Home Blog Page 209

Wheel counting in Vienna

Railway track experiences all the climatic extremes the planet can throw at it. It is also subject to heavy loads, vibration, pollution and electromagnetic interference. This is not the ideal environment for an exposed electrical circuit that is a safety-critical element of the signalling system.

That said, track circuits are generally highly reliable but, when they fail, this is usually due to environmental conditions completing the circuit.

As the system fails safe, there is no safety risk but such failures have a high service impact. This is one of the reasons that axle counters are increasingly popular and are now the train detection system of choice for Network Rail.

This much was apparent from the recent 2015 Wheel Detection Forum in Vienna, which was a three-day event attended by over 200 delegates from 34 countries. This was the third such forum, a bi-annual event organised by the Austrian company, Frauscher Sensortechnik GmbH. However, this was not immediately apparent, as its focus was the benefits of axle counters, rather than its own products.

Keynote speakers

With the exception of Wabtec’s Dwayne Allan, the opening keynote speakers said little about axle counters. Dwayne’s presentation concerned axle counters in Australia and New Zealand where they were introduced in the 1980s. Their early use was on ‘long skinny railways’
as, unlike track circuits, there is no restriction on signal section length if axle counters are used. Other advantages of axle counters were the removal of insulated rail joints and the ability to alter signalling functionality during infrastructure upgrades.

Presentations on the project management challenges of installing railway infrastructure in the 57km Gotthard Base Tunnel and the expansion of Turkish railways were fascinating. As far as track circuits were concerned, the Forum learnt that the new Gotthard tunnel used Thales axle counters and that in Turkey there was a mix of detection systems, with track circuits presenting the greatest reliability issue.

Max Schubert of DB Mobility Networks Logistics explained how Fibre Optic Sensing (FOS) detects wheels and anything else along the infrastructure causing ground vibration. This may be quite tiny, for example a human footstep.

FOS measures changes in reflected light from micro deformations in a calibrated fibre that typically can provide a ‘microphone’ every 10 metres over a 40km length. With fibre cables commonplace along the infrastructure, FOS can make use of spare fibres without the cost of additional infrastructure.

The FOS technique is being evaluated on a 33km section of high-speed line in Germany. This has identified 27 potential applications, one of which is timely station announcements of trains approaching at over 160km/h. Initial results indicate that FOS can fulfil this requirement. Although it is not certain whether FOS can be developed to the safety integrity level required by signalling systems, this trial shows its potential for other applications in the near future. In Britain, FOS is now used to detect rocks falling onto the Oban line from the steep slopes of Ben Cruachan.

Axle counter system

For signalling, the axle counter system consists of the wheel sensor, axle counters and communication with the signalling interlocking. Modern wheel sensors are mounted on the inner face of the rail below flange height. They have two upward facing magnetic coils. Wheels are detected when the voltage of the alternating current in the coils is suppressed as a wheel flange passes over them.

This is not the simple piece of kit it might be thought to be. The coils need to be immune to electromagnetic interference, for which Frauscher has developed the V.Mix technology.

This combines three inductive processes (inductivity, field deflection and eddy current/ hysteresis) to increase the sensor’s resistance to electromagnetic interference, linear eddy current brakes and electromagnetic rail brakes. Coils also have to operate consistently between -40°C and 100°C, despite significant changes to the conductivity and permeability of the coils’ iron cores over this temperature range.

header_sensoren [online]

The axle counter is the electronics that interprets the wheel sensor output. To do this, the counter’s evaluation board (EB) converts analogue signals from the wheel sensor coils to a digital pulse. As well as counting the number of axles over the sensor, the EB also detects direction and speed by comparing signals from the two wheel sensor coils. It also has a logic circuit that counts axles in and out of each signal section to determine whether the section is occupied or clear.

The axle counter unit also incorporates a power supply with over-voltage protection. If not directly wired to the interlocking, it also has a communications board to transmit clear/occupied section data and receive requests for resets.

Resets may be required as axle counters, unlike track circuits, do not continuously detect trains. Instead, they use logic to determine whether a section is clear using data from individual wheel sensors. When normal operation is disturbed, for example by equipment failure or engineering work, the normal logic does not apply and a potentially disruptive system reset is required.

Automatic reset

The Frauscher FAdC axle counter system has a high availability as it is designed to largely eliminate such disruptive resets without compromising safety. As Phil Blacker of Atkins explained, this approach assumes that trains cannot fly or materialise out of nowhere.

The FAdC system offers two ways of doing this: counting head control or supervisor track sections. The basis of counting head control is that, as the axle counter system knows where trains are, it also knows when a train is approaching a wheel sensor. Hence, it can identify wheel sensor signals that are not trains, for example maintenance trollies.

Supervisor track sections are two adjacent track sections. If there is an abnormal operation of the middle wheel sensor, the sensors at each end of the supervisor section will still count the same number of axles into and out of the larger section. The supervisor track sections overlap so that each track section is part of two of them. If there is a track section fault, the sensor concerned can be automatically reset provided one of its supervisor track sections is clear.

UK standards do not yet allow for axle counter resets using counting head control and supervisor track sections. However, use of these techniques to improve axle counter availability is being actively progressed and has attracted worldwide interest.

Monsoons, lightning and pythons

The forum heard how monsoon floods, frequent lightning strikes and pythons climbing up overhead line masts affect tropical railways.

Whilst pythons are not a problem for the UK, floods are. Lightning strikes are also not unknown. Anthony Darama Rajan, signalling manager for Kuala Lumpur’s 59km airport link, advised that Malaysia has up to 250 thunderstorm days a year. He explained how axle counters had proved resilient to the flooding and made a significant contribution to the air link’s 99.83% on-time service performance, once wheel sensor earthing had been modified to prevent wheel sensor damage from frequent lighting strikes.

Flooding is an inevitable consequence of Mumbai’s monsoons, as illustrated by Sanjay Singh, S&T general manager of Mumbai Railway. His presentation showed packed trains running whilst water was at rail height as wheel sensors continued to function. With 7.6 million passengers a day on its 319 km suburban network, reliability of Mumbai’s signalling equipment is crucial. In 2012, Frauscher provided 1,900 counting heads and 1,400 track sections to upgrade this system.

Sanjay explained that, in addition to the sensor’s high environmental resilience, Mumbai’s railways achieve high signalling availability by using supervisor track sections, counting head control and redundancy from overlaying axle counters on track circuits.

This arrangement allows combined Counting Head Control and trolley suppression track circuits to avoid resets from use of maintenance trollies. Trolley suppression track circuits do not detect trolleys as they have insulated axles. Using Counting Head Control, the wheel sensor will ignore the two axles of trollies if the adjacent track sections or trolley suppression track circuits are clear. In case the track circuit gets occupied by the passing of another vehicle, the connected wheel sensor gets activated and following sections detect passing trains.

Ethernet communication

Various speakers mentioned the advantages of a decentralised architecture, made possible by modern transmission technologies. This presents security and reliability issues for which the Frauscher Safe Ethernet protocol has been developed as an option for system integrators who do not have their own protocol.

Providing the required software interface to exchange data between the axle counter and higher-level systems, this protocol also transmits data for diagnostics and centralised remote monitoring.

An example of such decentralised architecture is the modular signalling installed between Crewe and Shrewsbury in 2011 by Siemens, the first such system commissioned by Network Rail. This required 79 wheel sensors with the Frauscher FAdC axle counting system installed in 19 external cabinets. Communication between these cabinets and the Westrace interlocking is through an Ethernet connection using duplicated fibre optic cables.

Data transmission between axle counters and signalling interlocking by open Ethernet networks over a radio network also offers significant installation savings by eliminating cable routes. This does, however, present the challenge of providing a power supply for the wheel sensor. It seems this is not an issue for countries like Australia where the sun always shines on the sensor’s solar panels.

Level crossings

Speaking by Skype from India, Petchimuthu Gopalakrishnan advised how India’s 40,445 level crossings account for 44% of the country’s railway accidents. He referred to the advantages of axle counters for train detection.

In particular, he thought mass violations of level crossing rules by vehicle drivers would reduce if crossings did not have excessive warning times. In this respect, the easy adjustment of wheel sensors location was useful.

In Europe, level crossings account for 29% of all railway fatalities. José Fonseca of the Portuguese company EFACEC and Laurenz Trunner of the Austrian company EBE solutions are both concerned with the manufacture and installation of level crossing systems for which they offered the forum similar insights.

They both considered axle counters to be a more reliable and flexible solution than track circuits or treadles, an important consideration when railways have differing crossing detection requirements. They also noted that axle counters made it easier to optimise crossing warning times. Unlike track circuits, axle counters are not affected by rusty rails at crossings with few rail movements.

Ethernet-based communication reduced installation costs, allowed for remote monitoring of multiple crossings and supported integration with signalling and road traffic systems as required.

José Fonseca noted that EFACEC’s previous use of track circuits resulted in, typically, one defect per year per crossing. Since axle counters were introduced there had been virtually no failures.

Oiling the wheels

Presentations by America’s BNSF Railway, Progress Rail, Hegenscheidt and LORAM made it clear that large numbers of wheel sensors are used in non- signalling applications. For such use, Frauscher recently launched a stand-alone wheel sensor with an open analogue interface allowing it to be used with a wide variety of equipment.

Bombay trains [online]

Vennie Dyavanapali of LORAM estimated that, in North America, track lubrication systems use an estimated 25,000 wheel sensors of which around 90% are in yards with the remainder on the main line. Since 1900, flange lubricators have reduced the coefficient of friction at the gauge-face, typically to 0.05. Top-of-rail lubrication has been used in yards since 1995 and on the main line since 2005. This accommodates wheel speed differences on curves by applying a friction modifier to give a coefficient of friction of typically 0.3.

Wheel sensors ensure the correct amount of lubricant is applied. For top-of-rail lubrication, they also ensure lubricant is not applied until the locomotive has passed.

Axle counters monitor lubricant consumption and are used for billing. In yards, wheel sensors also control wagon speed, determine car location, detect stalled cars and activate wayside equipment such as scales and wheel cleaners.

Vennie noted that, for track maintenance, wheel sensors needed to be installed and calibrated in less than two minutes. They also needed a very low power draw, to be immune from AC interference, and to have wireless capabilities. Frauscher wheel sensors meet these requirements. In particular, with no requirement to drill the rail, sensors can be quickly installed as they are mounted using a rail claw.

Automated train monitoring

Hark Braren of BNSF provided another North American perspective with his presentation on the use of trackside equipment to prevent wagon derailments. This equipment uses various sensors, generally at common monitoring stations. Bearings are monitored by acoustic sensors and hot bearing monitors that measure surface temperature. A wheel impact detector measures flats and other wheel defects.

Vision Monitoring assesses bogie geometry for worn wheels and poor steering as well as broken springs and friction wedges. It also identifies missing fasteners, broken welds, damaged structural components, defective couplers, low air hoses and wheel tread defects. Accurate wheel detection is an essential part of these monitoring stations, both to trigger the monitoring equipment and specify the location of any train defects.

Progress Rail, Germany, has developed a vehicle monitoring checkpoint for use before tunnels. This detects dragging equipment, out of gauge loads and has hotbox detectors. Throughout Europe, around 1,200 FUES hot box detectors are in use, including 145 in the UK. These monitor external and internal bearings, wheels and brake temperatures. They require accurate wheel sensors to trigger the temperature sensors and provide data on speed and direction.

Wheel lathe company Hegenscheidt has developed its ARGUS II system to monitor wheels using various sensors to detect cracks and measure the diameter, roundness and wheel profile. This is done at up to 15km/h in a depot monitoring station that also identifies the train by, for example, transponders or optical character recognition. The results are stored on a database and used to assess wheel life and time to the next wheel turning. Accurate wheel sensors are an essential part of this system as the monitoring cameras and lasers need to be triggered at exactly the correct point.

Hegenscheidt’s Peter Neumann stated that this system is to be developed for main line use at speeds up to 100km/h. For this, the Frauscher wheel sensor triggers when the dip voltage of its two coils is equal. Initial results are that, at speeds between 40 and 60km/h, wheels of 513 and 755 mm diameter can be detected within ranges respectively of 5.2 and 3.2 mm. As this was not sufficiently accurate, further development work is being done.

Far and wide

The 2015 Wheel Detection Forum certainly offered wide-ranging presentations. Many had travelled far to attend it. No doubt, they found it worth their intercontinental journeys. This worldwide spread of delegates was a reflection of the installation of over 100,000 Frauscher wheel sensors in 70 countries, giving the company a market share of around 40%.

It was clear that axle counters offer significant benefits, so wheel sensors installations are likely to have significantly increased by the next Wheel Detection Forum, in 2017. It will be interesting to see what this next Forum has to offer.

In case you missed it: It’s like cement but different

We all live in a world where any form of disruption is a major issue which dramatically affects our wellbeing. The infrastructures we use on a daily basis, especially rail, roads and highways, constantly need maintaining as they are often used at full capacity. This problem also extends to utilities – water, gas and electricity distribution – power stations, marine environments and others. Much of this infrastructure, especially within cities and large towns, now can’t cope with the demands put upon it.

The net result is that these indispensible systems have begun to wear and fail at a higher rate and speed than may have been the case in the past. They now require a higher level of repair and maintenance to keep them operational, and this has to be carried out with less access time to keep traffic flowing and trains moving. As a result, there is an ever-increasing need for high-performing products to achieve the best level of repair in the shortest time.

A lot of infrastructure repairs require the use of cement. It’s easy to buy, simple to use, and relatively foolproof – in normal circumstances.

Re-engineering the product

Portland cement has been the standard for many years, but also has had some shortfalls. It shrinks excessively, can’t be accelerated without negative effects, is susceptible to attack by prevalent chemicals and reacts destructively with certain aggregates. None of this makes it ideal to use in today’s high- pressure maintenance environment.

CTS Rapid Set products provide cementitious solutions to this problem, with products that cure in a very short time and allow operations to continue with a minimum of disruption. There is also a specialist selection of additives available that give versatility of use to the three main products that are used to cover most repair and maintenance works.

Market leaders in USA, CTS Rapid Set products are fast becoming established across Europe, Asia and Australia and have recently been introduced to the UK. The three main products have recently been added to the London Underground Approved Products Register and are likely to be adopted for use within LUL civils maintenance works.

Rapid Set Cement is an advanced high-performance hydraulic cement that provides structural strength in one hour. It is manufactured with the same raw materials, equipment and processes used to make Portland cement yet has reduced shrinkage and superior resistance to chemical attack.

Precise selection and proportioning of the raw materials, many refinements throughout the manufacturing process and comprehensive quality control combine to give Rapid Set superior performance and a unique chemistry.

When Rapid Set cement is used in concrete, it provides superior performance in terms of rapid strength gains, reduced permeability and low shrinkage. Traditionally, when fresh concrete is placed using conventional Portland cement, the heavier particles settle and displace the water mix which then forms capillaries as it rises to the surface as bleed water. After the concrete has hardened, these capillaries become routes of entry for substances that attack the concrete and reinforcing steel.

When Rapid Set cement is used in concretes, repair mortars, or any other Rapid Set products, it produces ettringite crystals that rapidly consume water and create a three- dimensional lattice. This stops the settling and displacement process, eliminating the capillary formation which reduces permeability and resulting in a more durable concrete.

Comprehensive range

Rapid Set cement forms the basis for several easy-to-use products.

Cement All is a multipurpose product that can be used for general concrete repairs, doweling, anchoring, industrial grouting and form work. It can be used from a feather-edge up to 100mm thick, the surface does not need priming, and can be water cured. It has an initial set time of 15 minutes and can be trafficked in one hour.

Mortar Mix is a versatile product that can be used for general concrete repairs to floor slabs, vertical and overhead applications. It is a high performance blend of Rapid Set cement and quality sands. Mortar Mix is non-metallic and has no chlorides and, when mixed with water, it produces a workable high-build mortar that can be applied anywhere from 10mm to 150mm thick. It too sets in 15 minutes and can be trafficked in one hour.

Concrete Mix is a multi-purpose, fast setting product that can be used for repair and construction of floor slabs, machine bases, and general concrete repairs. It is a blend of Rapid Set cement, grades of sands and 8mm aggregate.

When mixed with water, Concrete Mix produces a workable, high-quality concrete material that is ideal where fast strength gain, high durability and low shrinkage are desired. It can be applied from 50mm – 600mm in depth, is durable in wet environments, sets in 15 minutes and is ready to traffic in one hour.

In addition, there is a range of specialty additives for retarding setting, increasing flow ability and including reinforcement fibres.

All of which can come in handy when repairing a railway at two in the morning when trains are due to start running in a couple of hours.

Crossrail gets its rails

Andrew Briffett

The tunnelling is finished. It’s time to start building a railway. Ok, here at Rail Engineer we’ve taken an interest in the Crossrail tunnelling machinery. We’ve marvelled at the wonders of steering a delicate path through all the services and foundations beneath London. We’ve looked at the logistics of shifting all the spoil and the creation of a wetland nature reserve twice the size of the City of London at Wallasea Island in Essex.

But we’re really railway engineers, not tunnellers, and so it’s now, with the tunnels completed, that our enthusiasm for the project really kicks in. Over the coming months we’ll be looking at how an almost bare tunnel will be kitted out with the paraphernalia of a railway and how all that stuff is integrated to form a complete system capable of running a service of up to a train every two minutes.

This month, David Bickell covers the signalling and the transition from Network Rail to the Crossrail system and back again. In future issues, we’ll be looking in detail at the track installation equipment and how everything fits together, as well as delving into the power requirements and the overhead power delivery system.

And amongst all this there will be coverage of the logistics involved in not only feeding this voracious project but how all the various sites are kept safely apart. Of course, everything will depend on telecoms right through and beyond the construction phase.

But this is all to come. In the meantime we look at how things are at the moment with the rumble of the tunnelling machines now a thing of the past.

The contractor undertaking the Crossrail railway systems main works, contract C610, is ATC – a Joint Venture comprising Alstom, Transports Sud Ouest (TSO) and Costain Limited.

Gregg Purcell (Crossrail’s railway systems construction manager) and his team weren’t waiting for the last bucket of spoil to be transported along the Thames before they got into the tunnels. As each TBM receded into the distance, and its roar became more and more muffled, the railway began to take shape behind them.

The bore has not been left as a plain tube. It’s not entirely without a railway form. The tunnel construction team built mass concrete – ‘first stage’ concrete – up to just below slab track level along with walkways on either side. These walkways are a crucial part of the scheme of things.
It is on them that specialist multi purpose gantries run conveying the first components to make up the track structure, as we’ll see in a moment.

Version 2

Track types

The track support comes in five different assembly types:

» There’s direct fixed track – used in the Victorian-engineered Connaught Tunnel;

» For most of the railway there’s standard track slab using fibre reinforced concrete;

» High attenuation sleepered track – similar to standard slab – is used only in a few small areas to reduce noise/vibration;

» Floating track slab (light) is used to reduce noise and vibration underneath Soho;

» Floating track slab (heavy) will be installed to reduce noise and vibration underneath the Barbican.

Direct fixed track has been used within Connaught Tunnel. The track bed, a concrete reinforced structure, allows engineers to create a flat surface on top of the significant undulations in the ground and to work within the height restrictions which are a feature of this Victorian- engineered tunnel. A total of 2.6km of direct fixed track has already been installed.

Floating track slab (light) goes in between Tottenham Court Road and Bond Street to minimise noise and vibration impacts from the operating railway on nearby recording studios and hotels which is a requirement of the Crossrail Act. The track slab is cast and then jacked up so that it ‘floats’ on a combination of elastomet rubber bearings and heavy-duty springs installed beneath it. A total of 1.97km of floating track slab (light) will be installed.

Floating track slab (heavy) will be used in the Farringdon area due to the close proximity of the Barbican. It sits on heavy-duty springs. A total of 1.34 km of floating track slab (heavy) will be installed.

Due to the extra depth added by the spring base of the floating track, a stiff shallow slab is needed. To ensure that the shallower slab remains durable and effectively minimises noise and vibration, an unusually dense concrete called Magnadense is used. Magnadense, manufactured by LKAB Minerals, is over twice as dense as normal concrete due to its natural iron ore content.

Heavy!

Behind this one word, Magnadense, lies a whole story of engineering discovery in the UK. It’s a concrete type used extensively in Sweden as a way of making sure that house basements are heavy enough not to float in the high water table over there. There has been little use in the UK until now and so this has been a steep learning curve.

Gregg’s aside: “On the team is a gentleman who has poured vast quantities of the stuff in the French nuclear industry and his experience has helped with a range of novel issues that we have had to overcome.

This concrete is so dense that a full concrete lorry will be heavily overloaded. Road vehicles have to run half full to keep within standard HA loading. Batching plants have to learn how to handle it. Costs rise.”

Short test tracks will be used to test the construction methods, materials and equipment as well as for training purposes. A 100 metre long stretch of standard track slab has been built at Plumstead, a 30 metre section of direct fixed track has been constructed beside the Connaught Tunnel in Silvertown, and a 100 metre curved section of floating track slab has been built at Old Oak Common.

The majority of the track in the central section (about 80%) is standard track slab. This amounts to a total of 41.2km.

When constructing the standard track slab, the initial sequence of work is carried out by four multi- purpose gantries which transport and accurately position around 70,000 sleepers and 57km of rail in Crossrail’s central section. Each gantry, operated by a single person, will run along the raised curbed sides of the tunnel’s first stage concrete mentioned earlier.

After positioning 108-metre- long sections of rail along a stretch of tunnel, the gantry then carries and deposits sleepers at carefully measured intervals before lifting the rail into place on top of them. The track is then secured in place using clips, props and jigs before it is welded and the formation is concreted into position.

Two gantries will operate from Plumstead, one from Westbourne Park and the other will install the floating track slab underneath the Barbican estate.

The bespoke gantries have been manufactured for Crossrail by Metalliance in France and were delivered to London in August 2015.

Railheads

The two main temporary logistics centres for Crossrail’s railway systems are located at Plumstead in southeast London and Westbourne Park in west London. These will be used by the many different engineering trains during the fit-out of the tunnels and stations.

Plumstead is the larger of the two railheads with a total of eight tracks, an overhead gantry crane to supply engineering trains and an operations centre to coordinate the activity.

At Westbourne Park, the previous railhead that was constructed for the transport of excavated material from the western tunnels is being replaced with a new three-track railhead. The materials needed for the western tunnels fit-out will be stored and loaded onto construction trains at a temporary storage depot at Old Oak Common and brought to the Westbourne Park railhead.

Concreting train

The concreting train is a sophisticated mobile underground concrete batching factory, which is the reason for its significant length. Dry materials are loaded onto the concreting train, which then batches the concrete. At 465 metres long, this train plays a key role in creating the standard track slab. Refurbished and brought to the UK from France via the Channel Tunnel in August 2015, it will be based at Plumstead and used in the installation of standard track slab. At its peak production rate it will be able to install up to 250 metres of concrete track slab a day.

Running and maintaining the concreting train is a 24-hour operation. Concrete pouring will take place during the night with restocking and maintenance being carried out during the day. When the concreting train is not operating in the tunnels, it will be split in two due to its size and will be located on two of the eight railhead tracks.

Concreting shuttle

A concreting shuttle will be used to construct the standard track slab in the tunnels between Royal Oak Portal in west London and central London. Pre-mixed fibre reinforced concrete, provided by a batching plant at Paddington New Yard, will be loaded onto the shuttle. The concrete shuttle will be delivered to Westbourne Park in January 2016.

The main difference between the train and the shuttle is that the train is loaded with dry materials, the shuttle with conventional ready-mixed concrete. It has around half the output of the concreting train but is much shorter – a factor driven by the limited room available at its stabling point in Westbourne Park.

multi-purpose-gantry-lifting-sleepers-into-place-in-thames-tunnel_214853_22715770194_o [online]

Gregg observes that, with the shuttle, “you’re up against the clock the moment you load it up!”

Track installation

Around 70,000 sleepers have been manufactured for Crossrail by SBC Rail (Stanton Bonna) in Nottingham, a Consolis Holdings (SAS) company. These sleepers will be delivered into the Crossrail tunnels in bales by construction trains from Plumstead and Westbourne Park.

A specialised welding machine will be used to join the 108-metre-long sections of Crossrail’s permanent rail together. Tata Steel will supply more than 57km of its heat-treated, wear-resistant rail. The steel blooms are being manufactured at Tata Steel’s plant in Scunthorpe before being rolled at the company’s Hayange

mill in northern France and delivered to the Plumstead Railhead via the North Kent Line. Tata Steel will also deliver rail to the Westbourne Park railhead from January 2016 to support the track installation process in the western tunnels.

Drilling rig

As part of the tunnel fit-out, over 250,000 holes will be drilled to accommodate brackets for cabling, walkways and other equipment to support the operation of the railway.

ATC Joint Venture will deploy a state of the art, precision automated drilling rig which will drill many of the holes required, minimising the need for manual drilling. The Crossrail drilling rig was manufactured by Rowa Tunnelling Logistics in Switzerland and arrived in November 2015.

Once the track slab has been laid, the rig will sit on the track and move its way through the tunnels drilling the holes in pre-determined locations. The machine has a dust suppression system in place, producing a clean and accurate drilled hole every time. The drilling rig works in conjunction with real-time 3D laser surveys of the tunnel to ensure accuracy.

Powering Crossrail

The Crossrail route will be powered by a 25kV overhead line system. A rigid overhead conductor bar will be installed in the tunnels.

In the central section, traction power for the Crossrail trains will be provided by two new bulk supply points from National Grid at Pudding Mill Lane in the east and Kensal Green to the west.

A 22kV high-voltage network will be installed by AC (just Alstom and Costain without TSO) in the central section from Royal Oak Portal in the west to Limmo Peninsula in the east with an 11kV high voltage non-traction spur to be installed from Limmo through to Plumstead. This network will supply mains power to each Crossrail station, shaft and portal within the central section.

Crossrail’s communications and control systems

New communications and control systems will be installed throughout the new Crossrail stations and tunnels. These include:

» Customer information systems – customer information displays in ticket halls and concourses and at each platform screen door;

» CCTV – Digital cameras for station control and security while views of the platform are also transmitted to the drivers cab for driver only operation (DOO);

» Radio – Provision of radio infrastructure / network for operations and emergency services;

» Public Address System – For general and emergency announcements.

Current Crossrail progress

Construction of the logistics centre at Plumstead is complete. The construction of the Westbourne Park temporary railhead is underway.

The first delivery of permanent rail was made in August 2015 and installation of permanent track is also underway.

So, that’s the state of railway engineering on Crossrail. If you’re really bereft of the delights of tunnelling, then there will be three whacking great machines chomping their way through the London Clay from next year. However, these will be constructing the Thames Tideway – a tunnel just a little larger than Crossrail, but which will be transporting something considerably less wholesome.

In case you missed it: RVE 2015 best yet!

Rail Vehicles and Enhancements – RVE 2015 – did just what it says on the tin. Billed as “the only single-theme Expo aimed at the engineering of rail vehicles for refurbishment and enhancements”, the one-day show changed venue for its fourth year, moving to Derby’s Riverside Centre early in October.

It was very much a move for the better. The main exhibition hall was larger and accommodated the wide range of exhibitors with ease while not looking empty, and there was a buzz about the place all day.

This is a working show. Exhibitors were given limited space in the main room for a couple of pop-up banners, a table and a small display. No more was needed and it kept everyone on an equal footing.

The specific focus kept it sensible as well. It was all about the technology that goes into rail vehicles. So there were radios, and seats, and pantographs (OK – they actually go on top), and cables, and connectors, and passenger information systems, and even aromas (do you want your carriage to smell nice?).

Just through a doorway was another room, set up as a seminar theatre. Here Ian Walmsley, journalist for another publication (one you can buy in Smiths!), presided over an interesting series of talks and seminars that ran through the day.

Started with a bang

But what of the show in detail? It started early with a networking meeting by Rail Alliance in the theatre. Bacon cobs (baps, rolls, butties – call them what you will) were provided, along with tea and coffee, so the early birds could have breakfast, network with colleagues and hear a couple of presentations on ‘sensitive design’ from Veronica Elena Bocci and Luis Chomiak.

Meanwhile, next door, banners were being erected, tablecloths hunted down, and everyone was bustling about getting ready for a 9am start. Rail Media’s stand was up and ready early, and we seemed to be the designated table supplier, if only because the pile of tables had been leant against the wall next to our stand!

All was ready in time, and the first of around 500 visitors came through the door. Within half an hour it was really quite busy!

It was time for a cast around the show and, without naming everyone there (if you want to have a full list, the website is still live at www.rve2015.co.uk), there were certain stands that caught the eye.

DSC_3249 [online]

Lots to see

Harting had several boxes of connectors and jumper cables, including a neat way of pulling new cables through tight spaces in older vehicles. The cables are fitted with a slimline connector, looking a bit like a telephone plug. A pulling eye can then be snapped to this connector and used to pull it through bulkheads and cramped spaces. Once the cable is where it is meant to be, the eye is snapped off and the appropriate connector to interface with the equipment snapped on. Very convenient, and a great idea.

Insurance specialist Jobson James was next. Their advice to clients was simple – read the contract. In particular, check it for insurance implications as clauses in some contracts can invalidate insurance, which isn’t something you want to discover when it’s too late and everything has gone pear shaped.

GAI-Tronics had one of those stands you hate to be next to. Demonstrating how their on-board telephone system not only connected the crew with the driver but could also be used to make PA announcements was very interesting, but must have got on the wick of the stands next door by the end of the day. Still, they made their point and the system can even be run from the operator’s control room. Handy!

Design Analysis had one of the best logos on display. The company performs finite element analysis on train components, both for new build and refurbishments. The logo was made up of lots of little elements, reflecting the company’s activities, and was very eye-catching. So, too, was the rest of the display as a lot of it focussed on crash structures and their performance.

Signature Aromas make smells. A lot of people in railway carriages make smells too, as do the brakes and some of the electrical gear, but Signature Aromas’ are much nicer and you can choose what ‘flavour’ (is that the right word for a smell?) you want.

Brecknell Willis had a complete pantograph on its stand, and several experts, but not much else, while fellow Wabtec-company Mors Smitt next door had a few banners to show off its signalling capabilities. Both stands were busy.

Comprehensive displays

Hima-Sella’s stand was no bigger than anyone else’s, but they had a lot on it. GSM-R handheld radios by Funkwerk. Selective door opening equipment. A clever in-cab display that was actually two half-sized displays fastened together, so in the event of failure one half could still display vital information and get the driver home. This was a great innovation by partner Deute-Werk and one of the German company’s engineers was on hand to explain it all.

RDS was showing a video train positioning system. Knorr-Bremse (neé Railcare) promoted its vehicle maintenance and repair capabilities. Another recent name change, Ricardo Rail (formerly Lloyd’s Register Rail) was talking to visitors about certification and testing. I M Kelly had seats on display (not for sitting in, even by footweary exhibition visitors). HydraPower Dynamics was discussing hydraulic hoses while Elmatic had a range of heater elements on its table.

CCTV

specialists Comtrol – ‘Power To Communicate’ – was demonstrating an anti-bridge strike system it had developed with TEW Plus. Naturally this can’t prevent bridge strikes, but a dedicated camera which monitors a graticule on the other end of the bridge can detect movement, both that expected from a train passing but also from something striking the bridge. If the movement is permanent, all the alarms go off. It’s solar powered too!

Rail Order, part of ADComms, works with its customers to reduce cost through initiatives such as consignment stocking, kitting of service components and just-in-time supply.

Lighting specialist McGeogh’s stand was hard to get close to – it was so bright! LED tubes were the focus here – direct replacements for both 24V and 110V fluorescent tubes.

Onyxrail had a central stand. The turnkey enhancements and maintenance provider delivers both complete project solutions or individual components to the rail traction and rolling stock industry. It can also offer higher- technology manufacturers a route to market in the UK and elsewhere.

DSC_3213 [online]

Sister companies Brentto Industry, a supplier of high-quality castings, forgings and machined components to the rolling stock maintenance industry, and labour supplier Skills4Rail were alongside the Onyxrail stand.

There was a lot more to see than can be mentioned here. Infodev passenger counting systems, BTROS cable looms, Televic passenger information systems, DC Airco heating and ventilation, Road & Rail Protec video systems for route monitoring, driver-only operation and such details as pantograph monitoring, all of these had interesting displays and experts available to talk with visitors.

All this and seminars too

There was a lot to see in just one day. And that is without the seminar programme going on in the next room. Ten talks were crammed into six hours, covering everything from vehicle design to operations. Speakers from technology companies Interfleet, Knorr-Bremse, Wabtec and Interfleet were interspersed with those from Porterbrook, Eversholt, East Midlands Trains and Vivarail.

Just outside the door of the building, telecommunications specialist Westermo had brought its mobile showroom and training centre, which was parked in the sun, attracting visitors as they arrived and as they left.

All in all, it was a very successful day. The programme was packed, the hall was full, and visitors had something to see and someone to talk with from the moment they arrived (or even before, if the Westermo team got hold of them). Organiser Kevin Lane said simply: “I’m really chuffed.” When pushed to say a bit more, he added: “There are lots of big names here, going around and seeing our exhibitors, so it’s been a great success. Chuffed covers it.”

The next RVE event is already planned – 6 October 2016 at the Riverside Centre in Derby. So if you’re involved in Rail Vehicles and Enhancement, put the date in your diary. And if you didn’t exhibit this year, but should have done, Kevin has about six spaces spare…

Article was first published in Rail Engineer November Issue 133

In case you missed it: Let there be light

Clive Kessell’s article in issue 122 (December 2014) introduced us to the techniques of fibre blowing. So when Emtelle, a leading manufacturer of blown fibre products, staged an open day for the rail industry at its Hawick factory and head office site, Rail Engineer was naturally keen to learn more about production and installation processes and the benefits that this developing technology can provide.

Emtelle itself has grown over the past three decades from humble beginnings as a minor manufacturer to its status today as a global provider of fibre networking infrastructure. Under the brand name FibreFlow, it produces an impressive range of ducting systems and specialised fibre optic cables. As well as manufacturing sites in Hawick and nearby Jedburgh, the company also operates factories in Denmark and India, with a total workforce of over 800.

Micro and Mini

Emtelle produces a broad range of fibre optic cables, some of which are specifically designed to be blown into its duct systems using compressed air.

Microcable fibre units are intended for use in low friction 5mm micro-tube assemblies (micro-ducts). The bare buffered fibres, either multi-mode or single-mode, are firstly protected within an extruded resin coating. This in turn is surrounded by a low-friction polymeric sheath. With fibre counts ranging from 2 to 12, Microcable ranges in diameter between 1.1mm and 1.6mm. It has a maximum blowing distance of 1200 metres.

The Minicables range offers similar advantages to the Microcable series, but they are used when a higher fibre count is required. They range from 12 to 288 fibre cores, with corresponding diameters of 5.8mm to 10.5mm. The fibres are contained within gel-filled loose tubes, typically with 12 fibres per tube. A central strength member is provided and the cable is protected by an extruded low friction outer jacket.

The Emtelle ducting systems and fittings, as used by Network Rail in Scotland, were described in Clive’s article. They are manufactured from scratch at the Hawick factory, starting with the extrusion of the inner polyethylene tubes. Six extrusion lines work continuously to meet ongoing customer requirements. A low-friction inner lining is extruded concurrently with the tube outer wall. Up to 24 individual micro ducts can then be bundled together to form the finished product, incorporating fillers, metallic moisture barriers and a variety of extruded jackets.

The versions used by Network Rail so far are of two types – direct burial and direct install. In the direct burial type. a PVC filler surrounds the tube bundle. This is then surrounded by a 125μm aluminium water-barrier that has an adhesive coating on its outer surface. An extruded sheath of flexible black polyethylene bonds with this adhesive and a tough outer jacket of HDPE is then added.

The direct install micro duct system, intended for use within existing troughing, is similar in construction but does not have the tough outer HDPE layer. As polyethylene has a high coefficient of expansion, two longitudinal strength members of glass reinforced plastic are embedded within the jacket. These stabilise the expansion and contraction properties of the micro duct over a large temperature range.

How is it blown?

So what about the fibre blowing technique? This was demonstrated by Emtelle engineers during the open day and it appeared to be very straightforward. Once the micro duct system is in place, it’s a simple procedure to connect up a fibre blowing head. Push-fit connectors can be used to extend the Microduct or Miniduct to a convenient position for the fibre cable reel, portable air compressor and fibre blowing head to be set up. Expendable O-rings and gland seals are used to make everything air tight and the cable can then be fed into the duct.

A system of motor-driven rollers built into the blowing head feeds the cable into the duct at a constant rate, usually at about 50 metres per minute. As the cable enters the duct and friction increases, the feed rate starts to fall. With perhaps 300-400 metres of cable within the duct, the air supply to the blowing head is turned on and the feed rate immediately rises again. The flow of air passing over the entire length of cable produces a fluid drag that gently carries the cable along the duct.

In this way it’s possible to blow up to 2000 metres of cable, requiring an air pressure of 10 to 15 Bar, depending on the duct size, and a typical air flow of 100 litres per minute. This maximum stage length matches up nicely with the standard duct reel sizes of 1000-metres or 2000-metres. Longer distances can be blown, of course, by fleeting the emerging cable and then onward blowing it. The fibre blowing head can also be used to blow a cable out of a duct if need be.

Fibre blowing equipment on rail trolley [online]

Applications and installations

Emtelle’s engagement with Network Rail began four years ago, when the concept and benefits of air blown fibre systems were discussed. Various iterations of designs were proposed, culminating with the installation of lineside fibre as part of the Edinburgh-Glasgow Improvement Programme (EGIP) phase 1 in 2014. This 11km trial installation between Sighthill East Junction and Greenhill Junction signal box uses a Microduct system containing three 5mm tubes accommodating a 4-core fibre optic Microcable. In this application, the fibre cables are used solely for VoIP (Voice over Internet Protocol) telecoms, with the fibres being spliced into BOP (Box on Post) lineside enclosures. The sub-duct runs within the same lineside troughing as the existing FTN cable, which has not been disturbed.

Following the success of the EGIP trial, a similar, but larger, duct system has now been installed on the Borders Railway project between Edinburgh and Tweedbank. Here the ducting has been directly buried by using a combination of mole ploughing and open trench digging. The duct has three 12mm sub- ducts, one of which accommodates a 24-fibre Minicable that is used for signalling purposes. There are also three 5mm Microducts, each containing four-fibre Microcables for VoIP telephony.

A similar technique will also be used on the EGIP phase 2 project between Greenhill and Winchburgh. On this section there is currently no FTN network, so an Emtelle duct system will accommodate node to node links in the form of Minicables. Lineside services will make use of four-core Microcables.

Chatting with Roy Brader of Linbrooke Services, he was full of praise for the Emtelle fibre blowing concept and the use of fibre optics generally on the national rail network. On electrified routes, any systems relying on copper cables need to be immunised against inductive interference. Roy estimates that, on the EGIP scheme alone, the use of fibre optics has saved approximately £400,000 in immunisation costs.

Blown-fibre systems seem set to create substantial savings in other ways too. This quick and easy method of installing secure and robust lineside fibre cables makes the use of IP (Internet Protocol) technology a cost-effective proposition. On the Borders Rail Project, the Edinburgh SSI (solid state Interlocking) signaling is interfaced through MPLS (Multi-Protocol Label Switching) routers in conjunction with IP technology, making use solely of the lineside fibre optic backbone.

In view of the cost savings and versatility offered by this technology it seems clear that it will now be deployed elsewhere on the national rail network. The Borders Railway Project is very much seen to be leading the way on the concept of a fibre only railway. Ease of installation, reliability in service and the simplicity of adding or removing cables at will make it a no-brainer.

So will the entire UK rail network one day rely solely on fibre optic cabling for data and voice communications? Almost certainly, the answer is yes.

Article was first published in Rail Engineer May 2015 Issue 127

100 years – A signalling centenary

Many of today’s big railway signalling companies can trace their origins back for decades, some almost to the time when railways first became commercial operations. Almost none still carry their original name because acquisitions, mergers and expansion into other disciplines have altered the structure of the companies.

The technology of signalling has advanced beyond even the wildest dreams of the early pioneers and this situation continues today with the fantastic opportunities presented by the computer age.

One company that has recently celebrated a hundred years in the signalling business is Bombardier, which has duly produced a book to record the history and achievements of its ancestry over this period.

Early milestones

The first public railway, between Stockton and Darlington in NE England, was in 1825 and it was quickly realised that a means of fixed signalling was needed with the rapid growth of rail transport. Traditional semaphore signals were well established by 1840 and 1843 saw the first telegraph in operation.

In Sweden, signalling was implemented by ‘local workshops’. The company Ericsson began business in 1876 and entered the signalling business by producing its first mechanical interlocking in 1888. Then, in 1915, SJ (the Swedish Railway company) asked Ericsson to form a railway technical department, which became Signalbolaget (The Signal Company).

This is the date from which Bombardier measures its centenary. The initial business was focussed on export orders, with LM Ericsson supplying an electrical interlocking for Russia. Going forward from that beginning in 1915, the companies that today make up the present Bombardier Rail Control Solutions were busily engaged in developing some notable engineering advances.

The Bombardier heritage

Bombardier is a Canadian company that started life in 1937 making snowmobiles. Perhaps better known for its involvement in the aircraft business, it made its first acquisition outside Canada in 1971 and so entered the rail sector.

Having won a contract in 1974 for supplying the mass transit system for the Montreal subway, and following various mergers and acquisitions, Bombardier has become a global player in railways, both in signalling and rolling stock provision. The ancestral history of the signalling element is both interesting and complex.

  • 1915-1988 – Ericsson was the dominant signalling supplier in Sweden
  • 1929 – Ericsson established a signalling business in Spain
  • 1935 – Dansk Signal Industri (Denmark) acquired by Ericsson
  • 1957 – ML Engineering established in the UK
  • 1970 – Ericsson Signalling in Italy is founded
  • 1989 – Ericsson Signal business transferred to EBSignal, subsequently becoming ABB Signal
  • 1989 – ML Engineering acquired by EB Signal
  • 1990 – EB Signal starts business in Portugal
  • 1991 – ABB Signal India is established
  • 1992 – ABB Signal established in both Finland andPoland
  • 1996 – IVV in Germany, a company established in 1980by academics to plan mass transit and main line railway projects, is acquired by ABB
  • 1996 – AEG Westinghouse (USA) integrated into ABB
  • 1996 – ABB Transportation and AEG Schienenfahrzeuge(part of Daimler Benz) merge to become Adtranz
  • 1999 – Daimler Benz becomes sole owner of Adtranz
  • 2001 – Bombardier acquires Adtranz and formsBombardier Rail Control Solutions
  • 2010 – JV with Elteza in Russia formed
  • 2014 – RSS Australia acquired
  • 2015 – Bombardier NUG Signalling Solutions Co formedas a JV in China
  • 2015 – Bombardier Rail Control Solutions celebrate itscentenary, employing 3,600 people world wide.
4.0.1
Stockholm-Roslagen Railway (SRJ) locomotive no.5 ‘Wallentuna’ with flat car loaded with overhead wire on Stockholm-Djursholm, the first line to be electrified in Sweden, 1895.

 

Driving the technology

Signalling is almost an obsolete term nowadays, the more appropriate title being Control and Communications. Companies in this discipline today cannot progress without having skills that span the full range of technologies required to control a modern railway. Bombardier and its ancestry can chalk up some notable firsts in recent years:

  • Centralised Train Control. Following a centralised relay-based train management system introduced in Sweden in the late 1960s, the first fully-electronic CTC system using computers was commissioned in 1971 at Stockholm Central. This covered 377km of route and 60 stations. From this, emerged the EBI Screen product that is commonplace today.
  • Electronic Interlockings. The world’s first computer- based interlocking was brought into service at Gothenburg in 1978. This stemmed from joint thinking by both SJ and Ericsson, requiring the development of a new logic language named STERNOL, named after Bengt Sterner and Dag Nordenfors, both from SJ but working closely with Ericsson. Recognising that safety was paramount, they adopted techniques used bythe American NASA organisation to gain acceptance of computers in the use of railway signalling. In 2009, Bengt received the European Railway Award in recognition of this pioneering work. The interlocking has been developed since that beginning and is now marketed as EBI Lock 950, it being used by many railways across the world.
  • Automatic Train Protection (ATP). The need for improved driving aids and particularly drivers failing to observe red signals was an increasing worry on most railways in the 1970s. Reacting to this, Ericsson in conjunction with SJ developed a balise-based system now known as EBI Cab, which has been deployed in both main line and metro applications.
  • ERTMS. No description of new signalling technology can be complete these days without some reference to the European Rail Traffic Management System. Bombardier along with the other major signalling companies has been collaboratively involved in the development, more accurately with the ETCS (European Train Control System) element. In 2001, Adtranz supplied the first ERTMS Level 2 system for commercial operation on the Olten-Lucerne line in Switzerland. Perhaps an even more notable achievement has been the introduction of ERTMS Level 3 on rural lines in Sweden. Known as Regional ERTMS, these lines may yet pave the way for deployment of Level 3 onto busier routes. Bombardier has branded its ERTMS product INTERFLO and has equipped 27,000km of route and 3,000 vehicles around the world.
  • Automatic People Movers. With its origins in the USA, and as a result of the Westinghouse/AEG acquisition, the Skybus automated rubber-wheeled electric vehicle has become commonplace for transit systems at major airports since 1966.
  • Automated Metro Systems. Having to deal with significant population growth in recent years, cities have invested in high-capacity metro systems and Bombardier has been at the forefront in developing CBTC (Communications Based Train Control) technology. Leading the way with the BART (Bay Area Rapid Transit) system in San Francisco back in 1972, this was followed by a radio-based moving block system at San Francisco airport in 2003. From these emerged the CITYFLO product now in service on Metro de Madrid and, latterly, in the Chinese cities of Shenzhen and Tianjin.

The UK dimension

ML Engineering, established in 1959 in Plymouth, won the contract for Stoke Powerbox as part of the original West Coast main line electrification. Fortunes varied thereafter, with the company being acquired by EB in 1989. The development of the TI 21 track circuit has been a huge success and thousands are deployed across the UK rail network. Now re-badged EBI Track 200, the design has been upgraded over the years, with the new generation EBI Track 400 deployed for Thameslink, and continues to be the first choice when jointless track circuits are needed.

Page 41_CTC Gothenburg_1978 [online]
World’s first computer-based interlocking, EBI Lock 750, for Centralised Traffic Control, Gothenburg Sweden, 1978.

CITYFLO mass transit systems have been supplied for the Glasgow, Manchester and Nottingham tram networks plus people movers at Gatwick and Heathrow T5 airports. A new level crossing design for rural locations – the EBI Gate 200 – is aimed at improving safety for pedestrians at these vulnerable sites. A recent success has been the award to supply EBI Cab 2000 equipment for the Crossrail trains, which will include EBI Drive equipment for driver advisory operational information. A further success has been the installation of depot signalling solutions.

Bombardier has experienced some disappointment with the intended deployment of the EBI Lock interlocking not being pursued in the UK so far, but remains positive that opportunities may arise in the future. but this has been partly due to the inflexibility of British signalling and operating rules and the expensive adaptation of the product needed to meet these.

The London Underground sub surface lines re-signalling contract which was mutually released by Bombardier and London Underground, caused a number of lessons to be learned despite the success of the CITYFLO solution in many other cities . All companies suffer setbacks from time to time but understanding the causes is all part of the advancement regime.

Both in the UK and globally, Bombardier can be very proud of its signalling ancestry despite its complex structure. Managers and engineers down the years have had the vision to see a progressive way forward that combined the winning of contracts with the development of new products and systems. It has established itself as a global supplier and with that comes the readiness to adapt to local conditions and requirements.

Long may it continue to be successful.

In case you missed it: Signalling supply in 2015 – Small is beautiful

In the days of British Rail, there was always dependence on the private sector to design, supply and install systems and equipment needed for the introduction of new technology as part of various modernisation initiatives.

This was as true for the signalling discipline as for any of the other engineering functions within the rail industry. Names like Westinghouse, SGE and General Signal were part of the signalling partnership, with their staff and resources working hand in hand with BR in-house designers to deliver the new signalling systems. Many of these firms engaged with smaller contractors for the supply of subcomponents and piece parts, thus creating a hierarchy in the supply chain.

The coming of privatisation changed this natural order and many new SMEs (Small and Medium Enterprises) have entered the signalling fraternity. Why has this happened?

Firstly, the in-house Network Rail new-works signalling resource has been drastically reduced from that of BR and is now predominantly engaged in specifying and accepting signalling systems.

Secondly, the big signalling organisations have become global companies selling products that satisfy the international market with decreasing interest in supplying bespoke equipment for a limited local requirement.

Thirdly, many of the signal engineers made redundant by the downsizing of engineering and management numbers have either been recruited into or indeed created small companies that fill the niche elements in the signalling supply business. These SMEs have mushroomed in recent years. TICS is one of them, which Rail Engineer visited recently to learn how this part of the supply chain operates.

TICS history

The TICS (Testing Installation Correlation Services) brand was created in 1998 by Les May, a long time BR signal engineer and tester who found himself in an ever-changing market of consolidation with his employer seemingly changing names every 12 months.

Starting as a ‘one man band’, he foresaw that the industry was going to urgently need skilled testing staff as signalling schemes were authorised and implemented through new and different procurement channels. Recruiting some erstwhile colleagues in a similar situation, a plea for help with the works testing of the new signalling centre at Guildford was his initial assignment.

This quickly led to other things and a small team of staff soon developed. A relationship was formed with Lionverge (a similar sized company specialising in installation) and Tarmac Construction (Centrac) which was winning significant contracts for switch and crossing renewal. This enabled the testing expertise and size of TICS to expand.

The TPWS (Train Protection & Warning System) implementation programme of the early 2000s was running behind schedule because of a shortage of works testing resources, so Jarvis engaged TICS for testing work in the LNE area. The demands of this contract were considerable and thus further recruitment and growth was the natural result.

It became clear that it was not just works testing where skilled staff were needed, signalling design being another area of shortage. Thus TICS established a signalling design office, headed up by Steve Armitage as director of signalling design, to undertake discrete packages and thus complement the existing testing activity

Now, 17 years on, TICS (Global) Ltd has grown to some 70 permanent staff. 43 are engaged in works testing and 16 in design. In addition, there is a small group of four installation supervisors and team leaders with the remaining staff providing support in sales, commercial, finance, HR, IT, project management and administration.

The head office is in Robin Hood Airport Business Park near Doncaster, with a joint design and testing office in York and a further outpost in Peterborough. An installation depot has recently opened at Escrick (between Selby and York) where offsite construction and testing of trackside location cases and relocatable equipment rooms (REBs) can be undertaken in a safer environment. The company currently has a turnover of around £8 million, which is achieved with minimum flow through.

Work and contract relationships

To be a successful SME in the current rail structure, a company needs to put in place mutually-beneficial relationships. Accredited Link-up approval was in place for TICS in 2003. TICS (Global) holds the same accreditation today, this being essential to maintain the company’s competence and systems of operation.

Becoming established with the bigger players in signalling is necessary and, with the framework contract for new signalling projects being awarded to the big three companies – Siemens, SSL and Atkins, knowing what their strengths and weaknesses are is part of the process. Both design and testing work has peaks and troughs so it is convenient for large companies to use trusted providers as a means of managing the workflow. TICS has such relationships in place and these work very well.

The big civils contractors take on major projects which include signalling alterations and additions as part of the package. There is generally no in-house expertise for this element and thus TICS and others are engaged to carry out the necessary signalling work. Companies such as BAM, Buckingham, Murphy, AMCO, Morgan Sindall VolkerFitzpatrick and Spencer Rail have all employed TICS to undertake signalling design, install and test work on their behalf.

 

9 REB Installation a [online]

Work partnerships with other businesses established in the post-privatisation era are a natural consequence and TICS has a number of these in place in which different skill sets complement each other. AmeySersa, Colas (the two current S&C framework providers), Babcock Rail, Linbrooke and Kier are companies where the works testing resource needed to verify the installation work is not always available in house.

Co-ordinating the works testing activities and resource pool can be a challenge and Steve Brookes, director of testing, works closely with Symon Hall, the programme engineering manager (T&C) at Network Rail, who facilitates a working group that requires all the participating companies to meet bi-monthly and look at the ongoing testing demand during the CP5 and CP6 periods. This is very productive and allows the bigger picture to be understood by all, so enabling companies to plan and co-ordinate collaboratively in order to optimise output of an industry critical resource.

Projects to date

TICS has built up its expertise and reputation by successfully delivering its contractual commitments with signalling project delivery being headed up by Pete Coleman, the company’s director of operations. Its first forays into testing included the remote relay room at Brightside for the Sheffield re-signalling project and the signalling associated with the new carriage sidings at Bedford Cauldwell.

Many more projects have been undertaken since those early days, some with total design, install and test responsibility. These latter include the Doncaster North Chord, Ilford Depot expansion and associated signalling and the Killingholme turnback facility.

‘Bread and butter’ work remains signalling works design and testing projects and these recently include Selby swing bridge, Tyne Dock, Winsford, North Yorkshire, Cambridge CD/RA, Bromsgrove, Low Moor, Brierfield and Huncoat.

A significant contract won directly from Network Rail is to test and commission the upgrade of 10 AOCL+B (automatic open crossings, locally monitored, with barriers) level crossings.

The 10-year national programme for switch and crossing renewals always involves signalling changes and, as part of this, TICS has a relationship with both Colas and Amey-Sersa for the associated signalling design and works testing. Currently, TICS has testing resources deployed on the Balcombe resignalling project in the Brighton area as part of Three Bridges ROC introduction and at Hereford where a major signalling scheme is underway.

In addition, and outside the Network Rail arena, TICS is working with Associated British Ports (ABP) and Graham Construction at Killingholme – carrying out signalling design, install, test and commissioning activities on the remodelling of the sidings as the port expands its operations.

Nor is TICS (Global) work confined to the UK. A contract in NW Australia in connection with the double tracking of a freight railway near to Port Hedland led to 17 staff being deployed there for testing responsibilities. Some apparently enjoyed it so much they decided to stay, but this is all part of the competitive pressures for recruiting experienced signal engineers worldwide. Other testing work overseas has included the Oporto (Portugal) and Athens Metros.

Future prospects

Like many others, TICS has grown from a small to medium size company and this brings new and more demanding responsibilities such as ensuring all staff have the correct technical credentials. For design, installation and testing engineers, the qualification needed is an IRSE licence. All TICS engineers hold suitable categories, and this not only has to be worked for in the first place but kept up to date through five and ten year reviews.

As companies grow, they should accept the need to recruit and train new staff, especially school leavers. TICS is proud that it has taken on eight apprentices who are busy learning the intricacies of the signalling profession as well as studying for a Level 3 Diploma in electrical/ electronic engineering and NVQ Level 2 in performing engineering operations. Doing ‘real’ work as part of this training all adds to both the satisfaction and usefulness of the trainees.

As with all organisations in the signalling business, the introduction of new technology is outstripping the supply of engineers and technicians to both design and maintain the ensuing systems. TICS is well aware that it has to learn the intricacies of ETCS, CBTC, new level crossing techniques, radio transmission and other emerging technologies. This will not be easy and it will mean investment in training, test equipment and worldwide familiarisation visits if the appropriate skill sets are to be obtained for the company to adapt.

So, is small beautiful? Certainly, a niche market has evolved for small signalling companies which can capitalise on the expertise of the ‘grey haired’ brigade who, for whatever reasons, left the mainstream rail industry in the post- privatisation era but who wish to continue using their hard gained knowledge for the benefit of the profession.

Most companies of this type have succeeded, perhaps beyond their wildest dreams, but the workforce is ageing and many employees will have to face retirement before too long. The more enlightened companies will recognise this and plan for recruiting new staff to cover the technician, engineer and management roles. TICS can already boast having 25% of staff who did not previously work in the rail industry. Career progression is recognised as important, resulting in a very low staff turnover. The company ticks all the relevant boxes and must be wished well with its endeavours.

First published in Rail Engineer March 2015 – Issue 125

Preparing for the big freeze

There are some countries in the world, in the far North and East, where winter lasts for eight months of the year. In Scandinavia, Eastern Europe and elsewhere, temperatures can remain well below zero continuously for many weeks.

Whilst the UK experiences the fringes of the prevalent winter trends in Europe, it is nonetheless a challenge to keep rail infrastructure from freezing. Snow flurries can start in November and occur as late as April, with overnight frosts extending even longer.

So, with the advent of the 24/7 railway, steps need to be taken by infrastructure managers to make sure that switches and points don’t freeze up.

That’s not a great problem. Points heaters, which are long thin electrical elements designed for installation on switch blades to keep them warm at night, have been around for some time. However, switching them on for long periods consumes vast amounts of energy using valuable resources, adding to CO2 emissions. As energy costs rise, it’s a great shame that this expensive heat is radiated out into the cold air.

What is needed is some good yet simple insulation which will help ensure that heat is retained in the points where it’s needed, leading to reduced energy bills and improving the effectiveness of frost and ice prevention.

Keeping heat in and costs down

Step forward Tracktherm®, a heat retainer developed by the A Proctor Group specifically to be installed directly over existing points heating systems designed and tested by Network Rail and proven to work.

With the addition of Tracktherm, which is easily clipped into place over the heater to reduce heat loss, energy from the heater is more effectively directed into the rail. This reduces the warmup time of the heater by more than 50% , reducing the energy used by 25 – 30%. Raising rail temperature from -5oC to +3oC can take less than one hour rather than two hours using the same heater but without the Tracktherm heat retainer.

These improvements could mean that lower-rated energy systems could be used to obtain significant benefits on today’s technology. In the case of the railways in countries where winter temperatures are much lower, improvements could perhaps be achieved which will result in significantly less energy being required to operate the whole system and, as systems can use more than 200W/m, this would be worth exploring.

Images courtesy of shutterstock.com

T2 at North Pole

When Rail Engineer was invited to visit North Pole in early December, it seemed like a good opportunity to sort out Christmas presents. When the itinerary arrived, the route was found to be via St Pancras and Paddington. However, it was not then to catch a plane at Heathrow for the snow-covered North. Instead the next leg of the journey would be by bus.

For the trip wasn’t to Santa’s North Pole at all, but to Hitachi’s new depot at the edge of Wormwood Scrubs.

North Pole depot opened in 1994 as the maintenance facility for Eurostar trains, then operating out of Waterloo. A six-road, 400 metre long light maintenance shed and a four- road heavy maintenance workshop were built, along with separate buildings for a wheel lathe and a carriage wash.

When Eurostar moved to St Pancras in November 2007, maintenance moved to Temple Mills near Stratford and the North Pole facility became surplus to requirements.

Reworked for IEP

Until, that is, the Intercity Express Programme (IEP) was announced. Two related classes of trains were to be purchased for use on the Great Western and East Coast main lines. These were ordered from Hitachi Rail Europe and would be built in a new factory at Newton Aycliffe in County Durham, although the first 12 pre-series trains would come from Japan for main line testing.

The new Class 800 units will be bimode trains, capable of running off an overhead 25kV electrical supply but also fitted with underfloor MTU diesel engines so they can operate away from the electrified network if necessary. Both five and nine-car units will be manufactured.

The related Class 801 trains, also in five and nine-car variants, will operate solely on electrified lines. However, they will have one of the MTU diesels fitted so they can be driven out of a neutral or failed section if necessary and can manoeuvre in depots and sidings. Great Western is not taking any five-car 801 units, although Virgin East Coast will have twelve.

Three depots will look after the Great Western fleet: at Swansea, Stoke Gifford and at North Pole.

Hitachi Rail Europe, and leasing company Agility Trains, submitted planning applications to reuse part of the North Pole site in 2011. Following approval, work started to completely remodel the six-road, 400 metre long main shed and turn it into a modern facility that could undertake both light and heavy maintenance on the new train fleet.

Due to the length of the building, even the nine-car Class 800/801 sets will be under 250 metres in length. The decision was taken to have the wheel lathe inside the main building and to only have carriage washes outside. The old 200-metre heavy maintenance shed, which was anyway on another part of the site, was not included in the plans.

10242015IMG_6434 [online]

Looks like new!

By the time of the December visit, the facility was virtually finished. There was even a pre- series train sitting in the building, a five-car bimode, manufactured in Japan and the first to be fully fitted with seats and an interior. Code named T2 (test train 2 – to become 800002), it is scheduled to be loco-hauled to Stoke Gifford to continue the test programme next year. The pre-series trains have already covered 30,000 miles on the Signal Protected Zone (SPZ) on the East Coast main line.

Sister train T1 (800001), which is devoid of an interior but is fitted with a variety of monitoring equipment, has been conducting tests on the SPZ for the last few months. The third test train, T58, is so numbered as it is actually the first of the East Coast tranche of the order and will also be the first nine-car unit to run (800101).

Hitachi Rail Europe managing director Karen Boswell welcomed Rail Engineer to the North Pole facility, saying she was pleased we would both get the opportunity to look at the new depot and to get “up close and personal” with train T2.

Depot manager George Staines then showed off the new facility. It looks brand new, rather than a refurbished 1994 structure. Main contractor VolkerFitzpatrick has done a good job of completely remodelling the interior. The six roads now have inspection pits, which they never had before, and the floor has been both strengthened to take the loading of the lifting jacks and excavated for the bogie drop and the wheel lathe.

Numbered with road 1 nearest to the office accommodation (and to the Great Western main line which runs alongside the building), the first two roads will be used for general maintenance. Road 3 is fitted with a complete set of jacks to lift an entire train, supplied by Mechan. In fact there are, on the face of it, too many jacks. This is so that, if two five-car units arrive coupled together, the entire ten-car consist can be lifted as one unit.

Road 4 includes a bogie drop, also supplied by Sheffield-based specialist Mechan, while Road 5 has an overhead crane to remove roof-mounted equipment such as pantographs and heating and ventilation units (HVAC).

Road 6 is the home of the new Hegenscheidt wheel lathe. George Staines explained that the shed is so long that there can almost be a production line arrangement as a whole train passes over the lathe. “A luxury,” he said.

Overhead lines power three roads, with worker safety assured through the installation of a Zonegreen depot protection system, and there is a small shunter for moving trains when needed.

Outside, a new access from the Great Western main line has been created. Trains enter from the East, in the direction of Paddington, and pass by  a carriage wash supplied by Wilcomatic. As well as being able to enter the workshop, storage sidings are located to the south of the facility, and here are workstations where the diesel engines can be refuelled, the toilets emptied and water and water tanks refilled – all these units are from Derby-based Garrandale.

Both the sidings, and the twin turnback roads at the other end of the workshop, are controlled by a Bombardier LOPS (locally operated points system), installed by VolkerRail as part of the trackwork alterations.

All aboard

Having viewed the new depot, it was time to walk through the train. One of the MTU diesels was running to provide on-board air conditioning and lighting.

Starting at the front (first class end), the central driving position gives a great view of the line (or in this case, the workshop) ahead. The controls for ERTMS and other signalling systems surround the driver, and the GSM-R radio and other equipment are within easy reach.

Behind the cab, the galley stretches down both sides of the corridor for a surprising distance. It takes up the equivalent of 20 seat spaces, but is correspondingly well equipped.

In fact, there are four levels of catering installation on IEP trains. Level 1 is the full galley supporting a first-class at-seat service. Level 2 is still an at-seat service but without the full galley. Level 3 is a café-bar in the centre of the train (which takes out 16 seats) and level 4 is provision for an at-seat trolley facility.

Jon Colley, programme manager at Virgin Trains East Coast, confirmed that its trains will be fitted with a level 1 galley in first class and a level 3 café in standard class.

First class seating takes up the rest of the first coach. Set out in a 2+1 format, the seats are finished in dark grey. This is a standard for IEP. Both launch customers, Great Western and East Coast, will have the same basic colours and arrangements although touches such as antimacassars will be branded.

Through the door into the second coach and the floor rises in a slope. This is to give room for the underfloor diesel engines. While these MTU-supplied V12 700kW units, which meet European Stage IIIB emissions regulations, are very compact, they still need a slight increase in floor height – hence the slope.

Thereafter, the IEP Class 800/801 train is as you’d expect a modern train to be. Standard class seating is 2+2 with a mix of airline-style and tables. There is accommodation for two bicycles, in a separate storage compartment, and both disabled and conventional toilets. The sliding doors are unusual, but are as used on Hitachi’s Class 395 Javelin for Southeastern. It’s a very modern train, but using tried and proven technology.

 

IMG_1258 [online]

Both first and standard-class seating and tables are mounted on rails in the floor, so can be changed if either the mix of passengers changes or a new franchise-holder wants to alter the arrangements. Even the galleys are removable, though the water supplies and  drainage would have to be disconnected, but it is not the work of a moment as first class and standard class carpet colours and other details are different – it is all possible but would involve a major refit.

Power is provided at each seat, with both conventional 13A three-pin sockets and also a USB charging connection.

Luggage racks are included, as well as sturdy overhead storage. Hitachi’s brief was to provide for one small bag for each passenger and one large bag for every four passengers in standard class and for every two passengers in first.

The next step

Testing is continuing. When the Stoke Gifford depot is complete, T2 will transfer there to continue the programme. The trains are rated for 125mph operation, although 140mph is achievable with minor modifications.

As for the future, pre-series trains T3 and T4 are undergoing final pre-delivery testing at Hitachi’s Kasado works. T5 and T6 are being manufactured at Newton Aycliffe, with T5 being hand-built by the team that will become the specialists who train the next 200 team members joining the facility in the next few months. Construction of T5 is expected to take twelve weeks, as the workforce continues the knowledge transfer from Japanese colleagues and the standard operating procedures are tested and verified. . Thereafter production will be ramped up until it hits one train a week at the peak.

With the trains due into service on the Great Western main line in 2017, there’s still a lot to do. There is some debate as to whether the line will be fully electrified in time, or whether the service will need to start with the bimode trains using their diesel engines, at least for part of the route.

Be that as it may, the Hitachi Rail Europe team is confident that the trains will be ready on time, with all but 12 of them built in the UK by a British workforce. Yes, some major components will come from Japan, but no train builder sources all of its major components from one factory. Train manufacture is a global business, and Hitachi Rail Europe is just the latest manufacturer to spread its wings and open a new factory in a new market.

Making a rail impact

With its continuing drive for increased efficiency and the resulting cost savings, Network Rail has encouraged its contractors, and their sub contractors, and THEIR subcontractors, to invest in the latest equipment which can deliver more for less.

In the latest control period, for example, efficiency has to increase by 20%. That means every shift has to produce 20% more work, or a set project has to be delivered 20% more quickly and 20% more economically.

It’s a tall order and one which, frankly, Network Rail is struggling to achieve. But that doesn’t ease the pressure on contractors. If anything, it makes it more intense.

This need for speed reaches right across the railway. Every infrastructure project is looking for these savings. Traditionally, one of the more time-consuming elements of a project is the groundwork. With access to the railway limited, and with contractors often having to set-up and then break down the site so that trains can run during the day, the need to achieve more in a shift has never been more intense.

Investment is the key

During its 30-year history, Van Elle Group, based at Pinxton, Nottinghamshire, has established a reputation for delivering high-quality piling and ground engineering solutions for its clients.

A key element in the Group’s activities is its involvement in railway projects. This division  has gained significant experience and expertise in both design and construction, enabling it to undertake rail projects of all sizes and complexities for Network Rail and its contractors.

To carry out its piling and foundation work, Van Elle has invested around £15 million in plant and equipment during the last few years.

This substantial investment has resulted in the purchase of various rail- related machines including a number of DX impact piling hammers from British firm BSP International Foundations. Based in Ipswich, BSP is one of the world’s leading manufacturers of piling hammers and related equipment.

BSP has specifically developed the DX hydraulic drop hammer to drive tubular steel piles to support electrification staunchions, gantries and other railway projects requiring foundation piling. It has been designed as an attachment for mounting on road/rail or tracked hydraulic excavators with an operating weight of around 32 tonnes or more.

When mounted to the machine’s boom and dipper arm configuration, the hammer can be quickly erected from a horizontal transport position to vertical. Side tilt adjustment of five degrees left and right allows it to cope with the track’s cant. During piling, the hammer is automatically guided or crowded in the vertical plane.

Facts and figures

Three compact models are available from the Ipswich-based manufacturer. The DX20, DX25 and DX30 models offer dropweights of 1.5 tonnes, 2 tonnes and 2.5 tonnes respectively with maximum impact energies of 20kNm, 25kNm and 30kNm. Blow rate at rated energy for all the models is approximately 60 blows per minute.

As standard, each hammer is fitted with an 800mm diameter drive cap which is well suited to the common application of driving 762mm and 610mm diameter tubular piles used in the construction of electrification stanchions. It also accommodates other common sizes, such as 457mm, 406mm and 305mm steel piles.

Important features of the DX range include a hydraulic double-acting cylinder which produces high impact energy and a fast blow rate with a low hydraulic power requirement. The new models have the ability to drive piles with an ultimate load bearing up to 1800kN and, during operation, there is total control over hammer stroke and blow rate. Weighing from 4.5 tonnes for the DX20 up to 5.8 tonnes for the DX30, the hammers can be transported easily and be operational on site in a matter of minutes.

According to Van Elle Rail, the BSP hammers, mounted to a tracked/ wheeled excavator or the company’s Colmar RRVs, are the best solution for driving steel tube piles accurately, quickly and safely. They can be used to work alongside the company’s vibrating hammers as piles can be lifted, positioned and vibrated down before the BSP impact hammer completes the installation process using a rapid blow- rate. This pile installation system offers principal rail contractors and Network Rail an unrivalled solution to OHLE signal and gantry bases.

Recent rail projects involving the DX hammers include the installation of 610mm and 762mm diameter driven piles for the Great Western’s OHLE work on behalf of Amey, and piling for both Birmingham New Street and Reading stations for Volker Fitzpatrick and a Costain/Hochtief JV respectively.

Van Elle Rail’s investment in new rigs, equipment and staff training ensures that it has the resources to carry out rail projects of all sizes and complexities successfully and safely. The company is also a Network Rail plant operating scheme provider and a principal contractor’s licence holder.

Now that the TransPennine and Midland main line electrification projects are being resumed, and with HS2 to come, Van Elle’s investment in new plant and equipment, particularly the new range of BSP hammers, has been made at just the right time.