Home Blog Page 132

Stadler’s new SMILE (Giruno) train for the Gotthard Base Tunnel granted an operating licence.

Stadler’s new SMILE electric multiple unit, which Swiss national operator SBB calls Giruno (Buzzard), has been issued an operating licence by the Swiss Federal Office of Transport (FOT) to run at 200km/h (125mph) in single-train formations on the Swiss network. This paves the way for the Giruno to enter passenger service from early summer 2019, running through the Gotthard Base Tunnel, and the Ceneri Base Tunnel when it opens at the end of 2020, to connect Zurich with Milan and, later, Frankfurt.

Originally the EC250, the SMILE received its name as the result of a competition held during an open day, an acronym of Schneller Mehrsystemfähiger Innovativer Leichter Expresszug (speedy, multi-system, innovative, lightweight express train). It is claimed by the manufacturer to be the world’s first single-decker low-floor high-speed train. The low floor provides step-free access from platforms with heights between 550mm, the standard height in Switzerland, Austria and Italy, and 760mm (Germany).

Although based on Stadler’s successful FLIRT EMU design, the SMILE differs from its elder sister in many ways. It has a maximum operating speed of 250km/h (155mph), the train reached 275km/h (170mph) while testing between Hannover and Göttingen in Germany in February 2018, and iIt is designed to comply with the TSI (Technical Standards for Interoperability) High-speed regulations as well as to meet the EN 15227 crashworthiness standards.

In addition, the carriages are air-tight and air-conditioned, improving ride comfort for passengers. Provision is made for passengers with reduced mobility, with wheelchair spaces and accessible toilets in both first and standard-class carriages.

As ordered by SBB, each 11-car train is 202 metres long and seats 405 (117 in first class and 288 in standard). Two can be coupled together to form an 810-capacity, 404-metre-long train which can run at the full design speed of 250km/h.

Stadler EC250 “Giruno” SMILE on test between Erlen and Romanshorn. (Daniel Wipf)

The train has an articulated layout, with one bogie between each carriage and one at each end – 12 in total. Four powered bogies (in positions 2,3, 10 and 11) contain eight traction motors, and power is drawn through four pantographs, a mix of 1450mm and 1950mm wide, allowing the train to run using 15kV 16.7Hz AC, 25kV 50Hz AC and 3,000V DC supplies.

SBB ordered 29 trains in October 2014 at a value of CHF980 million (£632 million), with an option for an additional 92. The first train was unveiled at InnoTrans in Berlin in September 2016, just 23 months later, and the first unit was delivered to SBB in May 2017.

Tram Speed Protection

Tramlink service in a residential area

The tragic accident on the Croydon tram network in November 2016, in which seven people were killed and many more injured, has raised many questions about tram safety. As reported in issue 171 (Jan/Feb 2019), several recommendations were made in the subsequent report by the Rail Accident Investigation Branch (RAIB), a number of which have already been implemented. Key to all of these is how to implement an overspeed protection system such that the chances of a similar accident occurring are so low that the risk can be discounted.

Transport for London (TfL) has now let a contract to Deutsche Bahn’s UK subsidiary ESG Rail for providing such a system on London’s trams, with the component parts being supplied by Sella Controls, a Stockport-based company specialising in low-cost ground to train communication technology.

Rail Engineer went to meet Iain Wilkinson from Sella Controls to learn how the system will function and what will be involved to achieve full implementation.

Aerial view of the site. (RAIB)

Background to the challenge

In terms of operation, trams may be regarded as more like buses, in that the journey progresses by the ‘drive on sight’ principle whereby the driver is responsible for the safe movement of the tram according to what can visually be seen ahead. Signals in the form of horizontal, vertical or junction picture white bars are only provided at road intersections or where tram lines diverge.

The vigilance of the driver is therefore critical to safe operation and, on street-running sections, this is virtually identical to that of a bus driver with the exception of steering. Tram networks allow for steep gradients and sharp curves, so the vehicles are designed to cope with these.

However, the resurgence of tram networks in the UK has made considerable use of existing main line rail routes, either by reopening disused formations or taking over existing rail lines. On such sections, tram speeds can be much greater (up to 70km/h) as it is a dedicated right of way with no interference from road vehicles or pedestrians.

The Croydon acciodent occurred on a sharp bend after the tram had emerged from Sandilands tunnel. (RAIB)

In the Croydon area, a rail line existed between Selsdon and Elmers End. It was a Cinderella route in that it went from virtually nowhere to nowhere and, although electrified on the 3rd rail system, it carried few passengers and was closed in the early 1980s. The formation remained virtually intact, including a number of short tunnels.

In the planning of the Croydon Tramlink system in the 1990s, this redundant route was seen as potentially useful to link some outlying suburbs with central Croydon. To achieve this, the erstwhile line was linked at its half way point by two sharp curves into a street running section, with a new tram stop at Sandilands and onwards into the town centre past the busy East Croydon station.

The speed around these curves is 20km/h but, on the day of the accident, the driver allegedly lost awareness of his location and failed to slow down from the 70km/h of the former rail route section, resulting in the tram overturning. The route just before the curve is in tunnel and there was no natural daylight at the time. Hindsight would indicate that, in a dark locality, it would be all too easy to be confused as to the precise position of the tram.

Since the accident, much improved signage and a new driver vigilance system called ‘Guardian’ has been provided. Both of these contribute enormously to preventing any similar recurrence, but they stop short of actually taking over control should the driver fail to slow down for any speed restriction.

Designing a speed control system

The RAIB report did not specify the detail of a speed control system, just that technology should be used to intervene if a tram approaches a speed restriction too fast. It was left to industry to come up with a solution that is cost effective and with an appropriate level of safety integrity.

On main line railways, this would usually be a SIL4 system (Safety Integrity Level 4) with full failsafe status and active monitoring of the system integrity and functionality. Such an application to a tram network would be overkill and the considerable expense would be difficult to justify in view of the low risks involved.

A SIL2 solution has therefore been specified as one of the functional requirements to provide basic overspeed protection. The safety system will be invisible to the driver under normal circumstances, with the system only kicking in if the tram is detected as going too fast at a particular location. The risk of the safety system failing at the same time as an over speed is occurring is regarded as so small as to be discounted.

Should a system failure be detected, the system can be bypassed by the driver with the correct authorisation, thus allowing the journey to continue until such point as the tram can be taken out of service for investigation of the failure.

To make sure it wasn’t ‘reinventing the wheel’, TfL engineers researched what other light rail systems around the world were using to overcome this problem. Metro Tenerife has a system, but it isn’t SIL 2, and a few other networks also employ some measure of overspeed protection, but not to the standard that TfL required. So, the only thing was to develop a new system, using proven technology if possible.

Tracklink III

Tracklink III from Sella Controls.

Sella Controls has developed, over the years, a track-to-train communication link originally developed for selective door opening (SDO). This consists of a sealed track or lineside-mounted beacon that is powered from the radio signal of the train interrogator unit. The beacon is coded with data for the specific location and the information exchange between beacon and interrogator can be used for a number of applications.

For SDO, 18 fleets of UK trains are now equipped with the system. The radio link is in the 865.7 to 867.9 MHz unlicensed band and power levels of around 200mW give a range of around one metre. Rail Engineer articles on the SDO system appeared in issues 58 (August 2009) and 102 (April 2013).

Although, when used in SDO mode, trains are normally stopped at a station, tests showed that Tracklink III could get an acceptable number of ‘reads’ at speeds of over 70mph.

Could the system be adapted for the London requirement? Discussions between ESG and Sella Controls led to the emergence of a practical solution.

System design and application

The Sella Controls system has three basic component parts – firstly, the track beacons mounted transversely between the running rails, secondly, the underfloor beacon readers mounted on the underside of each tram and, thirdly, an on board controller (right) unit that monitors all the beacon ‘reads’ and which is linked to a 4G public cellular radio connection or Wi-Fi for reporting back to a workstation in the control room.

Trainnet onboard controller from EKE Electronics.

The onboard controller is being supplied by EKE Electronics of Finland, with whom Sella Controls has a partnership. The company is an independent supplier of TCMS (Train Control and Management Systems) and its Trainnet product is being used for this project.

A fourth unit is a cab display that indicates that the system is operating normally, whether a trip has occurred, a reset switch and a ‘break glass’ bypass facility. A driver activating a cab for a journey automatically connects the display of that cab to the onboard controller while a connection from the controller unit to the brake circuit enables the brake to be applied should a trip occur.

Each track beacon is individually programmed with the maximum permitted speed at that point.

On the approach to any significant curve, a series of beacons (up to four) will be positioned some distance in advance of the curve. Each beacon will be programmed with the maximum permitted speed at a specific point ahead which represents the start of a slowing down zone, thus a four-beacon arrangement would signify four zones.

The train odometry then measures the distance to the start of the first zone, this zone being typically 150 metres in length. The speed at that point is likely to be the line speed, which is already set at a maximum of 70km/h. If that speed is exceeded, the system trips in and a full service-brake application is made.

The second beacon would similarly give a speed and distance for the start of the second zone, the zone distance being shorter (typically 30 metres) with, say, a maximum speed of 60km/h, as the tram should be slowing down for the curve.

Similarly, the third beacon would give a speed for the start of the third zone at, for example, 40km/h and the fourth beacon indicates the speed near to the start of the curve – typically 20km/h.

Under normal driving conditions, the speed at the beginning of each zone should be well under the maximum speed permitted but, if the tram exceeds this, then a trip occurs and a service-brake application is made, bringing the tram to a stop.

The exact distance from the beacon to the zone start is not critical but will be around 60 metres. The zones are ‘virtual’ and are not marked in any way. Each beacon will be programmed with the distance to zone commencement, zone length and maximum tram speed within that zone. The four-beacon arrangement is such that the combination of all four can be positioned before the commencement of the first zone, so the tram odometry equipment is vitally important in monitoring the slowing down process as it has to measure the distance to the start of the different zones simultaneously.

If the curve is not so tight and thus the speed is higher, it is likely that fewer beacons will be required, but there will always be a minimum of two.

Should a trip occur and the tram stops, the EKE controller will immediately and automatically notify the London Tram control room of an over speed activation, following which the driver must speak with the control room to arrange a re-set. An instruction to activate the reset switch will then be given whence the tram brake can be released and the tram proceed on its journey. The onboard controller unit, with its data recording facility, will log every pass over a beacon and whether or not the tram is near the speed limit at that point.

Fitting the fleet

There are two types of tram in the fleet of 36 in London, supplied by Bombardier and Stadler, and both are already fitted with speed sensors and odometers. ESG and Sella Controls are undertaking the design of the system jointly, with ESG delivering the integration design of Sella’s system to the vehicles and for retro fitting the trams with the reader and controller equipment, including interfacing these to the brake and odometry circuits.

Sella has said that a ‘first in class’ fitment will be ready for testing in August 2019 and, following a reliability validation period, it is planned to fit the system to one tram every four days, with completion by the end of the year.

Once the system is commissioned, every tram will go through a test routine as it leaves the depot each morning, to prove that the onboard equipment is working.

Future potential

Clearly the seriousness of the accident meant that doing nothing was not an option for TfL, and many eyes from elsewhere will be watching as to the performance and effectiveness of the system once it is in service.

A SIL 2 system was called for in the specification, but alternative options are likely to be considered by other tram operators, both in the UK and abroad. A SIL 0 system, based upon SatNav positioning and an associated speed alarm but without direct intervention to the tram brakes, might be an option. It will all depend on the risks perceived.

Much will depend on the cost of fitting any future system. The costs for the Croydon system are not being disclosed, but the bulk of this will be in retrofitting the trams. The track beacons are relatively cheap and fitting on board equipment to a new tram is always much easier and cheaper than retrofitting.

It will be interesting to watch how over speed protection measures are progressed into the future.

Buying HS2’s high-speed trains – part 2

Visuals for the proposed HS2 Euston Station.

An earlier article in Rail Engineer described HS2’s £2.75 billion procurement of at least 54 classic-compatible high-speed trains to run from London to Birmingham, Manchester, Liverpool and Glasgow. This month’s issue considers the very-high-speed (over 200km/hr) pedigree of the companies competing for this contract and where they might build their new trains.

HS2 announced five selected bidders for its high-speed train contract in November 2017. These were Alstom Transport, Bombardier Transportation UK, Hitachi Rail Europe, Patentes Talgo and Siemens. In July, Bombardier and Hitachi announced that they would form a partnership to submit a joint bid for the contract. In response, HS2 invited Construcciones y Auxiliar de Ferrocarriles (CAF) to join the shortlist of bidders in the interest of maintaining robust competition. Bids are due to be submitted in May.

Shinkansen Series 700 and Series 100.

Shinkansen legacy

Hitachi’s high-speed train pedigree goes back to the introduction of the Japanese Shinkansen (shin – new, kan sen – trunk line) train service in 1964. Since then, the company has produced a further eleven types of Shinkansen train. Over this time, continuous improvement has reduced the weight of the train sets from 972 to 700 tonnes, increased their maximum speed from 210 to 320km/h and reduced power consumption such that the latest Shinkansen Series N700 at 300km/h requires only 68 per cent of the power of a Series 0 at 220km/h.

Hitachi entered the UK rolling stock market with its 225km/h Class 395 Javelin train, which started HS1’s high-speed domestic services in 2009. This was developed from the Series 400 Shinkansen, modified to comply with EU standards. Since then, Hitachi won the Intercity Express electric and bi-mode trains for the Great Western and East Coast Main Lines and an order for the ScotRail class 385 EMUs.

To build these trains, Hitachi Rail Europe built a 43,000 m2 assembly plant at Newton Aycliffe in County Durham. This started production in 2015 and can produce 35 vehicles a month. With the Newton Aycliffe plant operating at capacity, further train orders from Great Western, TransPennine Express and Hull Trains for class 802 bi-mode units had to be built at Hitachi’s Pistoia plant in Italy, which Hitachi acquired from AnsaldoBreda in 2015.

Experimental AEG three-phase railcar which set a world speed record for electric rail vehicles of 210.2km/h on 28 October 1903 between (Berlin-) Marienfelde and Zossen.

High speed consortia

AEG, one of the companies that eventually became Bombardier Transportation had a high-speed pedigree going back to 1903, when it supplied electrical equipment for a railcar, powered by a 10kV three-phase overhead line system, which achieved 210.2km/h, a rail speed record that stood for the next 51 years.

In more recent times, Bombardier was part of a consortium with Siemens that developed the German ICE 3 high-speed train which entered service in 2002. Bombardier led the development of bogies, structures engineering, aerodynamics and pantographs. The ICE 4, which entered service in 2017, was also developed in partnership with Siemens.

In a consortium with Talgo in 2005, Bombardier was entirely responsible for the development of traction and bogies for the power cars for the Talgo 350 train. In a partnership with Alstom, Bombardier built the USA’s only high-speed train, the tilting Acela, which entered service in 2000.

It was China that provided a market for Bombardier’s wholly designed high-speed trains that were built by local train builders. The first was the 200km/hr CRH1A, which was based on its Swedish Regina trains. This was followed by the 250km/h CRH1B trains in 2009. In total 344 of these trainsets were delivered.

The first of Bombardier’s Zefiro high-speed trains entered service in China in 2009. These are 250km/h 16-car sleeper trains. The CRH380D is a 380km/h eight-car Zefiro variant for which China has placed an order for 85. These have achieved 420km/h during tests on the Chinese high-speed network.

Hitachi and Bombardier’s Frecciarossa ETR1000.

The Zefiro 300 variant is intended for European use and is designed for UIC gauge. This design was offered by Bombardier in association with AnsaldoBreda (now Hitachi) for a bid that, in 2010, won the contract to build 50 Italian high-speed trains. With Bombardier supplying the bogies, traction equipment and control systems, Hitachi Rail Europe built the trains, including bodyshells, at its Pistoia plant. These eight-car ETR1000 trainsets, commonly known in Italy as Frecciarossa (the red arrow), entered service in 2015.

Learning from Italy

Rail Engineer was recently invited to travel on the Frecciarossa between Rome and Florence. This is Italy’s first high-speed rail route, which opened in 1977 and on which trains are limited to 250km/h due to its 3kV DC overhead line system. The remainder of the high-speed railway between Salerno and Turin is electrified at 25 kV AC and has a line speed of 300km/h. Frecciarossa services also serve stations on the conventional network.

The train has four classes. Standard and Premium each have 2 + 2 seating. Business class has 2 +1 seating and Executive is 1+1. The train design allows for a flexible mix of seating arrangements. Such flexibility will be needed for HS2 trains as the seating will be specified by the train operator after the contract has been let.

The Executive coach has just 10 seats and includes a six-seat meeting room. This was where Marco Sacchi, Hitachi Rail Italy’s head of high speed, answered questions. He advised that the train was designed for a maximum operating speed of 360km/h and had achieved 399km/h during testing. Although high-speed routes have better track quality than conventional routes, Marco is in no doubt that high-speed running presents significant challenges in respect of noise, vibration and ride quality.

High speed also has other challenges in respect of passenger comfort, for example to avoid pressure pulses the train has a predictive system that closes the heating and ventilation system air intakes, within a tenth of a second, immediately before entering a tunnel.

Although the Hitachi/Bombardier joint venture is focused on its HS2 bid, the two companies remain competitors in other markets. This requires special arrangements in respect of the bid team’s use of company-specific information. In the developing their bid and plans to build the HS2 trains, both companies will no doubt build on the partnership that built the Frecciarossa and use their manufacturing plants in Newton Aycliffe and Derby to best advantage.

Pre-production Alstom TGV in 1979.

French high speed

France has a tradition of high-speed rail records dating back to 1955 when a 1.5kV DC SNCF Class CC7100 locomotive achieved a world record of 331km/h. This run demonstrated challenges of routine high-speed running after hunting bogie forces deformed 400 metres of track and destroyed the locomotive’s pantograph.

This speed record lasted until 26 February 1981 when an Alstom-built TGV (Train à Grande Vitesse) achieved 380km/h on a slight down grade between Courcelles-Frémoy, Côte-d’Or, and Dyé, Yonne, on the LGV Sud-Est line.

V150 train setting the world speed record of 574.8km/h near Le Chemin, France, on 3 April 2007.

The current railway speed record of 574.8km/h was set on the newly completed but as yet unopened LGV Est line in 2007 by a specially prepared five-car train that was fitted with extra powered bogies, producing a total of 19.6MW from the enhanced 31kV overhead supply, and aerodynamic fairings that had been designed using a wind tunnel.

The first two pre-production TGVs left Alstom’s Belfort plant in July 1978. These were subject to thousands of tests before problems of high-speed vibration and bogie stability were eventually resolved. Alstom delivered the first of 87 production TGVs in 1980. These originally had a maximum speed of 260km/h and, on 27 September 1981, were used to inaugurate Europe’s first high-speed rail service on the 409-kilometre French South East high-speed line.

The French hi-speed network now consists of 12 lines totalling about 2,700 kilometres for which Alstom have delivered about 550 TGVs. These are articulated units of eight or ten cars that operate at speeds up to 320km/h. They include double-decker (Duplex) and postal service units as well as the first Eurostar trains. The TGVs have articulated passenger cars with a power car at each end which also powers the adjacent passenger car bogie.

In 2000 Alstom took over Fiat Ferroviaria, whose tilting technology is used in Virgin’s Pendolino trains. The company has since used this technology on the Spanish Avant classes 104 and 114, both built in a consortium with CAF, the Italian ETR500/600, the Swedish RABe503 and the Russian-gauge Sm6 that operates between St Petersburg and Helsinki.

Other overseas high-speed train orders included 94 CRH5A trainsets supplied under a technology transfer agreement to China. Another such agreement was for 46 18-car TGVs, of which 34 were built in Korea. Alstom also built 12 Duplex TGVs for Morocco.

In 2000, Alstom unveiled its AGV design, which is unique in using articulated bogies for distributed traction. AGV-type bogies were fitted to the shortened TGV Duplex that achieved the 581km/h speed record in 2007. 25 AGVs were supplied to Italy in 2012.

Alstom’s double decked Avelia high-speed train.

As previously mentioned, a consortium of Alstom and Bombardier supplied the USA’s Acela trains. These will soon be replaced by a tilting variant of Alstom’s new high-speed train range, the Avelia, which is due to enter service on the Boston to Washington corridor in 2021. In one of Europe’s largest-ever high-speed train contracts, SNCF has ordered 100 double-decker Avelia trains.

Should Alstom win the HS2 contract, it seems likely that its trains would be constructed at its 13,000 square metre Widnes facility in Cheshire, which opened in 2017. This is claimed to be the “biggest and most sophisticated centre for train modernisation ever in the UK”. It has three 260-metre roads and includes the traction equipment facility transferred from the company’s recently closed Preston plant.

Alstom has signed an agreement for technical training at Widnes to be led by the National College for High Speed Rail (NCHSR), to whom Alstom also donated Eurostar power cars and an AGV passenger car for training.

ICE and Velaro

Germany’s high-speed service started in 1991 using 280km/h ICE 1, trainsets for which Siemens supplied the electrical equipment. The ICE 2, which entered service four years later, was built by a consortium of Siemens and Adtranz – acquired by Bombardier in 2001. The next high-speed train involvement for Siemens was the supply of traction equipment for the 220km/h Portuguese Alfa Pendular tilting trains, which entered service in 1999.

Siemens Velaro E (AVE Class 103).

The German ICE 3 high-speed train was produced by a consortium of Bombardier and Siemens. This was licensed to run at 330km/h and reached 368km/h on trial runs. It has eight passenger cars with distributed traction and so has no power cars. This train was the basis for the Siemens Velaro family, the first of which, the Velaro E, was delivered to Spain in 2005 to run between Barcelona and Madrid at up to 310km/h.

Velaro variants were then supplied to Spain, Russia and Turkey. In addition, hundreds have been built in China. The 16-car Velaro e320 operates Eurostar services.

The Chinese Class CRH380B Velaro variant.

Siemens has also produced the ICE-T, a 230km/h tilting EMU for use on German conventional lines, and the Railjet which operates in Austria and the Czech Railways. This is a 230km/h locomotive and seven-coach push-pull trainset.

The company is currently producing seven and twelve-car ICE 4 trains for which it has sub-contracted Bombardier to optimise design aerodynamics and produce trailer bogies and bodyshells. An ICE 4 train can consist of between five and 14 cars, with a flexible arrangement of power and trailer cars.

In June, Siemens unveiled its Velaro Novo concept of an 8MW train operating at speeds between 250 and 350km/h which, it claimed, would “set new standards for efficiency and sustainability, using 30 per cent less energy when running at 300km/h”. Its car bodies are designed as “empty tubes” for flexibility and to increase passenger space.

Velaro Novo.

In March 2018, Siemens leased land in Goole for a planned train factory with a footprint of up to 75,000 square metres, an investment of up to £200 million. The construction of this plant was assured in November when Siemens won a £1.5 billion contract to build new London Underground Piccadilly line trains.

Trains in Spain

The Spanish high-speed rail network is more than 3,200 kilometres and was inaugurated with the opening of the 472-kilometre Madrid to Seville high-speed line in 1992. As this network is built to standard gauge, Spanish high-speed trains need to change gauge if they are to operate on conventional Spanish broad-gauge lines.

This line required 24 AVE class 100 high-speed trains. These are an Alstom TGV Atlantique variant, with some being built by Spanish train builder CAF as its first experience of high-speed rolling stock. A CAF/Alstom consortium later delivered a further 89 Spanish high-speed trains. These were the Avant Class 104 (2004), Alvia Class 120 (2006), Alvia Class 121 (2008) and the Avant Class 114 (2011). The Class 120 and 121 trainsets have CAF’s SIBI active tilt system and BRAVA variable gauge bogies.

CAF Oaris.

CAF supplied twelve 250km/h Class 120 /121variant to Turkey in 2009 and, in 2010, unveiled its Oaris high-speed concept for 350km/h operation, which has distributed traction and a flexible interior layout. In 2015, CAF won a contract to supply eight four-car Oaris trainsets to operate on the Oslo airport rail link in Norway.

CAF’s £30 million train production facility in Newport, South Wales, opened last year. This 15,000 square metre-plant is now fitting out Class 195 DMU bodyshells for Northern Rail and has started design and engineering work on the 77 DMUs that it is to build for the Wales and Borders franchise.

Unconventional articulation

Talgo has been progressively developing its unique trainsets since 1942. These feature short coaches, typically 13.5 metres long, between which are steerable two-wheel bogies without axles. Over the length of a conventional 26-metre bogie vehicle, this arrangement saves between five and ten tonnes as it has half the number of wheelsets. It also provides a low floor throughout the train. Furthermore, with less overhang, shorter coaches can have a wider bodyshell.

The independent wheels also facilitate Talgo’s variable gauge running gear which is needed for Spanish high-speed classic compatible trains. Talgo’s suspension system provides natural tilt as the bogie’s main suspension spring assembly is well above the coach’s centre of gravity. This could give the company an advantage for HS2 services on curved routes to Scotland.

Talgo’s two-wheeled articulated bogie, inset shows how its suspension system provides natural tilt.

Talgo’s first high-speed trainset entered service in 2005. This was the 300km/h Spanish Class 102, for which power cars were provided by Bombardier, of which sixteen were built. The Talgo/Bombardier collaboration delivered a further 72 Spanish trainsets, These were the Class 130 (2007), Class 112 (2010) and Class 730 (2012).

In addition, North America and Russia each have seven Talgo trainsets. Since 2016, Russia has been using these to operate the Moscow to Berlin service, for which a variable gauge is required.

Uzbekistan took delivery of two Russian-gauge 250km/h Talgo trains in 2011. In 2017, Saudi Arabia inaugurated its high-speed service with 35 Talgo 350 trains running at 300km/h, for which Bombardier supplied the power car bogies, propulsion and control equipment.

Talgo unveiled its Avril concept for an advanced 380km/h train in 2010 and now has orders for 30 of these trains for Spain. Although Talgo trains normally have low floors, an Avril variant offers step-free access from HS2’s 1115mm platforms.

Talgo Avril.

In November Talgo announced that its preferred location for building HS2 trains is the disused power station at Longannet in Scotland. This would be a 70,000 square metre plant employing at least a thousand people. An Innovation Centre would also be developed at Chesterfield. A Talgo statement advised that the company aims for “true UK manufacturing”, instead of assembling a kit of parts from overseas.

Only one winner

Each bidder will probably be spending around £10 million on this bid, which only one of them can win. Yet HS2’s future passengers will certainly be the winners from its train procurement. The Frecciarossa, Avelia, Velaro Novo, Oaris and Avril are all exceptional trains, evolved from hard won experience and a wealth of expertise. Interestingly, much of this is the result of the current bidders working together on various high-speed train projects.

The bidders all state that their trains will meet the HS2 tender requirements of energy-efficiency, ease of maintenance and flexible state-of-the-art passenger accommodation. By 2020, the HS2 procurement process will have quantified all these claims to establish which train offers the lowest whole-life cost to determine who will build these trains. Until then, readers may judge for themselves which one is most likely to win the HS2 bid.

The construction of high-speed railways in Japan, France, Germany and Spain has also given a boost to their respective train builders, who are now competing to build HS2’s trains. When HS2 opens in 2026, it will be 62 years since Japan and 45 years since France inaugurated their high-speed rail services. Despite this late start, it is to be hoped building the UK’s high-speed trains will bring a resurgence in UK train building.

Decarbonisation on the agenda at RIA’s innovation conference

A nice word cloud will words related to pollution. All of which are hovering above a large, industrial city.

European Environmental Agency figures show that, per passenger kilometre, rail transport’s CO2 emissions are respectively 28 and 11 per cent of those on road and air transport. Nevertheless, however good rail’s environmental credentials, the industry can and has to do much more to both reduce its carbon footprint and reduce harmful emissions.

This message was stressed by various speakers at the recent Railway Industry Association’s Innovation Conference. In his presentation on innovating to improve passenger services, Network Rail chief executive Andrew Haines stressed the importance of the decarbonisation agenda and advised that recent electrification schemes had been delivered to budget.

In her presentation Claire Porter, TfL’s head of transport systems engineering, referred to a recent study that concluded poor air quality was responsible for 9,000 deaths a year in London.

Presentations from Network Rail’s R&D team included the sustainability aspect of the Shift to Rail programme and Professor Clive Roberts advised how the UK Rail Research and Innovation Network (UKRRIN) is working both with Network Rail, to reduce electrification clearances, and with Porterbrook, on the development of the Hydroflex hydrogen train. M.A.D.E. (Materials, Automation, Data and Energy) pitches included Warwick Manufacturing Groups’ light-weighting and hybrid propulsion and the G-volution technology.

Porterbrook/BCRRE HydroFlex demonstrator.

Decarbonisation projects

The G-volution patented dual-fuel technology uses its optimiser to optimise combustion  introducing  Liquified Natural Gas (LNG) to co combust in an existing  diesel engine. The quantity of diesel required is therefore reduced as the LNG replaces it but the engine always retains its ability to run on 100% diesel should the secondary fuel (LNG) not be available. 

This enables particulate emissions to be reduced by 90 percent and a CO2 reduction of up to 44 per cent. The technology enables the dual-fuel engine to perform and operate exactly as if it were running  on 100% diesel. With the reduced fuel cost, its pay-back period is estimated to be two to three years.

This  technology has been proven on road with over  300 lorries in the UK covering over 50 million kms that are part-fuelled by liquid natural gas, stored at minus 190°C in a cryogenic tank.

RSSB has part-funded the  installation  of this technology to a Grand Central Class 180 unit that will be operational and demonstrated on network at the end of the year.

As Rail Engineer reported in December (issue 170), RSSB recently launched competitions offering funding for decarbonisation projects. In January, it was announced that five decarbonisation projects had each been awarded £345,000 in the “First of a Kind” competition run by Innovate UK on behalf of the Department for Transport. These were:

  • Trialling an Eminox exhaust after-treatment system on a South Western Railway Porterbrook Class 159 unit – although such systems are widely fitted to HGVs, this will be its first use on a railway vehicle;
  • Fitting a Class 66 freight locomotive with a Vortex exhaust system, the improved gas scavenging of which is expected to reduce particulate emissions by 50 per cent and reduce fuel consumption;
  • Unipart’s development of digital displacement pump transmission which, unlike conventional transmissions, is highly efficient at low speeds;
  • The “Riding Sunbeams” project to use solar power for third-rail DC traction;
  • Using Steamology technology – superheated steam generated from tanks of compressed hydrogen and oxygen drive a turbine which generates electricity – to power a range extender to charge the batteries in a Vivarail Class 230 unit.

The Decarbonisation journey

The second morning of the conference included presentations by Andy Mellors, managing director of the South Western trains franchise and chair of the IMechE’s Railway Division, Philippa Oldham, head of national network programmes for the Advanced Propulsion Centre and Andrew Kluth, RSSB’s lead carbon specialist.

Andy Mellors, managing director of the South Western trains franchise and chair of the IMechE’s Railway Division.

The presentation given by Andy Mellors (right) was entitled “The Decarbonisation Journey”. He noted that it was now ten years since the Climate Change Act gave the Secretary of State a duty to ensure that the net UK carbon account for the year 2050 is at least 80 per cent lower than the 1990 baseline and that, although the UK had reduced carbon emissions by 43 per cent since 1990, there was still some way to go.

He advised that the DfT have set his, and other, franchises challenging targets in respect of carbon reduction per passenger kilometre. This shows that, when trains are lengthened, they should not be empty during off-peak hours and that more passengers travelling by rail helps meet this target.

Hence, it’s clearly important that rail gives passengers what they want. Andy referred to Transport Focus information about passenger priorities which showed that, after value for money and getting a seat, greater punctuality, fewer cancellations and reduced journey time were important. He noted that none of these passenger priorities were concerned with what was “under the bonnet” so felt that passengers should be asked about the importance of carbon reduction in future surveys.

He also showed fleet reliability comparisons for three eras of diesel and electric multiple that, in all cases, showed that electric units were twice as reliable in terms of miles per technical incident (causing more than three minutes delay). Electric trains also offer faster, quieter trains and their acceleration enables them to stop at more stations.

Electrification therefore gives passengers what they want. Indeed, Andy noted that the introduction of electric trains on the Thames Valley lines had transformed the passenger experience. It also has good carbon credentials as, per passenger kilometre, diesel trains emit three times the carbon of electric trains.

For all these reasons, the Institution of Mechanical Engineers recommends that the UK Government rethinks its cancellation of electrification programmes and moves forward with a more innovative and long-term approach with an electrification rolling programme that can create skills and careers and develop supply chains. Andy was pleased to see that the interim report of the rail industry decarbonisation task force had concluded that “electrification is the better economic choice for an intensively used railway” and that its “costs and disruption are best minimised with a steadily managed programme rather than an intensive rollout of electrification”.

However, alternative traction needs to be considered on lines for which electrification is an unrealistic proposition. In his previous role as engineering director of First Great Western, Andy was pleased to have been involved in the development of the self-powered Class 769 “Flex” unit, which can also operate on overhead and third-rail electrification. This is soon to be operational on the Reading to Gatwick Airport service, where it will be powered by the third rail for most of the time.

Work also needs to be done to reduce the emissions of diesel trains, especially freight trains, for which innovation is required such as the decarbonisation projects mentioned above.

Andy noted that the Riccardo team that won last year’s Railway Challenge included automotive graduates. He felt this showed the potential for cross-sector innovation.

Class 387 Electrostar at London Paddington. (Luke Deaves)

Automotive roadmaps

Philippa Oldham explained how the automotive sector is subject to unprecedented technological change as it develops propulsion technologies to respond to numerous environmental and societal pressures as well as legally binding CO2 targets and tailpipe emission targets.

She noted the complex relationship between CO2 and tailpipe emissions, as shown by a recent increase in CO2 emissions from road transport due to the reduction in the sales of more efficient diesel cars as a result of concerns from tailpipe emissions. She also mentioned that, as the Government’s “road to zero” strategy was primarily concerned with electric vehicles, it could be difficult to fund research to improve internal combustion engines, despite them being needed for heavy duty vehicles for the foreseeable future. In this respect, there is an analogy with the difficulties of decarbonising rail freight vehicles.

To support the development of the required automotive technologies, the Advanced Propulsion Centre has produced its roadmap report. This considers the types of technologies needed for cars, buses and commercial/off-highway vehicles up to 2040 and has roadmaps for electrical energy storage, electric machines, power electronics, thermal propulsion systems and lightweight vehicles and powertrain structures. These show how specific technologies need to develop to provide the required targets.

Of these, the electrical energy storage roadmap is particularly relevant for non-electrified rail traction. This gives targets for cost and energy density as well as detailing technologies needed to improve electrolytes, separators, binders, solvents, anodes, cathodes and casings.

Phillippa noted that there were significant emissions associated with the production of batteries (the respective emissions for petrol and battery cars have been estimated to be 5.6 and 8.8 tonnes CO2) and that batteries generally cannot be recycled as they are not designed for this.

GB Railfreight class 66/7 no 66751 reverses a rake of loaded coal hoppers off the Thoresby colliery branch line. (Derek Wilson)

The taskforce

Andrew Kluth explained how UK carbon emissions were being reduced with power accounting for a 60 per cent reduction between 2012 and 2017. However, emissions from transport had increased by four per cent over this period. Although the sector was becoming more efficient, more people were travelling. Within the transport sector, rail accounts for two per cent of all emissions.

His presentation explained how the rail industry decarbonisation taskforce had a mission to move UK rail to the lowest possible carbon energy base by 2040. Its purpose was to draft the rail industry’s response to the Minister’s vision to remove diesel-only trains from the tracks by 2040. He advised that the transport sector’s climate change target was likely to be net zero by 2050 and that this might be accelerated to net zero by 2040. Hence the industry had to consider how to meet this challenge.

The taskforce had recently produced its interim report. This showed traction energy accounted for 63 per cent of all carbon emissions (37 per cent diesel, 26 per cent electric). It had particularly considered the various traction types for non-electrified lines. The final report is due in the late spring. Andrew explained that the vast majority of rail journeys were, for some part, on the electrified network and so the task force was considering how to use this network to charge batteries for the part of the journey on non-electrified lines. They were also considering alternative self-powered traction for long journeys away from the electrified network.

In this way the final report will identify where electrification is likely to be the best option and where it is never likely to be an option. It will also determine where journey demands off the electrified network would be suitable for battery operation, now or at a reasonable time in the future, and where it won’t be.

The task force’s interim report has concluded that electrification is “currently the most carbon efficient power supply” and that “in general, electrification is the better economic choice for an intensively used railway”.

However, it does understate the benefits of electrification – for example, the executive summary doesn’t mention its conclusion that electrification is appropriate for intensively used railways. Furthermore “most carbon efficient” underplays the fact that electrification is three times more carbon efficient than diesel as shown by data in RSSB report T1145: Options for Traction Energy Decarbonisation in Rail which also estimates that CO2 emissions from diesel trains by 2040 will be halved as, by then, the proportion of electricity generated by renewables is expected to have increased significantly.

Why the term “currently most carbon efficient” has been used is not clear. There figures in RSSB report T1145 show that electrification will be the most carbon efficient form of traction in 2040. Furthermore, any self-powered traction requires onboard energy conversion, which incurs significant thermodynamic or chemical losses whereas electric trains only have minor on board efficiency losses.

The interim report considers the suitability of various types of traction for use beyond the electrified network but does not consider their performance. For example, the fact that bi-mode trains have a lower power-to-weight ratio in diesel mode than in electric mode is not mentioned. Furthermore, the interim report does not consider the requirement for medium-speed trains with high acceleration, needed for commuter services that stop at many stations.

Speaking to Rail Engineer, Andrew did stress that the interim report was very much “work in progress” and emphasised that the final report would address all relevant issues.

After the high cost overruns, on the recent electrification projects, it is understandable that the UK Government has lost faith in electrification. In this respect, the RIA electrification cost challenge report has done a valuable job in demonstrating that electrification can be, and is being, delivered in a cost-effective manner.

However, government also need to be convinced why further electrification is required, as Andy Mellors and the Institution of Mechanical Engineers have stated. The final report of industry’s decarbonisation task force is a valuable opportunity to do just this.


A full report of all aspects of RIA’s innovation conference will appear in the May 2019 issue.

Unlocking the benefits of HS2

Visuals for the proposed HS2 Euston Station.
Guest opinion by John Downer
John Downer

HS2 is being built, an Act of Parliament has set up HS2 Ltd, funding is in place and, crucially, construction has begun in earnest this year. We are breaking ground on a transformational piece of national infrastructure, and in advanced discussions with a diverse range of stakeholders and local communities about how we maximise the benefits of the project for the whole country.

So why do we continue to hear politicians reheating tired and flawed arguments about HS2? That train has long since departed. A choice between HS2 and regional rail improvements is no choice at all, we are already delivering HS2 and we will deliver both.

So, what does this mean about the future discussions to be had? It means talking about complementary expansion, upgrade, and integration of the existing network. It is not credible to pretend that we have a choice between improving the existing rail infrastructure and delivering HS2. They are separate but strongly related questions. Political choices are so rarely ‘either or’, and more often should be ‘both’.

In presenting the choice of rail investment as one between HS2 and regional schemes, political leaders and commentators betray the benefits of building both. As an industry we should make the case for HS2 and its integration with Northern Powerhouse Rail and Midlands Connect.

Government policy is to build HS2, both phases one and two, and to improve regional rail connectivity through schemes like Northern Powerhouse Rail and Midlands Connect. To do one without the other is a foolhardy choice and does a great disservice to the country. Nowhere would feel the full benefits of HS2 if we see it as a binary choice between HS2 and other programmes to better connect our regions. The great towns and cities across the North and Midlands, from Bradford to Birmingham, need both.

Suggested design for Birmingham Curzon Street HS2 station.

There are opportunities across the country to improve connectivity, boost jobs, and regenerate towns and cities which, for too long, have lacked the tools to succeed. These are opportunities that are realised and maximised through the HS2 network being integrated with NPR and Midlands Connect.

HS2 is building on a renaissance of delivering high quality infrastructure projects in the UK and, through that, creating and retaining highly skilled jobs and boosting economic growth. Currently, HS2 is supporting over 7,000 jobs. This will rise to 30,000 at the peak of construction. Importantly, 70 per cent of these jobs will be based outside of London.

Right now, over 250 apprentices have worked on HS2 and, over the lifetime of the project, 2,000 apprenticeships will be delivered. This next generation of industry leaders will experience working on a world class infrastructure project, an opportunity that will shape their careers and understanding of the industry for years to come. HS2 will develop future geologists, architects, and horticulturalists, as well as engineers, project managers, and designers.

HS2 will be integrated with Midlands Connect and Northern Powerhouse Rail, amplifying and widening the scope for meaningful apprenticeships. Crucially, it will develop these skills all over the country and for the benefit of the whole country. The careers of these highly skilled workers do not begin and end with one project; these workers are a national asset and part of a workforce fit for the future.

These projects, when viewed holistically, are about transforming the economic geography of the country. The North has just over 15 million people, with a gross value added of £315 billion to the economy. In London, with just over half that number of people, they are producing around £600 billion Gross Value Added. We know that the North is underperforming, and we know that part of the problem is connectivity east to west, as well as north to south.

Preliminary design for Leeds HS2 station.

The Strategic Transport Plan for the North of England offers a £70 billion vision for the future, targeted at supporting 850,000 fulltime additional jobs, and 100 billion gross value added by 2050. HS2, NPR, Midlands Connect, the Transpennine Route Upgrade and the improvements to the East Coast main line are all part of the solution.

Key to this is capacity and connectivity between cities in the North, for which the benefits are only truly gained if we integrate NPR with HS2. Currently, only two million people can get to four of the major cities within 90 minutes – with NPR that will rise to nearly 10 million.

By increasing the average journey speed in the North, from just nine miles an hour faster than a car to up to 125 mph, or 140 mph when operating on HS2 lines, we will see the journey from Sheffield to Leeds reduced from 43 minutes to 28, with four trains per hour instead of just one. There will be thousands of additional seats between the great hubs of Manchester and Leeds every hour. This current programme means thinking holistically about how we use HS2 as the main artery of a new kind of rail network.

High Speed Rail Industry Leaders (HSRIL) represents companies with an interest in high speed rail projects. Our members’ businesses are located across the length and breadth of the country, as well as around the world. We know what benefits rail can bring, we see the benefits on the ground but also in the strong economic evidence base.

Of course, we are champions of high-speed rail, but our voices are not the most significant in this debate. It is the political and business leaders in the North, the Midlands and the rest of the country that are crying out of the politicking to end and the serious decisions to be taken. From Manchester Mayor Andy Burnham, Leeds City Council Leader Judith Blake, to West Midlands Mayor Andy Street, they are stepping up to the plate and demanding that HS2 goes all the way to Manchester and beyond, but that is not considered in isolation. As an industry, we must provide ballast for those advocates willing to say it is not ‘either or’ but ‘both’, despite the political inconvenience it causes for them.

HS2 will leave a lasting legacy on the country. It will bridge the North-South divide, boost regional economies, and ease pressures on our ageing infrastructure. The physical and financial legacy of the programme will only be part of the story. The human side of the story will see HS2 supporting supply-chain businesses and communities across the country. A generation of professionals will gain skills and experience working on a globally renowned project, and will go on to do great things in their careers as a result. HS2 is about so much more than speed or capacity – but we can only unlock the extra value that it can bring by thinking broadly and deeply about the future of the country.

Railways are not easy and solutions are not simple. Politically expedient answers might offer a temporary fix for those craving headlines, but the problems are multifaceted and the solutions need to be too. We must, as an industry, continue to challenge the lazy rhetoric around HS2 and what it means for the country.

There is so much at stake and it is up to us to rise to meet this challenge.


John Downer is a director of High Speed Rail Industry Leaders and Client Account Director – Rail Solutions at Jacobs. However, the views expressed in this piece are his own.

RSSB publishes business plan for CP6 (2019-2024)

RSSB, the not-for-profit company that is owned by major industry stakeholders and was established as the Rail Safety and Standards Board in April 2003, has recently published its 2019-2024 Business Plan.

This sets out how, over the next five years, RSSB will act to support a safer railway into Control Period 6 (CP6) and beyond.  It details how RSSB will meet a range of industry priorities and challenges to put passengers first and focuses on the crucial areas of safety, health and wellbeing, sustainability, efficiency, innovation and the future post-Brexit. 

RSSB CEO Mark Phillips

RSSB chief executive Mark Phillips commented: “With a sharp focus on research, analysis and standards, we are determined to improve the overall experience for our customers, deliver value for our membership and reduce our dependence on the membership levy by developing commercial opportunities including enhanced training and bespoke services.”

Immediate concerns

Over the course of the first year of CP6, RSSB will be supporting the industry in reducing the effects of poor adhesion conditions, using improved technology and procedures to achieve better reliability and resilience, including piloting double variable rate sanders on the British main line.

A new Health by Design web hub will be launched, containing key resources for incorporating health and wellbeing within member organisations, including trialling health and wellbeing training for the workplace.

Research will continue as part of the PERFORM programme – the Enabling Better Performance Research Challenge that sets out to achieve performance improvements and run more trains on time today while improving the rail performance of tomorrow. This will include research into enabling better planning and resource management during train disruption.

Building on the work undertaken during CP5, RSSB will continue to provide the functionality, guidance and training that its members require to use the industry’s Safety Management Intelligence System (SMIS).  This is delivering the safety intelligence a world-class railway needs with improved linking of data to the tools, models and systems used by the industry.

The industry strategy for Leading Health and Safety on Britain’s Railway (LHSBR) will be refreshed, monitoring progress through the publishing of quarterly updates, working in collaboration with the industry.

And RSSB will support delivery of the industry’s carbon and air quality strategies by identifying, agreeing and systematically collecting environmental metrics for the rail industry to monitor.

A wider context

Any plan takes a while to formulate, and so can be overtaken by events. The RSSB business plan is no exception. It includes the intention to agree a revised regulatory framework, including the role of standards with industry and the Regulator, post-Brexit. As the terms and timing of the UK’s exit from the EU still haven’t been agreed, the work needed to accomplish this must be in doubt.

So too is the intention to develop new digital railway standards based on the requirements from the Digital Railway Programme. Network Rail’s digital railway is now going to be devolved to five routes across the country, surely needing a rethink from RSSB as well.

But these are details and both can be worked out when the situation becomes clearer.  As Mark Phillips said: “RSSB is in a unique position within the rail industry and we are indispensable when it comes to ensuring best practice in reducing risk and cost, and maintaining the high levels of safety the industry currently enjoys.”

Putting Passengers First

A guest editorial by Alex Hynes, managing director, ScotRail Alliance
Alex Hynes, managing director – ScotRail Alliance

Network Rail is changing how it operates. Putting Passengers First is a new model for the organisation, which will make the company more responsive to the needs of train and freight operators and, ultimately, the fare paying passenger and freight shipper.

Decisions that affect customers need to be taken closer to the coal face and the move to a regional structure with greater local accountability will help Network Rail achieve this.

In my experience, Scotland provides a great environment for collaborative working. There is more overlap between ScotRail and the Scotland route than in many of the routes south of the border and Transport Scotland is a strong client that expects Network Rail and its train operators to work together. Hence, the Scotland route is already fortunate to have a close working relationship with its customers, including freight.

For this reason, I expect there to be less change in Scotland than elsewhere. Perhaps the biggest change is that the regions will have a much bigger engineering capability, under the leadership of an engineering director. Although we have some brilliant engineers, engineering resource in the routes is currently stretched.

The regions will also take over responsibility for project delivery, with strategy and planning functions also moving as part of the changes. This will put all the levers of the railway system under the leadership of a single team that is attuned to local requirements.

A strengthened engineering function is needed to close the gap between our current PPM performance of 87.6 per cent and our target of 92.5 per cent, with infrastructure failures accounting for a third of all delays and many of the high-delay incidents earlier in 2018. On certain parts of the network, we have to aim for no service-affecting failures in the peak. The strengthened engineering team will determine how this can be achieved. It is then my job to find the money for their solutions, which could include more in-built redundancy, intelligent infrastructure to predict potential failures and standards that consider both safety and reliability.

Standards will be another big change. The intention is that regional engineering directors will set standards as a collective, administered by the company. Such company standards will be an irreducible core and will give regional engineers the flexibility to deal with the very different types of railways across the UK.

The engineering team will also develop and implement regional engineering strategies. Although I’m proud that Scotland has delivered both the Stirling-Dunblane-Alloa and the Shotts electrification schemes early and to budget, we intend to find better ways of working and drive down costs further.

As part of the pipeline for the new control period, we are also currently investigating electrification schemes on other lines but understand the Scottish Government will only invest in these if we can demonstrate good value for money.

A whole-system signalling strategy is also being developed, in consultation with our client and funder, Transport Scotland. This will only include the digital railway if it delivers the outputs of capacity, journey time and reliability. The digital railway is not being pursued as an end in itself – the extent to which it is part of this strategy is a decision to be taken in the region.

I feel very optimistic about the future as I am certain that the new organisation structure will build on what Network Rail’s routes have already achieved. Bringing engineers and project teams closer to passengers and freight customers will give them a more satisfying role and help drive up performance to keep people and goods moving.


Thanks to Alex Hynes for his guest editorial highlighting the crucial role of engineers as Network Rail moves towards a more passenger-focused railway.

An example of the flexible approach to standards he mentions is the risk-based management of continuous welded rail, as Chris Parker describes. A risk-based approach is also used to manage earthworks. However, as Nigel Wordsworth makes clear, this is not easy.

To control the risk from trams overspeeding, Clive Kessell explains how a tram speed protection system is to be fitted on the Croydon tram network following its fatal accident in 2016.

Decarbonisation was a key topic at the Railway Industry Association’s innovation conference, where IMechE Railway Division chair, Andy Mellors, described how electrification both saves carbon and transforms services to give passengers what they want. Innovation was also the theme of the second Plantworx awards – it attracted 120 entries, we name the winners.

The second part of our HS2 train procurement feature describes pedigree of the bidders who are all offering state-of-the art trains. These will also reduce the UK’s carbon footprint by attracting passengers from less carbon-friendly cars and planes. In an opinion piece, John Downer, of High-Speed Rail Industry Leaders, explains how HS2 will create extra capacity on the West Coast, Midland and East Coast main lines to the north and boost regional economies.

For those going to Railtex, we have a preview of the exhibitors and details of Rail Engineer’s technical seminar programme. Do come to these presentations or join us at our stand.

DAVID SHIRRES – RAIL ENGINEER EDITOR

GRIP (Governance for Railway Investment Projects) process explained

Network Rail developed the GRIP (Governance for Railway Investment Projects) process to manage and control investment projects – ones that enhance or renew the national rail network as opposed to those involved with routine maintenance of the railway. It was developed in order to minimise and mitigate the risks associated with delivering such projects .

GRIP divides a project into eight distinct stages. The overall approach is product, rather than process, driven and, within each stage, an agreed set of products is delivered.

  1. Output definition.
  2. Feasibility.
  3. Option selection.
  4. Single option development.
  5. Detailed design.
  6. Construction test and commission.
  7. Scheme hand back.
  8. Project close out.
The eight stages of the GRIP process.

The stages in detail

GRIP Stage 1: Output Definition

This stage establishes the scope of investment and and the work being proposed. In particular, it considers:

  • The objective, scope, timing, and specification of the enhancement;
  • Funding for the project and any project risks;
  • Procurement methodology: what should be undertaken in development and implementation works;
  • Any likely interface with existing railway operations and other relevant projects and route strategies;
  • Other stakeholder involvement.

GRIP Stage 2: Project Feasibility

Following successful review and prioritisation of the investment proposal, Stage 2 moves the project forward. Where a scheme changes the capability of the railway, for example it changes the timetable or operation of the network, or it integrates with existing major programmes of work, then Network Rail’s System Operator team is likely to sponsor the scheme. Other schemes, such as investment in stations, will be sponsored by Route Enhancement teams.

GRIP Stage 3: Option Selection

At the end of this phase, the following workstreams should have been completed:

  • The various options available to complete the project will have been identified;
  • Each of these available options will have been appraised; and
  • A single option and outline design should be recommended.

The business case should confirm whether or not the project is affordable, including consideration of whole-life cost issues, whether it can be delivered in a reasonable timescale, whether it will provide value for money, and, on this basis, whether to proceed to detailed design and implementation.

GRIP Stage 4: Single Option Development

Development of the chosen single option selected in stage 3 commences to create the outline design.

Outline designs are produced, and any technical or legal issues that could cancel an option or a project are usually identified by this point.

GRIP Stage 5: Detailed Design

The completion of a robust engineering design that provides definitive costs, times, resources and risk assessments.

Stage 5 will deliver the full design to which the project will be built is produced. This includes cost and time estimates.

GRIP Stage 6: Construction, Test and Commission

The project is built to the design and specification detailed during stage 5. It is tested to confirm everything is operating as specified and commissioned into use.

GRIP Stage 7: Scheme Handback

Transfer of asset responsibility from the contractor’s project team to the operator and maintainer.

GRIP Stage 8 – Project close out

The project is formally closed.  Contracts are settled and warranties agreed. Benefit assessments commence and the project team disbands.

Railtex Technical Seminars – Thursday 16 May 2019

Seminars take place in the Rail Engineer Seminar Theatre on stand D61

10:30 – Rail track, real performance
Daniel Pyke
Product Marketing Manager – Rail, British Steel

Aug 2014 – Tata Steel , Scunthorpe site – Rail products

The rail industry faces many challenges – mostly doing more with less:

  • more trains – less headway
  • more life – less cost
  • more distance – less time

When it comes to steel rails, this means that British Steel works with infrastructure owners to develop rails that deliver more life with less maintenance.

The company’s research boffins are consistently on the case, developing more durable steels, but lab testing, however sophisticated, can only reveal so much about product performance.

So take a step out of your business attire to don some orange and have a look at examples of real rail performance:

  • High Performance HP335 rail (HPrail®) – heavy freight troubles tired track
  • Zinoco® – rail rust reveals hidden horrors
  • Multi-Life grooved rail – urban regeneration with a tramway twist

Each example explores typical track challenges and how smart steel selection delivers benefits, helping the industry to build stronger railways.

This covers what’s in Daniel Pyke’s talk – more or less…

11:10 – Innovation in collaborative ground risk management using Geospatial Information Systems
Gerard McArdle – Senior Engineering Geologist, TSP Projects
Callum Irving – Geotechnical Data Manager, TSP Projects

Gerard McArdle

The development of digital ground models has become more widespread over the last few years.

TSP Projects has developed innovative ways of using available technology, working with industry partners such as the British Geological Survey, to improve how information and ground data is managed, assured and shared across organisations. I

If project information and ground management objectives are set and aligned at the start of a project, improved project outcomes can be realised. These can include reducing the programme by early identification of ground risk, increasing productivity in design and construction and developing more accurate cost projections from early project development stages.

Callum Irving

In this seminar, Gerard McArdle and Callum Irving, from teh geotechnical team at TSP Projects, consider the challenges, tools and systems used, such as 3D geological modelling, identification and management of geological and geotechnical hazards, management and assurance of data for use by various parties, efficiencies in collection and the dissemination and use of ground information.

11:50 – KEYNOTE: Devolution and the Digital Railway – A national approach to local needs
Stuart Calvert
Managing Director, Group Digital Railway, Network Rail

Following his ‘100-day review’ of Network Rail, new chief executive Andrew Haines announced that many centralised functions would be devolved out to 13 routes operating in five regions. This included the Digital Railway, which had been seen by many as THE WAY to improve signalling and control, and boost capacity, on a national basis. So how will it now proceed in a devolved environment?

Stuart Calvert, the new managing director of Group Digital Railway, will address just that subject in his keynote address to Railtex. Traffic management is still seen as the way to go, but what of ETCS? Will it be level 2, level 3, or something partway between? And how will the regions differ in their approaches?

Stuart Calvert is the man with the answers, so it will be highly interesting to hear what he has to say.

12:30 – Hydrogen-powered trains – how they help replace diesel
Mike Muldoon
Head of Business Development, Alstom

The rail industry has been set a challenge by government, to replace pure diesel trains by 2040. Whilst bi-modes and battery EMUs/DMUs may suit mixed routes with sufficient electrification, there are huge parts of the network that will never be, and were never planned to be, electrified. These routes tend to be operated by DMUs, regional trains as Alstom defines them.

It is in this area that Alstom sees the application of hydrogen fuel-cell trains helping the industry to meet the challenge and replace diesel. Hydrogen is an efficient energy store and its use is being considered in a huge range of applications within the emerging concept of the ‘hydrogen economy’. Whether used for home heating, industrial processes or powering cars and other modes of transport, hydrogen offers carbon free solutions to some of the UK’s most pressing climate change concerns.

Fuel cells produce nothing but pure water as a by-product of their operation, eliminating CO2 and toxic particulates. When combined with renewably generated hydrogen, they offer lower emissions than even today’s electrified routes, dependent in the national grid.

This talk will explain why hydrogen is viable for this application and how it can be delivered, as a system, to the UK rail network. It will also update listeners on the Breeze concept, unveiled earlier in the year by Alstom and Eversholt Rail as they prepare to convert Class 321 units into Breeze HMUs and start replacing the 2,500 DMU vehicles operating on the UK’s regional railways.

13:10 – Intelligent or closed-loop pantograph
Lee Brun
Engineering Manager, Faiveley Brecknell Willis

The potentially revolutionary intelligent or closed-loop pantograph from Faiveley Brecknell Willis, a Wabtec company, is currently in service trials in the UK and is fitted with fibre-optic sensors which are paired with GPS and Video equipment.

The sensor system measures various pantograph and OLE interface parameters which can then be used to determine the condition of the pantograph or the overhead line with which it interfaces. This data is then presented via a user dashboard which can be used for condition monitoring of either the pantograph\OLE or to actively control the pantograph for optimum performance and current collection.

The system can be retrospectively fitted to any Faiveley Brecknell Willis pantograph and truly demonstrates the organisation’s innovating ambition and ability to collaborate as the idea was initiated through a 2011 collaborative fund grant from the Engineering and Physical Sciences Research Council (EPSRC).

13:50 – KEYNOTE: Labour’s plans for rail
Andy McDonald MP
Shadow Secretary of State for Transport

The Labour Party, and Her Majesty’s Opposition, have their own views on how the rail industry should be run, how trains should be operated and how the system should be financed. In this presentation, Andy McDonald will explain what Labour’s views and policies are, and how he feels today’s railway could be improved for the benefit of passengers and the Nation.

Back to preview
Tuesday 14 May 2019
Wednesday 15 May 2019

Railtex Technical Seminars – Tuesday 14 May 2019

Seminars take place in the Rail Engineer Seminar Theatre on stand D61

10:30 – OPENING CEREMONY
Gordon Wakeford, Co-chair, Rail Supply Group
Anna Delvecchio, Commercial Account Director, Amey

Darren Caplan, Chief Executive, Railway Industry Association
Nicola Hamann, Managing Director, Mack Brooks Exhibitions

Nicola Hamann is the new managing director of show organiser Mack Brooks Exhibitions. Purchased by RELX on behalf of Reed Exhibitions earlier this year, Mack Brooks also organises rail industry exhibitions in France and Italy as well as shows for a number of other sectors around the world, particularly in the fields of industrial fasteners and sheet metalwork.

Darren Caplan joined RIA as Chief Executive in January 2017. Since then he has led the RIA team, with a mission to promote rail supply sector growth and increase RIA’s visibility amongst political and stakeholder decision makers and influencers. Prior to RIA, Darren was for six years chief executive of the Airport Operators Association (AOA), the trade association for UK airports and the sector’s suppliers, where he led award-winning campaigns targeting airport sector growth and fairer levels of aviation tax.

Anna Delvecchio began her career in rail as an apprentice. Now commercial accounts director at Amey, she is currently seconded to the Rail Supply Group and was part of the team that drove through the recently announced Rail Sector Deal between industry and government and is the current Transport Woman of the Year, as announced at the 2018 FTA everywoman in Transport & Logistics Awards.

Gordon Wakeford is head of Siemens Mobility in the UK and also co-chair of the Rail Supply Group, a role he shares with the Secretaries of Sate for Transport and for Business. As such, working with a team that included Philip Hoare of Atkins and Anna Delvecchio of Amey, he was instrumental in developing the Rail Sector Deal.

He will deliver a keynote speech on the topic of the Rail Sector Deal later in the morning.

11:10 – Predictive Maintenance Strategies for Continuous Track Monitoring
Deep Desai
Business Development & Strategy, Frauscher Tracking Solutions

Reducing maintenance costs is a task of high importance. Systems, which enable a complete and continuous monitoring of assets on tracks, can support appropriate approaches. Additionally, they can provide relevant information to improve efficiency and traffic management.

Due to the importance of such applications, and based on the high number of components that need to be monitored on tracks and trains, a vast number of technologies and systems are available today to meet all related requirements. This plurality, as well as the fact that several units might be needed for various tasks contribute to rising efforts.

The newly developed Frauscher Tracking Solutions FTS provides a vision of an efficient solution to continuously monitor the track health outlining a paradigm shift towards predictive maintenance strategies. By continuously monitoring the wheel-rail interaction, the Frauscher Tracking Solutions FTS detect changes in the condition of various assets at a very early stage. This forms the base for a cost-effective option to continuously monitor components on tracks of a whole network at a glance.


11:50 – KEYNOTE: The Rail Sector Deal – Working together for the future
Gordon Wakeford
Co-chair, Rail Supply Group

The Rail Sector Deal will build on the strong partnership working between the rail sector and the government to exploit the opportunities of new technologies, improve the efficient use of rail network capacity and enhance the experience of those who use the railways.

In its foreword, the Rail Sector Deal states that it will enable companies to drive innovation, invest in research and development, up-skill the workforce and look beyond the UK to export markets worldwide. It will provide certainty for the industry, with clarity and involvement in shaping investment in the railways for the first time, and, through this collaboration between government and businesses, it will provide better railways for the country’s rail customers.

In his keynote address, Gordon Wakeford will consider just how implementation of the new Rail Sector Deal will help improve both the railway and its supply chain. What is needed to make it more efficient? And what export opportunities could present themselves once the Rail Sector Deal starts to make itself felt?

It is too easy to see the railway as a mode of transport, which of course it is, and not to remember it is also a business – but it is.

12:30 – CBTC or ERTMS? The answer is ATO
Ian Jones
Key account manager, Siemens Mobility

The railway industry is seeing unprecedented rates of change. The move towards a ‘digital’ railway has seen a significant acceleration in the adoption of new technologies, not least those that provide command and control of the trains themselves.

The railway press is full of references to technologies including communication-based train control (CBTC) and the European Rail Traffic Management System (ERTMS). These systems unlock capacity and improving safety levels through the use of secure digital radio messages sent between trackside and train-carried equipment, allowing levels of throughput and operational flexibility that were not previously possible.

These train protection systems are only half the story though; automatic train operation (ATO) uses computer-based technology to drive every train at the optimum speed at every location along a track.

Whilst ATO has been part of the metro railway world for some 50 years, it is new to main line operation. On London Underground’s Victoria line, a 36 trains-per-hour timetable is delivered smoothly and efficiently by ATO-driven trains under the supervision of a world-class control centre solution that continuously evaluates the state of the railway and makes adjustments to service to maintain 100-second headways.

The Thameslink project takes a similar approach on a heavy suburban system running through severely constrained infrastructure, using ATO not only to ensure that every train can make use of the capacity unlocked by ERTMS, but also to optimise the use of energy and infrastructure as well as minimise wear on critical rolling stock components.

13:10 – How can we digitise the journey to benefit the customer?
Mike Hewitt
Chief Technical Officer, ADComms

How do we deliver a customer-focused transport model? The rail industry needs to meet the challenge of future multimodal journey options, including ride sharing application, autonomous vehicles, drone-based taxis, personal vehicles, and the challenges that rail transportation will face from new connected modes of transportation, and become integrated into one of many options that the passenger will have.

It’s no longer just about getting from A to B – the passenger demands connectivity, information, and reliable infrastructure to get them from their home to their destination.

How does the rail supply chain respond to these challenges? What are the opportunities to introduce technologies like IoT, BlockChain/Distributed Ledger, Assisted Intelligence, Additive Manufacturing, and Automation to deliver innovative new solution into legacy infrastructure?

In his presentation, Mike Hewitt will look at the challenges that connectivity presents, and the opportunities it enables – at the application of new technologies, and collaboration that will enable innovation. He will talk about the security implications and considerations, including cyber security, when mixing and supporting legacy and connected infrastructure.

Lastly, he will consider the models that the railway will need so that it can engage and collaborate with innovators, SMEs and the large organisations so as to bring true innovation to the rail industry, to allow it to be more responsive, more agile and be able to apply new ways of working that reflect local needs and deliver a resilient, reliable end-to-end journey that places rail at the centre of connected passenger journeys and the centre of freight transportation for the next 50 years.

13:50 – Signal and Stop Board Stand Back survey and assessments
Simon Gardiner, Managing Director, Gioconda
Steve Jones, Production Manager, Gioconda

Simon Gardiner, Gioconda.

Gioconda was established in the UK in 2006, specifically to develop desktop signal sighting tools for the UK rail market.

The award of two Network Rail framework contracts helped to establish the business as a primary source for UK signal sighting and driver briefing. Since then, Gioconda has worked on some of the biggest and smallest projects in the UK and prides itself on the quality, accuracy and efficiency of its services.

In this presentation, Gioconda will take you through the process it uses to capture, process and report on cab stand back to stop board validity.  The speakers will explain to delegates:

  • How to use simple train-borne video correlated to aerial imagery for a stage 1 check;
  • Options for a more detailed, higher accuracy, stage 2 check;
  • The modelling process to use where remedial action is required.

The presentation will demonstrate how this can be used in an underground situation and talk about the varying limitations imposed by operators when arranging to capture data using in service and special train services.

14:30 – ZF EcoWorld: Efficiency with Connectivity
Steve Brew
Key Account Manager – Rail Drive Systems, ZF Friedrichshafen

ZF Friedrichshafen is involved on a number of projects to introduce high efficiency ZF EcoWorld2 transmissions as retrofit option for existing DMU trains in the UK.

This is also an opportunity to showcase ZF Smart condition monitoring technology being developed in line with the company’s ‘See = Think = Act’ principle.

In his presentation, Steve Brew will aim to provide an introduction to the feature of ZF EcoWorld2 with an overview of ZF Connect@Rail digitisation for Rail applications.

15:10 – Trust: How cyber secure are you?
Steve Little
Cyber Lead, Frazer-Nash

There is an unprecedented amount of investment, and hence change, in the UK rail sector – spanning major infrastructure projects, the replacement of rolling stock, staff processes and procedures, and methods for accessing train information and buying tickets. The introduction of new systems is complicated by having to co-exist with legacy systems and practices dating back over many decades.

The rail sector has, for many years, been an evangelist in ensuring the safety of passengers and staff. However, as a consequence of digitalisation and legislation, the threat posed from cyber space is being considered – specifically how to identify, protect, detect, respond or recover from a cyber-attack.

Typically, this has been considered solely a technology problem, but complex enterprises, such as the rail sector, are an amalgam of People, Processes, Information, Technology and Facilities (PPITF).

Countering these cyber threats, and the risks they pos,e requires a whole system approach and understanding of PPITF and the interdependencies between them. In tackling this challenge the rail sector could learn lessons from other sectors, balancing the new with the legacy, ensuring any mitigation or response is both appropriate and proportionate.

As part of his presentation, Steve Little will provide insight into how other sectors such as energy and defence understand and mitigate their cyber risk by considering PPITF holistically.

15:50 – Real-time remote diagnostics and condition monitoring
– improving asset utilisation and reducing maintenance cost
Severinas Monkevicius
Product Manager, Trimble

As the world population increases – and becomes increasingly urban – the need for efficient transportation networks becomes ever more pressing. The pressures on modern train operating companies increase every year – as networks reach capacity and assets age. Efficient management of rail assets requires accurate, authoritative data delivered in a timely manner.

The focus of rail asset lifecycle management technology (which encompass real-time remote diagnostics and proactive component condition monitoring) is the automated collection and analysis of data to allow for high performance asset management and planning, allowing train operators to increase utilization and reduce maintenance costs. The lifeblood of these solutions is actionable intelligence derived from the processing of the abundance of raw data available from sensors on-board and wayside.

Drawing on recent project examples from across the European passenger and Australian freight sectors, this presentation will look at the benefits of rail asset lifecycle management and demonstrate how many customers are deriving real value from these solutions.

The seminar programme in detail:

Back to preview
Wednesday 15 May 2019
Thursday 16 May 2019