the canal wall. The few lifts that would impact on the operational railway were undertaken during normal overnight possessions.

John Edelsten felt that some of the biggest challenges were the interfaces with other concerns. There was a significant amount of utilities work and the project also liaised closely with Scottish Canals both to ensure that the design met its standards and to facilitate inspections at hold points before the canal is re-filled. During maintenance of the Falkirk Wheel the canal water flow had to be carefully regulated as the outlet pipe for the Falkirk Wheel basin is adjacent to one of the sheet pile dams.

John commented that the Carmuirs tunnel work had generated a lot of interest from the passing public who had great views, not the least from the temporary bridge. BAM Nuttall has provided good information boards to keep everyone advised of progress including overhead photographs taken by drones.

Railway and canal revival

165 years ago, the contractor for Carmuirs tunnel and other original bridges on the Scottish Central Railway was Thomas Brassey, in partnership with Robert Stephenson. Their structures were well built and could have remained in place for many years to come had it not been for the need to modernise the railway. As part of the EGIP programme, BAM Nuttall has provided modern replacement structures, of which the Carmuirs aqueduct provides W12 clearance for container trains and overhead electrification due to be energised here in 2018.

Just 200 metres from the new aqueduct is the Falkirk Wheel, opened in 2002 to connect Scotland’s two lowland canals. It replaces eleven locks which were closed in the 1930s. The Wheel is one of Scotland’s most visited tourist attractions and plays an essential part in the revival of its once-derelict canals.

The new Carmuirs aqueduct may not have the tourist pulling power of the Falkirk Wheel. Yet, for those with an interest in modern transport, it is good to see these adjacent modern structures as part of a railway and canal revival.

Finding the real causes

After nearly ten years of operation, during which it has published 252 investigation reports, the Rail Accident Investigation Branch (RAIB) is well known within the industry. It was formed as a result of a recommendation by the Ladbroke Grove rail crash inquiry, which required the investigation of rail accidents to be undertaken by an independent body as is the case for the air and marine sectors, and became operational in October 2005.

The story of railway safety includes learning from accidents. This is one reason why the industry now has a good safety record with no passenger fatalities in the past eight years.

Paradoxically, as railways get safer there are also fewer accidents from which to learn. This makes it more difficult to assess both levels and areas of risk. Hence the need for a thorough investigation of the rare serious accidents or near misses that do occur from which there may be significant safety lessons to understand.

Different accidents, common themes

As an independent investigation body, RAIB is well placed to undertake such investigations and also ensure that it focuses on safety improvement rather than apportioning individual blame or company liability. By doing so, it can highlight areas of risk not fully addressed by the industry.

In a recent presentation to the IMechE Railway Division in Glasgow, Carolyn Griffiths, RAIB’s chief inspector of rail accidents, illustrated this point through two quite different derailment investigations. These were a broken axle on a Class 222 Meridian train at East Langton, Leicestershire, on 20 February 2010, and the flange-climbing of a wagon wheel on curved track at Camden Road, London, on 15 October 2013. Fortunately, neither accident resulted in any injuries. However, in different circumstances, both were potential multi-fatality events. As will be seen, Carolyn felt these accidents had common themes.

Twist faults at Camden

Prior to the October 2013 wagon derailment, the track at Camden Road on the Up North London line was in a poor condition. It had opposing twist faults and the section manager had recorded that “it is difficult to express on paper how poor and deteriorating the entire patrol (length) is”. The track-recording vehicle (TRV) had last measured track geometry 46 weeks prior to the derailment. A TRV should measure category 3 track, such as the North London Line, at normal and maximum intervals of respectively 16 and 36 weeks.

20 ft container after repacking [online]

Asymmetrically loaded scrap machines inside 20 ft container – repacked after the derailment to replicate original weight distribution.

Derailment by flange-climb occurs when the ratio of  the lateral force of the wheel flange on the rail (Y) to the vertical wheel load (Q) exceeds a critical limit value which depends on both the coefficient of friction and angle of contact between flange and rail head. This occurred at Camden Road due to the combination of twisted track and uneven wagon wheel loadings.

However this was not the only cause. Wear on the gauge face of the rail and the presence of metal particles indicates that the rail lubricator installed 75 metres before the point of derailment was not fully effective. The resultant increase in friction lowered the critical limit value and so increased the probability of derailment.

A further factor was that there was no check rail on the 187 metre radius curve at Camden Road although relevant standards require them for curves of less than 200 metres on passenger lines. A check rail would have prevented the derailment by preventing lateral force on the flange-climbing wheel.

Hidden hazard inside containers

Although various infrastructure defects contributed to this accident, the report makes it clear that the derailment resulted from a combination of these defects and an unevenly loaded container wagon. The RAIB report notes two similar previous incidents.

Although, as the duty holder, the operator is responsible for safe operation of its freight trains, it cannot check inside the containers which are often customs-bonded. It is therefore difficult to control the risk from unevenly loaded containers. This problem is compounded by the way containers are loaded on the 60 foot container wagons which can take combinations of 20ft, 30ft and 40ft containers which may be empty or fully loaded. As a result, the centre of gravity of the wagon and its containers can be a significant lateral and longitudinal distance from the wagon’s centre, as was the case at Camden Road in October 2013.

A significant part of the RAIB report is devoted to the effects of this asymmetric loading and how this is controlled. With the load in the 20ft container being disturbed as a result of the derailment, it was not possible to directly determine its original centre of gravity (CoG). To estimate the container’s load offset, it was repacked as closely as possible to its original configuration. An assessment was also made on the basis of measurements from a Wheelchex site over which it had passed prior to the derailment. As a result, the container’s CoG was estimated to be offset laterally by between 0.10 and 0.24 metres. Data from a British port indicated that 2% of containers have similar offset loading.

Class 222 Broken Axle at East Langton [online]

Derailed Class 222 bogie trailing wheelset with broken axle.

The derailed wagon was carrying an empty 40ft container of 3.9 tonnes and the previously-mentioned 20ft container which was loaded with scrap machines and had a gross weight of 28.8 tonnes. As a result, the wagon’s CoG was approximately 3.2 metres towards the front from the wagon’s centre line.

The estimated result of all this uneven loading was that the wagon’s leading bogie was carrying 2.7 times the weight of the trailing bogie and the left-hand wheels were carrying between 1.2 and 1.4 times the load on the right hand wheels.

This asymmetric loading, combined with the poor condition of the track and the lack of a check rail, were thought to be the main causes of this accident. Incidentally, the damage to the track, a viaduct wall and adjacent overhead line equipment that were the result of this derailment, closed the Up and Down North London lines for six days.

Broken axle at 94 mph

In Carolyn’s second example, the broken axle on a class 222 at East Langton, in February 2010, occurred on a train travelling at 94 mph when a hollow axle failed inside a final drive. This was the first such known accident anywhere in Europe. This axle had been in service for 920,000 miles.

Subsequent metallurgical analysis showed that it had been subject to a maximum temperature of around 1,100 to 1,200°C at the seat of the gear end (GE) output bearing, causing a loss of axle bending strength and resulting in its fracture.

As this heat destroyed much of the evidence, the investigation had to consider five possible causes. After a process of elimination, it was concluded that the initial cause of the failure was the GE output bearing stiffening up so that it could no longer rotate normally, resulting in the axle spinning inside the bearing inner race. Computer modelling indicated that this could generate a heat input of around 30kW. After a further process of elimination, it was concluded that the most likely cause of the bearing failure was a loose fit between the GE bearing inner ring and axle.

These conclusions were reached with the assistance of a technical group set up specifically for the investigation comprising of RAIB, ORR, East Midlands Trains, Bombardier Transportation, Eversholt Rail Group, Serco (consultant for failed gearbox strip down and axle investigation) and ESR Technology (consultant for bearing investigation). This group also oversaw various metallurgical examinations and rig testing of final drives with various low GE bearing interference fits. It also investigated six other powered axles with between 0.67 and 1.2 million miles service that were found to have poor GE bearing fits and so could have been potential failures.

Loss of interference

Class 222 FD and Gearbox [online]As this was an unprecedented failure of a normally highly-reliable safety-critical component, it was important to understand how a bearing could have lost its interference fit. The design intent was that the inner rings of both GE and non-GE bearings should have an interference fit on the axle of 75 -120μm (1μm = 0.001 mm). However, on this axle, the GE bearing is immediately adjacent to a gear wheel with a heavier fit of 243 – 309μm. Mathematical modelling indicated that this heavier interference fit would shrink the adjacent seat of the GE bearing by between 24 and 30μm on diameter for a hollow axle. The corresponding amount of shrinkage for a solid axle would be between 5 and 10μm.

When the axle was made in 2004, the manufacturer did not have a company procedure for dimensional checking as it does now. The final drive manufacturer also did not check axle bearing seat dimensions. On the failed axle, the undamaged non-GE seat was found to be undersize and tapered. This indicated that possibly the GE bearing seat, which had been damaged in the failure, may also have been slightly under size.

Although the GE output bearing’s interference fit on the axle was probably less than that specified, the axle had run almost a million miles over six years before its failure. This is indicative of a progressive loss of interference fit. The report explains that this could have been caused by a combination of two mechanisms. The first is inner ring growth, a gradual and normal increase of the bearing bore occurring over time due to the bearing’s metallurgy, its operating temperature and loading. The second mechanism is fretting – wear and corrosion that occurs when there are small relative movements between two surfaces in loaded contact.

Evidence of fretting was found on several other GE  output bearings in the class 222 fleet. Fretting wear combined with inner ring growth could have reduced the interference fit to a level at which there would be circumferential slip, which then accelerates the loss of fit.

Common themes – whole system

Although a broken axle and an unevenly loaded wagon on twisted track are two quite different derailments, they have common aspects. One of these is the requirement for a whole system approach. The Camden Road derailment was caused by a combination of track and train issues for which the infrastructure controller and freight operating company had separate responsibility.

In its report on the Camden Road derailment, RAIB found that neither company had quantified the risk from unevenly loaded wagons. As a result, it suggested that the industry’s approach to the understanding of risk for asymmetrically loaded wagons had not been effectively co-ordinated and, consequently, the level of risk and required mitigation measures were unknown.

The Class 222 final drive involved in the East Langton derailment was supplied to a specification by the train manufacturer which had overall design responsibility for the train. Its quantified risk assessment did consider the risk of axle failure from an overheating final drive. However, it concluded that having the final drive produced by a reputable transmission manufacturer to industry best practice, a record of satisfactory service on similar fleets, and specified maintenance procedures provided sufficient mitigation.

In fact, while the Class 222 axles were hollow and relatively thin-walled (45 mm), the interference fits for solid axles had been applied. The bearing manufacturer was unaware that its products were to be fitted to a hollow axle and no analysis had been done to assess the effect of the gear wheel interference fit on the adjacent bearing seat.

Common themes – traditional standards

Standards are often derived from lessons learnt from previous accidents. However, such lessons do not always remain relevant.

Bearing Cutaway [online]

In common with other railways, track twist is measured over three metres. This may have been an appropriate derailment mitigation when there were numerous three- metre wheelbase four-wheeled wagons. However such wagons were discontinued many years ago. The derailed wagon at Camden Road had a 14-metre bogie spacing with two metres between the axles on each bogie. When the track was measured after the derailment its twist, measured over three metres, was found to exceed the seven-day action limit but was within the 36 hour action limit. There are no corresponding limits for twist measured over 14 metres.

For many years, oil sampling has been used to determine potential failures yet, three days before the East Langton derailment, the failed final drive’s oil sample was well within the then-specified iron content caution limits. However, when the oil samples were retrospectively analysed to determine the cumulative iron over the whole life of the final drive, it was found to be significantly greater than other final drives which had loose GE output bearings.

Furthermore, during the investigation it was found that oil samples taken from final drives with loose GE output bearing fits had a significantly darker colour than normal oil samples, which indicated that colour may be a useful additional parameter to monitor in oil sampling. Prior to the derailment there was no requirement to assess the colour of final drive oil samples.

The real lessons

For those with a technical interest in the issues that led to these derailments, the 69 and 93 page RAIB reports into the Camden Road and East Langton derailments are a fascinating read. They can be found at www.raib.gov.uk and they include appropriate recommendations to prevent recurrence of the causal and underlying factors.

As a result of the work done by RAIB to investigate these derailments and publish reports that clearly show their causes, no doubt much has been and will be done to prevent the recurrence of similar accidents. However the real challenge is preventing apparently-unpredictable rare accidents that could have serious consequences.

In part, this requires acceptance of the common themes of these derailments. One of these is that the required mitigation measures would have been evident beforehand had a robust analysis been undertaken of the interaction between all associated technical factors. The other is the need to challenge standards that may no longer be appropriate or provide all required mitigation.

In the RAIB 2014 Annual Report, Carolyn Griffiths considered that its investigations may bring new focus to areas of risk that are not always evident to the industry. These accident reports support this view and so demonstrate the value of an independent investigation body.

The transition to ERTMS in the UK

Oh dear, readers will say, not another ERTMS article! Yes, but this is inevitable as the UK gets ever nearer to introducing a main line deployment of the technology. Valuable lessons were learned from the Cambrian line early deployment project but that was limited in scope and many other factors need to be considered before the nation can be confident the system will deliver the predicted benefits and reliability.

A recent conference in London organised by Waterfront managed to attract speakers from all elements of the spectrum, ranging from the advocates who believe that ERTMS will solve all capacity problems, through those that recognise the advantages but see the implementation as difficult, to a few prophets of doom who predict it will be a costly failure.

The up-beat message

Andrew Simmonds, the chief rail systems engineer for Network Rail’s Digital Railway, pronounced ERTMS (the European Rail Traffic Management System) to be a major driver for economic growth. Passenger number forecasts are rising by 3% per annum, meaning that the current 1.6 billion journeys per year will have risen to three billion by 2035. Some examples of the predicted increase per route are WCML 201%, Thameslink 171%, GW Suburban 108%, South West Trains to Woking 154%, Southern Suburban to Caterham 149%. Handling this capacity is not just aligned to signalling but will need to embrace customer interfaces, ticketing, journey planning, infrastructure operations and the whole operational framework.

ERTMS (especially the ETCS – European Train Control System – element) is very much part of this and should yield around a 40% increase in capacity. Spin-offs include a 10% reduction in delay minutes through better reliability, an 80% reduction in SPADs (signals passed at danger), a 50% reduction in the need for lineside work, energy savings from better regulation of trains and improved utilisation of maximum line speed. Needing to go hand in hand with Traffic Management Systems (TMS), ETCS will be introduced on a route-by-route basis with the initial plan covering the period 2019 to 2029, structured around three main phases.

Phase 1 – development of initial routes; primarily Thameslink plus TMS at Cardiff and Romford and connected driver advisory systems (C-DAS);

Phase 2 – provision of electronic compatible interlockings, removal of lineside signals, a robust telecom layer in the ROCs (rail operating centres) and provision of ETCS infrastructure and cab fitments;

Phase 3 – more of the same but progressing to 100% roll out and start of classic train detection removal.

All very impressive but will it go to plan and will the necessary finance be available in CP6/7 and beyond?

More detail emerged on the ECML rollout, itself covered in a Rail Engineer March 2015 article (issue 125). Whilst that primarily looked at the technical implications, Paul Boyle from Virgin East Coast explained how preparations are underway for ETCS.

Visits to Austria, Denmark, Netherlands, Norway, Spain and Portugal have highlighted 13 elements of operation ranging from train fitment and GSM-R provision through to TMS, track worker safety and station operation. The ECML will be the first main line to totally migrate to ERTMS, Great Western being an overlay project. Four constituent activities have to be tackled – operations, safety, fleet and control.

Driver training has already started using simulators with the DMI (driver-machine interface) layout now available on smartphone or tablet screens. A high percentage of Virgin East Coast staff will engage with ETCS in some way and an ERTMS Awareness Day has recently been held at Kings Cross for all operations staff.

Train fitting will require contracts to be let, trains to be released from service and a full change management plan put in place. The programme to fit the Class 43 HST power cars, the Class 91 electric locos and the Class 82 DVTs will run up to 2020 in readiness for the time when lineside signals are removed.

All very impressive but will it go to plan and will the necessary finance be available in CP6/7 and beyond?

More detail emerged on the ECML rollout, itself covered in a Rail Engineer March 2015 article (issue 125). Whilst that primarily looked at the technical implications, Paul Boyle from Virgin East Coast explained how preparations are underway for ETCS.

Visits to Austria, Denmark, Netherlands, Norway, Spain and Portugal have highlighted 13 elements of operation ranging from train fitment and GSM-R provision through to TMS, track worker safety and station operation. The ECML will be the first main line to totally migrate to ERTMS, Great Western being an overlay project. Four constituent activities have to be tackled – operations, safety, fleet and control.

Driver training has already started using simulators with the DMI (driver-machine interface) layout now available on smartphone or tablet screens. A high percentage of Virgin East Coast staff will engage with ETCS in some way and an ERTMS Awareness Day has recently been held at Kings Cross for all operations staff.

Train fitting will require contracts to be let, trains to be released from service and a full change management plan put in place. The programme to fit the Class 43 HST power cars, the Class 91 electric locos and the Class 82 DVTs will run up to 2020 in readiness for the time when lineside signals are removed.

Learning from the Cambrian

The Cambrian project, introduced into service initially from Harlech to Pwllheli in February 2010 and on the whole line from Shrewsbury to Aberystwyth / Harlech in March 2011, was reported on at the time in Rail Engineer. It was not an easy introduction and the train service suffered in the early days. Even now, the ETCS system is not as flexible as the RETB technology that preceded it. Matthew Phillips from Interfleet told of the lessons learned and how these will be used for future deployments:

»  The project had been engineering rather than operations led;

»  Operational changes were underestimated with new rules not reflecting the real world;

»  The operational benefits were not optimised;

»  Insufficient focus was given to simulation while sub-system integration proved very complex;

»  Approvals for on-board equipment need to be phased so as to keep trains in service;

»  ETCS reliability (especially on-board equipment) has been worse than expected;

»  Whole-life support was not part of the contract.

The cost of retrofitting the Class 158 DMUs (by Interfleet) and the Class 97 (ex-37) locomotives (by Transys) proved very expensive in terms of design and approval costs, especially as the trains had minor variations between units. It took 10 days out of service to fit a Class 158.

The freight dimension

Whilst much of the ERTMS roll out is focused on the passenger railway, the impact on the seven freight operating companies (FOCs) is of vital importance. Simon Gledhill from DB Schenker quoted the statistics: 950 locos of 19 classes, 20,000 wagons and around 5,000 staff. It is a growing business, with £2 billion invested since privatisation, but is very competitive, performance sensitive and has changing market dynamics. The annual turnover is £30 billion with 1 in 4 containers carried by rail plus 50% of the fuel used for electricity generation. Thus any technological change that even minutely disrupts this flow is regarded with suspicion.

ERTMS awareness exists but, for freight, it cannot be linked to any one route. It must take account of the variation in the length, consist and weight of trains, plus shunting and banking activities, and the whole freight operation needing to be based at multiple locations. Locomotive fitting will be crucial and should follow the pattern of ‘first in class’ (FIC) fleet fitment, training and driver familiarisation. Braking data variability is vital and needs a major refinement over the individual expertise used at present.

An implementation programme running from 2015 to 2021 is being developed with operating rules revised by 2016 and fitment beginning in 2017. ERTMS teams within the companies are being assembled. The transition from lineside signals to in-cab data will be difficult, but the FOCs and Network Rail are working well together, recognising that freight has to be part of the National Operations Strategy (NOS).

Passenger train fitment

This is probably the biggest challenge in the ERTMS introduction. Andy Norris from CPC Project Services and the project director for the ETCS National Joint ROSCO Project (rolling stock company) explained the main elements in determining how fleets are equipped. The national deployment map is the starting point but alongside this are franchise considerations and whether these are existing, direct awards or in the course of development. Any delay to franchise letting will have ETCS implications.

There are no spare trains in the UK so fleet fitment will take many years. Procurement of equipment is needed now for fleet fitting over five to six years. Test facilities will be available by April 2016 at Old Dalby for electric trains and Tuxford for diesel locomotives. Network Rail is funding the FIC design and installation with fleet fitment funded primarily via franchise arrangements but with Network Rail backup. Open access operators have to organise their own funding in conjunction with Network Rail.

The progression is to obtain around 30 kits for FIC design and approval, and 1,465 kits for fleet fitment. A maximum of 11 FICs can be handled at any one time, recognising that some classes are essentially similar (such as 158/9, 375/6/7/8, 175/180), and a programme is in place for every class of passenger train. It will be a TOC decision as to whether elderly trains such as Pacers and 313s are fitted.

The TOC requirement is to have no loss of seats, cycle or storage space and thus the kit has to be distributed in roof spaces, under seats or underfloor, which will add cost. The Hitachi product (issue 125, March 2015) is already designed this way. The work will be let competitively and contracts must include aftercare support.

Additional challenges include:

» Getting ETCS software to baseline 3 – Europe is dragging its heels on this;

» Funding certainty and timing;

» Cyber security protection;

» Engaging the supply chain with the urgent need to place orders;

» Skilled resource shortage for both UK and European workload;

» Reliability of the installed kit; » Technical options for DMI.

The Department for Transport will need to enhance clauses in franchises for ETCS commitment. There are many stakeholders including the Government, TfL and Transport Scotland but these and the ROSCOs are working well together currently.

The ORR perception

With ERTMS involving many parties, the ORR is only too aware of its complexity, so says Anna O’Connor, head of projects. Industry does not have an unequivocal shared vision and, even if it did, implementing ETCS technology would still be a difficult task. There is much uncertainty on the time frame and lots of ambiguity, making the project akin to a patchwork quilt. The main risk seems to be with the multitude of interfaces raising big questions on the ability of Network Rail and its suppliers to deliver the programme, particularly when engineering resources are in short supply.

Safety issues have to be all-important and safety legislation is also complex involving ROGTS, Safety at Work, CDM, Workplace Regulations, EMC, Interoperability and others. The detail within these is important but should not be used as an excuse for delay.

In-cab computer-based signalling is a major change and requires four basic steps to be understood:

»  Need to assess the risk of the change with associated design optioneering;

»  How far can the risks be eliminated and useof ALARP;

»  Consideration of the specific statutoryrequirements within the work packages;

»  Identify appropriate opportunities -ERTMS should not be a digital like-for-like replacement and the integration of level crossing operation and improved worker protection should be part of the package.

Other opportunities should embrace the accuracy of braking curves, maybe with real time monitoring of braking performance. A list of possible applications should be prepared.

Lessons from Europe

Anyone who thinks that European railways have had an easy ride with ERTMS should think again, according to Kimmo Oostermeijer from Leigh Fisher. Despite significant funding, the deployment is behind schedule, project management has been un-coordinated and appropriate measures have not been taken to prevent delay.

One key lesson is that ERTMS is more about organisation and economy rather than technical. The dictate on TEN-T (trans-European transport network) corridors demands safety, system performance and interoperability to yield the benefits for passenger and freight customers. The risks are higher when implementing the system on an existing railway, mainly due to the retro-fitting of trains, introducing new rules and track worker safety.

The UK may benefit from not being first in the queue. The ORR noted that Sweden has benefited from creating a Systems Authority to make the necessary strategic decisions. Network Rail has considered this in the past but without making any progress. Maybe it should be resurrected, as the lack of a ‘Directing Mind’ appears to be a significant gap in its organisational structure.

Other factors

With the significant number of parties involved, the need for robust contractual frameworks is essential and associated legal safeguards must be in place. Tammy Samuel from Stephenson Harwood listed some of the necessary measures that must be considered and decided:

» Purchase of equipment; what if it is late and/ or doesn’t perform?

» Liabilities imposed by end customers;

» Funding of downtime of trains through failures and proving of cause, interface between track and train and associated delay attribution;

» Who is the customer and the supplier – ROSCO, TOC/FOC, Network Rail?

» Who is responsible for approvals and commissioning?

» How will major system upgrades be managed?

» Intellectual Property and ownership plus issue of licence and the extent of this.

Cyber security is another issue and an assessment should be made of the places where this can occur. Julian Gill from Thales stated that nine possible threats were identified, the main ones being end-to-end communications, train-to-balise interactions, denial/traceability of keys, secure usage of components and the common numbering system within GSM-R. The classic fail-safe criteria of ‘if in doubt, stop the train’ will not necessarily be a workable solution. Seven layers of defence were identified ranging from data configuration through to policies and procedures.

Overall, the conference gave a fascinating, if not slightly worrying, exposure to the main line introduction of ERTMS/ETCS. If nothing else, it achieved a wider awareness of what might go wrong. Many eyes will be watching the first deployments, both for infrastructure provision and train fitment, and the readiness by which the almost inevitable unforeseen situations will be identified and resolved.

Scarborough Bridge – Monte Carlo or bust

It was a very ordinary structure, comprising two spans across the Ouse to the north of York Station. Its replacement, installed over the February half term, is also pretty average. You might wonder then why I’m wasting your time telling you about it, or indeed why the project cost £6 million. Thing is, this wasn’t a typical bridge reconstruction. The key to its delivery – overcoming the site constraints – had been turned in advance of the nine-day blockade which saw the new steelwork craned into place. That’s why I can write this beforehand, leaving the project’s denouement to be conveyed in a few dramatic pictures. And given the size of the crane, I’m confident they will be very dramatic. Judge for yourself.

Comings and goings

Head towards the coast from York and the first structure you’ll encounter – just 40 metres off the end of Platform 4 – is Scarborough Bridge, unsurprisingly identified as YMS/1. When the route opened in 1845, trains crossed the river on timber arches, the sockets for which are still visible in the masonry pier and abutments. The latter incorporate archways allowing pedestrians free access along the banks. The spans were rebuilt in 1875 to comprise four 22 metre wrought iron main girders, ornamental lattice girders to both sides and a timber deck. The east side features a footbridge, tied to the main structure but effectively independent.

Corroded ironwork – for which the city’s vast pigeon population must bear some of the blame – and rotting timbers are only to be expected after 140 years, but there eventually comes a need for intervention. The bridge is not heavily trafficked (two First TransPennine Express services use it every hour) but its RA0 load rating meant bridge examiners had to be in attendance whenever a steam special crossed. And its movement was not kind – often fatally so – to the bats which roosted in its nooks and crannies. Studies concluded that the baseline effort involved in doing any major work on the structure made reconstruction the most cost-effective option, rather than just strengthening what was already there.

The four new weathering steel decks, manufactured in Chepstow by Mabey Bridge, are U-shaped in section and each is supported by a pair of plate girders. Whilst not aesthetically pleasing, the decks will demand no substantive maintenance for 60 years. In any case, they are screened by newly-fabricated latticework on the west side – emulating the original – and the existing footbridge to the east.

Story Contracting, the principal contractor, pinned down the buildability early by working closely with Network Rail’s in-house design team. The decks are swan-necked, sitting on shallow (200mm) cill units from Moore Concrete and thus avoiding the need to break out any stonework. The arrangement brings with it full RU loading. The pier and abutments remain in good condition although they have benefited from some stitching. Added on the west side is a cantilevered walkway to provide a safe crossing route for track staff.

And that’s it, except…

4B-DecksArrive(MulhollandMedia) [online]

The final frontier

York’s central area is compact – a function of its historical roots – with tight streets and space at a premium. Valuable railway land has been sold off for housing development, a reality which prevents larger vehicles from reaching the triangle between the East Coast main line and the York-Scarborough. This area could then only act as a secondary compound for the works, with bulk materials driven onto site during possessions of the ECML.

The main focus was on Marygate car park, a council-owned facility north of the river which was taken-over in phases. The railway fortunately forms its western boundary. Network Rail’s project team established a ‘command room’ here last November, cohabiting with Story. Although the car park is fairly generous, access can only be gained via a narrow street off the A19 and involves negotiating a sharp right-hand turn with buildings on each corner.

Separating the south side of the car park from the river is a row of houses and wide pedestrian walkway. Alongside the end-terrace – now a bed and breakfast – is a gap of about 10 metres to the toe of the bridge’s approach embankment. It was in this gap that a crane would have to operate, the longest lift being 75 metres over the river to place the cill unit onto the southern abutment.

Under the microscope

Forget the Romans; York is a railway city. The train operators and Network Rail have a substantial presence here and those members of their workforce who use the footbridge were no doubt inconvenienced by the need to close it. So the job was very visible, adding to the burden on the project team’s shoulders. Arguably, the temporary loss of the footbridge was felt more keenly than that of the train service.

It is a busy thoroughfare, forming a key route to the station and nearby businesses. In mitigation, there had to be a big hit of publicity in the York Press, together with signage on the ground and letter drops.

Also affected from time to time was the Ouse, with a full closure in place during the main works and partial closures for specific activities such as the erection of a scaffold, supplied by the Wood Group (formerly Pyeroy). This comprised a footbridge onto which the lengthened S&T cabling was slewed as well as providing access across the river when the footbridge was blocked off; working platforms were also wrapped around the pier and abutments. To combat the threat of flooding – one of the project’s two biggest risks – debris boards were installed around its base, designed to cope with a river level reaching the top of York’s flood defences.

For years, trains have being sharing Scarborough Bridge with a 16-inch main owned by Yorkshire Water. Typically, stats companies charge substantial sums for the removal of their services and rarely do so at a pace in sync with a project timeline. However an agreement was already in place here that allowed Network Rail to request the main’s prompt removal, at Yorkshire Water’s expense. To fulfil this obligation, the sections at either end were disconnected and removed, leaving the remainder to be lifted out with the lattice girder.

5-CraneInDeck(MulhollandMedia) [online]

In the railway’s early days, members of the public accessed the bridge by stairways within the abutments, emerging between the two tracks and then crossing whilst trains passed on either side. The inevitable happened on more than one occasion, eventually prompting the installation of the footbridge. But the stairways left voids within the abutments which have now been filled, not with foam concrete but a structural resin called Benefil, produced on-site from a liquid base. A bit like Heineken, it gets into places other materials cannot reach.

High hopes

Identified as the right machine to fulfil the big lifts was Ainscough’s Demag CC 2500-1, configured with an 84-metre boom and thus reaching 14 metres higher than the central tower of York’s nearby Minster.

A crawler crane, it boasts a 500-tonne capacity and superlift attachment which, for some loads, can itself weigh up to 250 tonnes. It comes to site on the back of 17 wagons and takes three days to build with a 200-tonne crane. You can understand then why this process was begun a week ahead of the blockade to minimise the possibility of disruption due to high winds, the project’s other big risk.

For the crane to reach its two operating positions, a ramp had to be provided from the corner of the car park, requiring the railway embankment to be cleared of vegetation over a distance of 75 metres. However, as all the trees were covered by preservation orders, consent had to be sought from the Council and a replanting scheme developed in liaison with Bootham 2025, a group which oversees the local conservation area. A crane mat was installed at the top of the ramp comprising 200 piles, sunk 12-18 metres and arranged in two strips to accommodate separate pile caps for each of the crane’s tracks.

To ensure optimum efficiency, the sequencing of lifts for the bridge removal and installation was planned methodically by the Story team to minimise the number of changes in the crane’s position and loading.

A merry dance

The four bridge decks journeyed to site two days before the blockade got underway. To help this difficult operation, they were jacked up on their trailers, allowing them to sit further forward than would otherwise be the case. Even then, as a result of their 24-metre length, they had to be reversed down Marygate – the narrow street off the A19 – for 300 metres in order to take the right-hand turn as a left-hander, approaching it face first. Marygate was matted out for these manoeuvres, stripped of lighting columns and other furniture, and a dwarf wall dismantled in front of a pub.

Careful consideration had to be given to choreography within the compound. As well as the new decks, the Demag CC 2500-1 and its service crane, there was a need to carry the old decks away to be cut in half and loaded onto wagons for removal from site, involving the use of a third crane. This was added as an insurance measure relatively late in the planning process to ensure nothing impacted on the main crane’s activities.

8-Trackwork [online]

Nailed down

The project’s preparedness for the blockade was the subject of regular reviews from a year out. Each element within the programme was analysed using Monte Carlo simulations to calculate the probabilities of different outcomes occurring. From this, a confidence level could be established for the job finishing on time. Scarborough Bridge passed the 95% threshold despite the uncontrollable concern of crane operations being brought to a standstill by wind speeds exceeding 25mph, common features of a British winter.

At the start and end of the blockade – which ran from 23:40 on Friday 13 February to 05:25 on Monday 23rd – Rules of the Route periods were used to make signalling modifications, ensuring the occupation of track circuits by the project’s RRVs did not affect movements on the East Coast main line. The points were clipped and scotched.

Beyond that, I’ll leave the pictures to tell the story. There was nothing unique to report about the removal and installation sequence: it was a bridge replacement like many others. If all went to plan (and someone turned up with a camera), this story should look rather eye-catching. I will, though, report the high praise of Story by Network Rail’s scheme project manager, Darryl White: “The magnitude of this project has brought with it sizeable challenges and the Story team has lived up to its reputation of a superb standard of delivery.”

Coming together

Two other things are worth flagging up. The York-Scarborough meets the line up from Hull at Seamer, 40 miles away; the blockade encompassed all of it. To maximise the opportunity afforded, the call went out to find other projects that could be achieved over the nine days, with around two dozen going ahead: canopy cleaning, culvert relining or reconstruction, point-end replacement, level crossing works, spot resleepering and wholesale vegetation clearance to reduce leaf-fall problems.

The cost of these jobs was significant – around £3 million – but by pulling them into the blockade, this price tag came close to being covered by the £2-3 million worth of efficiency savings that would otherwise have been spent on access arrangements and piecemeal overnight/weekend working. The ambitious intention now is for no additional possessions to be needed on the route during the whole of CP5.

And then we should take our hats off to team member Eamon McAuley who literally built the bridge single-handed…albeit in Lego. It was remarkably detailed – including the track layout and little orange men with chainsaws – and could be deconstructed and rebuilt to follow the lifting sequence. Sitting as a centrepiece in the conference room, it proved more useful than a PowerPoint when explaining the challenges to visitors and stakeholders.

Yes, this really was a model project.

Photos courtesy of Mulholland Media

Issue 125 – March 2015

Supplying the next generation of signal engineers

As we steadily approach the conclusion of the first year of Control Period 5 (April 2014-March 2019), the forecasted peak in engineering shortages – predicted to hit the hardest around 2016/17 – is creeping ever closer and is likely to affect the whole rail industry.

NSARE (the National Skills Academy for Railway Engineering) released its report ‘Forecasting the Skills Challenge’ in early 2013. This predicted that, in order to overcome the subsequent difficulties, around 10,000 people would be required for industry training between 2014 and 2018 – predominantly in the signalling sector.

Linbrooke steps forward

This set a challenge for the industry as a whole and various initiatives were adopted. One of the first organisations to respond was Linbrooke Services of Sheffield and the result is its newly- opened, state-of-the-art, National Training Academy (NTA).

With an aging workforce and the demand for signalling testers being at an all-time high, the National Training Academy is primarily geared up for providing training for signalling works testing. The new site’s authentic platform and tracks incorporate various styles of signals, point operating equipment and train detection and protection equipment. These provide a realistic and accessible set-up for safe and practical training from basic appreciation right through to high-level modular testing competence. In order to enhance the learning experience, the signalling facility also incorporates associated power and communications equipment.

A combination of legacy and traditional equipment, as well as the flashing aspects associated with high-speed turnouts, gives Linbrooke’s new academy the ability to offer more than just theoretical and on-par practical training. Operating under the ntrs banner, a wide variety of ‘off the shelf’ and bespoke courses are on offer. Indications are that the academy will see a steady influx of fresh apprentices and trainees as well as industry organisations looking to upskill their workforces.

Over the next three to five years, Linbrooke and ntrs intend to register 100 apprentices from the local community alone – with others travelling from further afield to take advantage of the new centre’s expertise.

signalling 2 [online]

Experience and expertise

The training team has a wealth of knowledge and expertise in signalling systems so is able to offer a basic understanding across the complete signalling spectrum. This ensures that graduates can recognise and properly operate all pertinent systems nationwide. Under one of the industry’s acknowledged experts, Mike Smith, Linbrooke can now offer both traditional and exclusive courses. These include Signalling Works Testing courses from Mod 5 (Test Assistant) through to Mod 3BL/4 (Functional Tester) as well as the exclusive testing management training course Mod 1 (Tester in Charge) and training in SWT G110.

Further enhancements to the facilities are already in the pipeline. The centre will soon have an integrated interlocking to further train principles testers.

With the majority of other training facilities concentrating their efforts on specific subdivisions of signalling, Linbrooke’s National Training Academy is unusual in its widespread offering of signalling knowledge and experience, as well as telecommunications and power, so providing high-calibre training across the board. While opening the new academy, Pete Waterman – music entrepreneur, railway enthusiast and Patron of NSARE – pleaded for ‘more centres like this please’.

The Secretary of State for Transport, Patrick Mcloughlin, also endorsed the new National Training Academy as an asset to the signalling sector, the industry and the nation.

“In order to build a world-class railway you need a world-class workforce,” he said. “With an engineering industry that is recognised around the globe, South Yorkshire is the perfect home for the trackside National Training Academy.

“As part of our long-term economic plan, we’re investing record amounts in the UK’s railways by generating jobs and training opportunities. This new academy will ensure the local people in Chapeltown see the benefits of this investment, as well as developing a lasting legacy for the future. I sincerely congratulate Lee Hallam and everyone involved in bringing this project to fruition.”

Midland Metro undermined

Railway civil engineers, in the UK at least, have always been concerned about unknown or unpredictable hazards affecting their infrastructure. Buried abandoned mine shafts are a classic example, and there are well known photographs showing dramatic accidents caused by collapses under the tracks. Rail infrastructure operators are generally well aware of that particular risk and take appropriate measures.

The Midland Metro recently encountered a slightly different hidden danger that had a major impact upon operations and track renewals. On this occasion, the culprit was not a hidden shaft but the remains of an old mine working, believed to have been what is known as a bell pit.

Abandoned workings

Bell pits were used in the early days of the industrial revolution and probably a long time before that too. Each pit began as a short vertical shaft, dug from the surface down into the coal seam or other stratum to be mined. The miners then set about excavating the desired mineral from around the base of the shaft, working outwards and so forming a bell shaped excavation. The excavated material was hauled up the shaft to the surface for use in industry.

Created with Nokia Smart Cam

Clearly this was a dangerous business as the ground above the pit was often left unsupported, and it must have been a fine judgement deciding when to abandon a pit before it collapsed onto the miners!

In the Black Country, bell pits were commonly used to obtain coal or iron ore. When one pit was determined to be worked out or unsafe, another would be started nearby until no more valuable material could be safely and economically recovered from the site. It was quite usual to just walk away from worked out pits, leaving them to remain standing or to collapse, as nature and weather dictated. It was not common practice, at the time, to document the location of these pits, and even if it had been it is likely that such records would no longer be available today.

Modern consequences

Time to return to the present, and to the Midland Metro in the centre of Wolverhampton late last year, close to the stop known as ‘The Royal’, the last stop before the St. George’s terminus in the city.

As part of a project upgrading the Metro for the introduction of new and longer Urbos 3 trams from CAF, a new crossover had been laid in just south of ‘The Royal’. A life expired old crossover north of the stop was redundant as a result, and work began removing it and excavating out the foundation slab upon which it had lain.

All this was encompassed in a £4.5 million track improvement scheme lead by Centro, the region’s public transport co-ordinator. Main contractor for the works was Graham Construction, with specialist railway works undertaken by Rhomberg Sersa.

It was at this point that the project team got a nasty surprise. Paul Griffiths, metro programme director for Centro, recounted that, as the excavation proceeded, it became clear that under the slab was a lot of rubble, full of voids and unstable. Ground proving radar surveys had not detected this (probably because of the existence of the reinforced concrete track slab, it is thought), and neither had desk studies of existing records of the area and of the original Metro construction.

Reinstating the Metro over the top of this without proper remedial measures was clearly not an option. Whilst investigations were undertaken to establish the extent and depth of the rubble filled void, Centro began seeking advice about what they had found and how it might be made safe. Consultant AECOM was engaged to provide expert advice and Centro also consulted other metro operators, through the UITP and UK Tram.

The problem lay in an awkward location, since at the affected location the tramway runs between the two carriageways of the A41 Bilston Road between Steelhouse Lane and Hospital Street. The proximity of the highway restricted any engineering activities because of the risk of damaging the road. With the tramway shut, closing the road and further restricting options for commuters and other travellers was not an option.

IMG_20150211_130301 [online]

Investigations eventually determined that the void extended to a depth of about 12 metres, covering an area about 54 metres long and 20 metres wide. With the size of the problem determined, activity shifted to consideration of possible remedial options.

What to do?

Amongst those considered was sheet piling right around the void, excavating the rubble fill and backfilling with suitable material, properly compacted. This was dismissed as too expensive and time consuming. A similar conclusion put paid to the option of bridging over the void with a slab carried upon bored piles inserted down to sound ground.

Other options considered and rejected included grouting up the existing fill, and the idea of laying in ballasted track over the rubble, accepting that regular track maintenance by tamping would then be essential for many years.

The solution eventually adopted involved covering the existing fill with a geotextile to prevent the migration of fines, then layers of geogrid separating layers of compacted hardcore, all supporting a 5 metre wide reinforced concrete track slab. AECOM recommended Wrekin’s E’GRID 3030L or an equivalent medium loading (100kpa or 12 tonnes axial load) biaxial geogrid.

The work obviously involved a certain amount of excavation of the existing fill so as to get the correct levels for the final slab, but this excavation was relatively shallow and presented no risk to the adjoining highway.

Major changes due at Waterloo

Since Eurostar moved from Waterloo to St Pancras, the International platforms have lain mostly unused. This despite the fact that Waterloo is London’s busiest terminal with 98 million passengers in 2013/14 and a train arriving or departing virtually every minute during peak times and it could badly do with the extra capacity.

However, that will soon be put right as an agreement has been reached between the South West Trains-Network Rail Alliance, Skanska, Colas Rail, AECOM and Mott MacDonald to scope out plans to boost capacity at London Waterloo and other inner London stations. These detailed plans will then be submitted to the Office of Rail Regulation and Department for Transport.

The agreement aims to develop detailed plans, including the reopening the former Waterloo International Terminal to be used regularly by commuter services and lengthening Platforms 1-4 to allow 10-car services to run on suburban routes for the first time ever. The aim is to boost peak time capacity by 30 per cent by 2018.

Skanska’s James Richardson, speaking on behalf of the consortium of contractors, commented: “An investment of this size is excellent news for rail passengers in the region and, of course, an exciting opportunity for our alliance team. Working through a unique collaboration model, we will be able to combine and integrate the skills and expertise of a strong supply chain to deliver this challenging programme.”

RINM Asset Viewer

Senior readers may remember Euston House as the headquarters of the British Rail’s London Midland Region and subsequently HQ of the British Railways Board until completion of privatisation when it was vacated by the railway.

This modernistic-style building, standing just across Eversholt Street opposite the eastern entrance to the station, was built in 1934 as the headquarters of London, Midland & Scottish Railway Company. Construction of the 150,000 sq ft of office space took just 11 months from site possession to occupation using a ‘fast track’ construction method.

Today the building once again plays host to the railway industry and is headquarters of the Digital Railway, the concepts of which were explained in issue 123 (January 2015).

Network Rail, in conjunction with IT consultancy CSC, recently hosted a demonstration at Euston House of how the RINM (Rail Infrastructure Network Model) Viewer, a sub-system of ORBIS (Offering Rail Better Information Services), is placing quality rail asset data into the hands of a mobile- enabled work force.

ORBIS, a £330 million five-year programme to create a detailed digital model of the UK’s rail network, is one of Europe’s largest rail infrastructure transformation programmes. Launched in 2012, the programme began a digital revolution of the UK’s rail infrastructure to help manage assets more efficiently, cost effectively and safely and is predicted to save up to £1billion over the next decade.

Through the introduction of apps and tools specifically designed to capture high quality asset data and new ways of viewing the railway, Network Rail is delivering the resources to meet these aspirations. CSC’s partnership with Network Rail began with an IT outsource in 2007 and the relationships and engagements have constantly expanded since then, both within IT as well as within the business. In October 2013, CSC became the systems integrator for the ORBIS programme which is managed within the Digital Railway Directorate.

Quality data at the heart of decision-making

Network Rail director Steve Dyke described Asset Information (AI) ORBIS as a programme of asset information data and services capability enhancement that provides a vital enabler for condition-led asset policy implementation. This enables customers to manage their asset base for less, and exploit existing railway system capability better.

ORBIS is principally an infrastructure knowledge service that will collect, evaluate, collate, analyse and communicate intelligent data to the business in a way that aims to put quality asset data at the heart of decision-making in Network Rail. The chosen method of data movement originates from the National Criminal Intelligence Service. Data may be presented to planners, engineers and technicians on desktop, laptop and mobile devices. The latter are seen as essential tools for the guys and girls in orange with some 10,000 iPads having been issued.

Aerial Survey - Oblique 1 [online]

RINM goes live

David Moran, solution lead for CSC, gave a brief introduction to the Geo-RINM, an enhanced visualisation tool for the British rail network. The Viewer is a critical tool that will assist users from across Network Rail (and eventually external partners) by providing better worksite familiarity during pre-work planning, mobilisation and early design stages. This will reduce overall expenditure on surveys and, by minimising the amount of time required trackside, it will further increase safety when working on the railway.

A key source of information that will go into the Geo-RINM Viewer is the National Aerial Survey which the ORBIS programme undertook last summer and is described below. The programme is also creating an underground services geospatial data layer (Network Rail and third party) and is in the early stages of defining the end-to-end processes for the exchange of asset information when performing maintenance or major infrastructure projects. The project team will continue to work closely with a range of people and teams across Network Rail to plan future work based on business value and prioritisation.

A new view of the railway

Using geospatial technology, the ORBIS team has been building a logical model of the railway that will provide a detailed, Google-like map of all assets. Taking data from a range of sources, including images from existing master asset registers and aerial surveys, RINM will create a clear picture of the entire railway network and how it relates to the wider environment – from roads to power networks.
RINM will support the connection between the worlds of asset management, operations and maintenance, enabling staff to understand the relationships between assets more accurately – how track links to signalling then into E&P and finally into telecoms. This will improve access to information across the network and aid quicker, safer decision- making. RINM will be delivered through seven phases in structured packages to ensure safety, to release the benefits incrementally across the routes and to develop the programme through feedback from users.

Geo-RINM rolled out to 4,600 users Delivery of RINM has been broken down into stages with the current focus aimed at the rollout of the Geo-RINM Viewer. The first phase concentrates on visualising a number of key datasets and this will be followed by future releases to colleagues and teams across the network. The initial release of the Geo-RINM Viewer will display existing Gl Portal data, track centreline, an enhanced level crossing view and five mile line diagrams. New data sets will be continually added to the viewer from other asset-related data sets, including access points, underground services and workbank, plus high resolution images. As data is added, the viewer will play an increasingly vital role in early planning and design – reducing the amount of time required trackside and increasing worksite efficiency.

A programme of continual development is now in place to develop the Geo-RINM Viewer. This includes additional datasets and access via mobile devices. Model Offices are taking place around the country to identify users’ priorities ahead of this release.

A view from above

The ORBIS Aerial Survey Data Project was key to collecting data about the infrastructure.

What has been done?

» Aerial survey of the entire railway network;

» Capture a rich set of information;

» Analyse raw data to gather key insights. How does this help to run the railway better?

» Reduced survey costs;

» Increased maintenance efficiency;

» Fewer people trackside, less of the time;

» Better data about our level crossings;

» Reduced risk of doing work in the wrong place.

Standard project deliverables

» Imagery – downward facing, full colour;

» Imagery – downward facing, false colour infrared;

» Imagery – oblique;

» LiDAR point cloud;

» Digital terrain model, surface model;

» Advance project deliverables;

» Tree Database;

» Nairns profiles (for level crossings);

» Vector data (mapping).

To achieve this, more than16,000 route kilometres across Britain’s rail network have being photographed and captured using laser technology during a five- month long national aerial survey. Capturing approximately 60TBs of data, the survey will record enhanced downward and oblique imagery and LiDAR data across the entire UK rail network. As the images are processed and quality assured they will be deployed to the Geo-RINM Viewer.

The Air Operations team in Network Operations provide specialist aerial inspection and survey services to Network Rail, carrying out targeted inspections to improve performance and safety with no disruption to train services or worksite activities. The team includes five aerial survey specialists covering the entire network using two dedicated and specially- equipped helicopters. Both aircraft contain mounted cameras with sensors fitted, including high definition video, thermal imaging, corona discharge and a spotter scope capable of 80-times magnification.

The aerial surveys record at a height of 250 metres and cover 15 metres either side of the formation. The aerial photography RGB is a true- colour representation of the real world showing ground features at a resolution of 4cm, providing far superior quality than Ordnance Survey off- the-shelf Aerial imagery at 25cm resolution. In order to keep track of environmental changes, the full national survey will be done every five years with a refresh every year on an ‘as required’ basis. The team are investigating the use of drones, rather than manned helicopters, to carry out future surveys.

As the current RouteView system (containing aerial photography) and new Geo-RINM Viewer are complementary, Al ORBIS and Network Ops will be working together to further integrate and evolve the two systems.

Practical examples

Richard Pease, business analyst – asset information, demonstrated the Geo-RINM Viewer. It is a web-based system and the user starts with a map view from which the various data layers can be switched on. Some examples of the system showed the potential. A map of Euston Station was displayed on the screen from which a data layer was selected showing tenants data about leases granted by the property division.

Aerial Survey - LiDAR Classified Point Cloud Image [online]

An example of a real life benefit may be appreciated in relation to track renewals. Sometimes it is necessary to change ballast when relaying but it can freeze when stored. A frozen-solid mass of ballast is treated with de- icer but this cannot be used in environmentally- sensitive areas such as nature reserves, areas of Special Scientific Interest and where there is protected wildlife close to the railway. It would need to be replanned for a warmer period. Geo- RINM will show the job planner exactly where these sites are in relation to the railway without having to make a site visit, thereby making the planning process much more efficient, avoiding time consuming applications to agencies to find out about such environmental sites in the locality of the planned work.

Using LiDAR, it is also possible to take a cross-section of the formation. This will allow analysts to look at the terrain including such variables as the slope of a track and the density and shape of the trees that border it. Decisions can then be made on maintaining cuttings and embankments by looking for signs of degradation and landslips.

Investment project teams will be a key user of the survey data as the RINM Viewer will provide the information that would hitherto have been gathered by time-consuming site surveys conducted at the outset of a new scheme.

The RINM Viewer naturally lends itself to the visible aspects of railway infrastructure such as track and structures. ORBIS, on the other hand, has much to offer other disciplines as it links the data held in the separate engineering functional record depositories, enabling users to call up all the data for a specific area including track, structures, signalling, communications and power supplies.

From the S&T perspective, for example, it is possible to envisage the iPad playing a crucial role for a technician attending, say, a points failure. After keying the asset reference (point number) into Geo-RINM Viewer, a route would be plotted which would guide the technician to the appropriate lineside access point. The system will also provide detailed safety information about the running lines, then guide the technician to the exact location of the failed point.

Keying in a request for circuit diagrams would cause RINM to display the circuit diagram layer of data with diagnostics information. Removing the need to study paper road maps, find site access information and seek out the paper signalling circuit diagrams housed in a cabinet somewhere will obviously save considerable time. The ORBIS programme continues through to 2018, with advanced asset and system decision-support tools to be rolled out.

Thanks to Network Rail’s Steve Dyke, Richard Pease, Marco Sala and Sara Hirsch, and CSC’s David Moran, Mark Davis and Ruth Armitage, for their help in the preparation of this article.

The challenge of ERTMS on the ECML

There have been many articles on ERTMS (European Rail Traffic Management System) and its component elements of ETCS (European Train Control System) and GSM-R, the radio transmission link. Most have been upbeat, confidently predicting that this is the technology to adopt for future interoperability. A minority have alluded to the problems associated with roll out and the difficult logistics that can sometimes occur.

A talk given recently to the IRSE Scottish section looked at the proposed implementation of ERTMS on the southern section of the East Coast main line (ECML) from King’s Cross to Peterborough. Unusually, the talk barely mentioned the technical aspects of ETCS but concentrated on operating challenges (Graeme Boyd from Network Rail) and the limitations of GSM-R (David MacLennan from Jacobs). Both were refreshingly honest about the system in general and the specific issues that lie ahead.

The objectives and the plan

Why is ERTMS being introduced on the ECML? There are a number of reasons. Firstly, the route comes under the category of a European TEN (Trans European Network) and thus has to comply with interoperability requirements. Secondly, it will provide a fully fledged ATP (Automatic Train Protection) system, and thirdly, because it is seen as an integral part of the forthcoming ‘digital railway’.

Whilst ERTMS is already in service on the Cambrian line (the early deployment scheme) and has been tested for interoperability on the Hertford Loop, the next projects will be on the central section of Thameslink in 2016 and on the GWML in 2018.

Although the ECML project will follow these, it is not anticipated that all known problems will have been overcome and thus it will still be regarded as a development project in terms of defining rule sets, a reference design and finalising of Network Rail standards. These difficult issues have to be resolved before ERTMS can be regarded as a standardised technology.

Before any ERTMS work can begin, the re- modelling and re-signalling of Kings Cross station is needed. The present layout dates from the mid- 1970s and is based around a number of double- slip points. These are expensive to maintain and a much simpler arrangement is being planned, which will be implemented in February 2018. Thereafter, a number of ERTMS phases are envisaged and the whole project is currently in GRIP 1-3 (output definition to selection) planning stages.

Elements of the plan

The ECML ERTMS scheme has to be integrated into a number of other projects that will be happening in the same time period. These include signalling centralisation and the introduction of the Rail Operating Centres (ROCs). For the ECML, this will be at York and will replace the existing signalling centres at King’s Cross, Peterborough, Doncaster, York and Newcastle.

At the same time, Traffic Management Systems (TMS) will be incorporated into all the ROCs and will form the intelligence for train operation and pathing, and a new National Operating Strategy will be introduced, bringing with it an associated national rule set.

Each of these has to be considered for its relationship with ERTMS including technical interfaces and timescale. Once established, the ERTMS program can be developed, a major element being the testing and commissioning strategy. For this, decisions are needed on:

» The baseline software for the ETCS element – currently at 2.3.0, it is expected to have been revised to 3.0.0 by 2018, which is important because the current baseline is not forward compatible;

» The responsibility for application data preparation;

» Determining the scope of the functional test;

» The need for an operator’s test track;

» The suitability and possible enhancement of the GSM-R radio transmission system;

» Trackside installation tests;

» Dynamic testing of train-borne equipment; » How to carry out functional testing;

» The need for a period of shadow running;

» Future power requirements with the opportunity to rationalise the existing configuration and reduce the overall load as increased reliability is considered essential through the provision of more resilient supplies.

The transition from conventional signalling to ETCS along the route is another important factor. The current thinking is that a Movement Authority under ETCS will be issued after a train has passed a minimum of two consecutive green signals and  is expected to take 40 seconds. At 30mph, this extends to 1.6 miles but at 125mph, it will be seven miles.

The lessons from Cambrian are proving valuable, particularly the operations and maintenance elements. Building up route asset information – line speeds, gradients, stations, speed restrictions, use of imperial or metric measurements – is essential. Studying the migration strategy for other ERTMS projects will hopefully pave the way forward without too many unknowns in the equation.

The GSM-R capacity dilemma

It has been known for some time that the spectrum allocation of 4Mhz in both the up and down link directions is inadequate for an ETCS circuit switched connection to every train in busy locations. Even on the relatively rural Cambrian line, the availability of radio capacity has occasionally been noticed as a potential issue.

In continental Europe, the solution has been to revert to conventional signals on the approach to city centres and terminal stations. This is seen as undesirable for the UK and ETCS to the ‘buffer stops’ is very much part of the requirement. So what is the solution?

The adoption of packet switching – GPRS (General Packet Radio Service) – is the obvious answer and indeed this is being tested out on the Hertford Loop trial (issue 117, July 2014).

However, GSM-R as a voice service provision for driver-to-signaller communication will exist on the ECML long before the introduction of ETCS. Enhancing the system to provide more robust coverage is known to be needed, but there is no consensus on what the coverage levels should be. The stated minimum standard for guaranteed 95% coverage is -95 dBm for lines with speeds lower or equal to 220km/hr, but is this level high enough especially for packet switching?

The Hertford loop trial showed problems even though the computer-derived coverage plots were to the standard. It would appear that there is no substitute to having a radio survey train to get an accurate account of radio signal strength from temporary aerials erected at the nominated sites. This can be an expensive and time-consuming process.

Weather is another consideration and radio signals can vary whether it is winter or summer (tree foliage being a factor) and indeed from day to day, depending on climatic conditions.

ERTMS/ETCS

The radio link needs to give reliable coverage at the handover points between adjacent base stations. A matrix for coverage is therefore being drawn up for the various sections of line to be encountered on the ECML and will range from plain line, including embankments and cuttings, to station areas and tunnels. Already this is showing up likely levels of between -60dBm to -85dBm at some locations with base stations in the proposed positions. Whilst only a desktop exercise at present, sufficient alarm bells are ringing for this to be a contentious issue.

Another factor is the impact of any external interference. The allocation of adjacent spectrum to other users is known to have created some performance problems in Europe and even in the UK ‘lock ups’ on the extant GSM-R network have been experienced in weaker signal areas caused, it is thought, by interference from O2 and Vodafone. Software modifications to reduce the risk of this have been put in place and it is envisaged that the next software issue for the on-board EDORs (ETCS Data Only Radios) will largely resolve the problem.

The need for GPRS is clear as, with circuit switching, the realistic maximum of six channels for ETCS train communication will be woefully insufficient and calculations show that 12 simultaneous connections are required in the busiest area. This does not take account of any radio ‘overspill’ from adjacent routes, in particular the London area, nor the additional capacity required to give greater resilience if perturbations in coverage occur.

Packet switching should enhance capacity by about eight times, which is the good news, but as yet, there is no finalised GPRS specification for ERTMS usage.

The way forward has been the creation of a national ERTMS Steering Group that comprises all involved parties within Network Rail including NRT (Network Rail Telecoms), Telent (as the fixed network supplier) and Kapsch (as the radio infrastructure contractor). The group will take account of feedback from Europe as ERTMS projects are rolled out on the continent and a set of Guidance Notes will emerge.

Whilst the final design of the radio infrastructure is not yet completed, it is likely that an additional 12 base station sites will be needed over and above the original expectation. These will require access to the current FTN fixed bearer network, which could be problematic and changing the design to access the forthcoming FTNx IP-based network is a possible solution.

Other radio concerns

As well as the capacity constraints of GSM-R, a persistent worry is how long this radio technology will last, both in terms of continuing to be in a licensed band and the ongoing supply of equipment. GSM-R is a 2G technology and, with the public mobile service now existing in 3G and increasingly 4G, manufacturers will gear up to supplying the mass markets in these bands. Just how willing they will be to supply an obsolete technology for the next decade or so remains to be seen but, whatever the situation, it is likely the price per radio unit will increase.

As to licensing, assurances have been given that the GSM-R allocation will be safeguarded until 2026 and it may be available for longer than that. Whilst this may appear a long time, it is quite short in rail investment terms and rail companies investing in ERTMS systems will rightfully expect the systems to be in service for around 20 years.

No-one knows the answer to this dilemma and, from a European perspective, it keeps getting put back in the ‘too difficult’ basket. A migration to a 4G service is visualised by some but whether this would be with a dedicated frequency allocation for railway use or by sharing the public 4G band, opinion is divided.

A shorter-term worry is the recognition that ETCS will not operate without the radio link. Whilst the design criteria will maximise the robustness the GSM-R availability, the day may come when the network fails. Keeping trains moving in such scenario represents a real challenge.

A back-up radio via the public GSM networks is one possibility but it also begs the question as to whether lineside phones need to be retained. It should be the objective to eliminate these but, when all signalling has effectively failed, telephone communication may be the last resort for keeping trains on the move, albeit rather slowly.

Implementation

The ECML will not be the first main line to be equipped with ERTMS, the Great Western should have an operational system some two years before. Many of the lessons to be learned will hopefully have been teased out before the ECML changeover starts.

The current plan for ETCS Level 2, beginning in 2020, shows:

» Phase 1A – King’s Cross to Wood Green, retaining lineside signals except for the Northern City Line to Moorgate, where signals will be removed.

» Phase 1B – King’s Cross to Peterborough (Fletton Junction) without lineside signals including the Hertford Loop and the Cambridge line up to Royston. Signalled transitions will remain for the Harringey spur, the North London Incline and the Thameslink line connection. The latter, although destined for ETCS and thus a seamless transition, will have fall back signals in case of interface problems.

» Phase 2 – Peterborough to Doncaster without lineside signals.

The provision of ETCS from King’s Cross to Doncaster is going to be a challenge for rolling stock fitment and will demand an element of captive fleet management to ensure all trains on the route are equipped.

Much is at stake with this and other ERTMS projects. Growing pains and teething problems are inevitable, both technically and operationally. One can only hope that with all the planning and evaluation work being undertaken, the introduction will be smooth.