Home Blog Page 206

Muck – a very moving experience

It must be a heart-in-the-mouth moment – that instant transition from mundanity to disbelief as you drive your train around a curve to find the line blocked by fallen trees. Where’s Jenny Agutter when you need her? So on goes the emergency brake, off comes the power; then all you can do is hope.TowardsNewcastle

Those were the events that unfolded early on the morning of 7 January as an out-of-service DMU headed west through a cutting on the Newcastle-Carlisle line at Farnley Haugh near Corbridge. It struck the trees and came to a stand.

The driver’s report described water cascading down the cutting slope, turning to slurry at the bottom. When examining engineers attended, minor cracking was observed in the field above but, after 24 hours, these cracks had opened up considerably to expose a fractured main pumping raw sewage onto the hillside at a rate of 400 litres per minute. Coupled with this, similar volumes of water were pouring over the field towards the railway, the surface drainage having been overwhelmed. Things were not helped by the deliberate pushing-over of a dry-stone wall which had previously been acting as a dam and causing the nearby road to flood. With that, a Highways problem suddenly became Network Rail’s.

An initial conclusion was reached that the toppled trees were basically a function of a large washout flowing down the slope. As we all know, the North had suffered from record rainfall over the preceding weeks, with the December average exceeded by 300%.

Deep cut
To better understand the reality – which proved rather more complex – we need some historical context. Engineered by Francis Giles, the affected section of line was built by the Newcastle and Carlisle Railway, opening to goods and mineral trains between Blaydon and Hexham in November 1834 – a distance of 17 miles, most of which was single track.LatestWork

Back then, there was no cutting at Farnley Haugh; instead the railway passed through a tunnel 170 yards in length. To handle an expected increase in traffic, this was enlarged after ten operational years to accommodate two tracks, the work being delivered with only one brief interruption to services when a failure of the original lining blocked the passageway with running sands.

The tunnel suffered from considerable water ingress and some distortion due to ground movement. Repair work was undertaken in 1871 at a cost of £1,000, and the arch was subsequently strengthened throughout with iron ribs and laggings. Concerns over gauge clearance and possible formation scour from the adjacent River Tyne led the Chief Civil Engineer of BR’s North Eastern Region to order the construction of a deviation. This resulted in the cutting being excavated between November 1959 and June 1962.

Photographs taken during those works show an area of rock pitching (riprap) mid-slope, used to stop weathering by emerging springs and coinciding exactly with the location of the landslip. Drawings were also extracted from the archives showing an unusually extensive drainage provision at this location. It was therefore reasonable to deduce that the engineers had been confronted by considerable groundwater issues.

Over the intervening 50-plus years, the cutting has not proven problematic except for a couple of minor washouts around 300 yards east of where the slip occurred. These were resolved by a refurbishment of the drainage in 2010.

Safety first
The operation to remediate January’s landslide was mobilised immediately, the works being undertaken by Construction Marine, Network Rail’s earthworks framework contractor for the London North Eastern and East Midlands route. AECOM was responsible for the design.

A compound was secured at the entrance to a field rented from the local farmer and traffic control measures introduced on the adjacent A695 to account for the number of plant movements. Despite the inconvenience caused, locals continued to support the on-site team with hotdogs and boxes of cookies. Around 30 of them accepted an invitation to visit the site over the first weekend to gain some understanding of what was going on. Relations have remained excellent.

FailedSewerOver the first four days, the project team progressed the urgent task of making the slope safe for workforce and machinery. With the inundation of water continuing, trees could still be heard cracking and falling to the ground. Northumbrian Water attended to turn off the sewer and divert it back 50 metres from the crest; meanwhile a field drain was intercepted and taken eastwards to a cascade at the top of the cutting where it discharged into a different drainage system. This allowed the slope to dry out…or at least that was the hope.

Eye in the sky
Initially, the intended methodology for disposing of the spoil involved moving it to the bottom of the cutting and taking it out by rail. However, large amounts of water were issuing from springs mid-slope – as had been the case during the cutting’s excavation – and liquefying the material. From a safety perspective, this instability rendered unsustainable the idea of bringing trains onto the site.

An unmanned aerial vehicle (or drone if you prefer), operated by Central Alliance, was brought in to perform a full photogrammetric survey of the landslide. This was repeated twice during the remediation. From thousands of geo-referenced digital images, a topographical 3D model was produced to an accuracy of a few millimetres. On the first pass, considerable interpretation was needed to account for the fallen trees – numbering around 100 – and reveal the ground profile. Without getting boots dirty, valuable information was derived on the extent of the slip, its shape and the volume of material involved – crucial in estimating how long the line might be closed.

Ground investigations, fulfilled by Geotechnical Engineering, found that the top part of the slope – to a depth of around 15 metres – consistently comprised glacial till: sands and gravels, with boulders of perhaps a metre across. Below this was a variable layer of clay, impermeable to water. At the surface, self-seeded silver birches covered the slope, together with some scotch pines. The former’s shallow root system acted to stabilise the ground to a depth of around 0.5 metres but, with the failure plane much lower, each one also acted as an approximately 20-tonne point load which tended to open the ground up as the wind acted on it. By saturating the sands and gravel with floodwater and sewage – increasing the weight of the ground above the clay layer by 40-50% – all the elements had come together for a significant slip. The back scar reached the line of the sewer where a trench must have been excavated at some point in the past 60 years. Could this have created a weakness which acted as a tipping point? We’ll never know.

What had become clear from observation, investigation and technical insight was that the landslide was not just a washout as originally thought. Something more significant was happening: a rotational failure in the hillside. This changed the complexion of the recovery operation.

The earth moves
The field above the slip hosts the buried remains of a Roman fort, discovered in the 1950s and comprising three camps. The nearest one to the crest – about 15 metres away – dates from just ten years after the Roman invasion. Archaeologists from Historic England were on-site for the first three weeks, supervising the removal of topsoil and recording any finds. Geophysics surveys were carried out to map the structures and ensure all works took place clear of them. Their presence did constrain the location of entry ramps into the cutting.LatestWork

Tractor-mounted winches, sitting at the crest, were used to pull the fallen trees up the slope where they were fed into chippers. Some of what came out was used to form the surface for a 300-yard walking route from the compound to the site. Thereafter it was possible to get in heavy earth-moving machinery to start the regrading, taking weight off the top of the landslide – which otherwise would have continued to drive it – before removing material at the toe in order to clear the railway.

Throughout, it was regarded as an active landslide with established slip planes, so a constant balance had to be maintained as the slope was battered back from 1:1.6 to 1:2.5. At its peak, more than a dozen large items of plant were involved in the operation, from track dumpers to 40-tonne excavators. Around 35,000 tonnes of spoil was shifted and stockpiled in the field until a final resting place for it was agreed.

As a temporary measure, two deep counterfort drains were provided on the lower of two benches to deal with the water flows from mid-slope. A permanent, future-proof system will replace them as part of the full remediation works – now underway – which will also involve placing rock pitching on the lower slope to control shallow surface movement. Higher up, top soil and seed will see vegetation re-establish itself. There’ll also be inclinometers for monitoring purposes.

Whilst the p-way sustained no actual damage, the Down (Carlisle-bound) line did slew over towards the Up by around 100mm. The correct alignment was restored during tamping. Network Rail’s works delivery unit supplied a rail vac which, over two days, removed fouled ballast from a 70-yard section on each road, as well as a shallow cess drain. Around 600 tonnes of fresh ballast was put back. The vac proved significantly more efficient than the traditional approach, obviating the need to cut the track and lift it out, excavate, replace, weld and stress.

More to come?
Trains started running again through Farnley Haugh on Monday 8 February, barely a month after the line was blocked by trees and slurry. That’s no mean feat given the scale of the landslide and the difficulties it presented. The site will remain active well into the spring to deliver the final design, deal with the spoil and demobilise.Reinstated

Thankfully, fire-fighting is something the railway is very good at. Just as well – there’s been lots of it to do since the storms ravaged Britain. If the climate change experts are to be believed, severe wet weather is set to become more commonplace during our winters. Whilst there is no emergency brake for that, we can at least see it coming. The challenge then is to make the infrastructure more resilient to its impact. That will have both financial and engineering implications, but it’s something Network Rail is committed to tackling into CP6 and beyond.

Resignalling in East Nottinghamshire

Resignalling in East Notts

A number of projects have taken place recently to abolish yet more lever frame signalboxes and mechanical signalling. Few of these remarkable survivors of nineteenth-century technology remain in main line service and it will be left to the heritage sector to ensure future generations know how signalling was achieved in the past.

One of the projects was in East Nottinghamshire, on the line from Nottingham to Grantham. Older readers will recall that this route was originally a Great Northern line (the Great Northern disappeared in 1922 – how old do you think our readers are? – Ed) and terminated at the now demolished Nottingham Victoria station. In 1967 a new connection at Netherfield enabled Grantham line trains to access Nottingham Midland station via the Lincoln route.

In 2013, Nottingham station was closed for a six week period whilst the entire layout of the station was remodelled with the signalling transferring from the 1969 Trent Power Box to the new Derby ROC.

This project extended the signalling boundary out to Lowdham fringe box on the Lincoln line and Bingham fringe box on the Grantham line, thus enabling modernisation of the route and associated level crossings in the city’s eastern suburbs. Eastwards of these locations, traditional mechanical signalling still existed including numerous level crossings. Modernisation was long overdue.

The East Notts scheme

Back in 2012, Network Rail developed a scheme based on the premise that the modular signalling solutions then coming on stream would enable a more cost effective and faster upgrade compared to conventional technology. Tenders were invited at GRIP stage 4 in the autumn of 2013, with a contract awarded in March 2014 to Signalling Solutions Ltd (SSL).

The firm had recently delivered its first modular signalling pilot project on the Ely – Norwich line. This enabled the modular approach to be developed and proven and, as a result, potential problems associated with this new and innovative approach had been identified and resolved.

New signalling was to be extended to Newark Castle on the Lincoln line and Allington Junction (close to Grantham). No permanent way alterations were envisaged other than the removal of some redundant crossovers and a new switch crossing at Newark Castle. No line speed improvements were instigated.

The signalling would be mainly two-aspect with discrete block sections but including some three-aspect signals where required. Allington Junction signalbox, commissioned in 2005 and equipped with an Entrance-Exit panel and relay interlocking, was built to accommodate the construction of a curve that eliminated a flat crossing on the ECML for trains from Grantham going towards Sleaford, Boston and Skegness.

At Newark, the Lincoln line crosses the ECML on the level with train movements being controlled from Doncaster Power Box. As such, the new signalling had to be interfaced with these controls. Derby ROC already had a Netherfield workstation under the Nottingham project with sufficient capacity to accommodate the two new lines.

Modular Signalling

The idea of modular signalling is to construct the necessary elements to a standardised design whilst also aiming to use pre-assembly and test in a factory environment to minimise the amount of installation and testing work needed on site. The East Notts project consists of:

  • An interlocking using the Alstom ‘Smartlock™’ electronic product already in use at many UK locations, the first being Horsham some 10 years ago. This equipment is positioned in the Derby ROC equipment room.
  • A ‘front end’ to link the signaller’s workstation and mouse to the interlocking, in this case using the well-proven Siemens (ex-Invensys) Westcad system. The two companies worked well together even though they are competitors on many occasions.
  • Local Trackside Functional Modules (TFM) installed in ‘Signalling Island’ Relocatable Equipment Buildings, known as SI-REBs, located adjacent to an existing junction or level crossing. These contain all the SSI (Solid State Interlocking) modules, transformers, rectifiers and relays needed for each location.
  • Local cabling out to signal points and level crossings pre-made in measured lengths with plug and socket connectors for ease of installation.
    Train detection equipment using Thales AZLM type K axle counters.
  • A transmission link from Derby to the ‘Islands’ using the Network Rail Telecom-owned FTN network. These links are formed in rings such that any cable cut does not stop traffic being carried. ‘Points of Presence’ were established at all the SI-REB sites, from where the data streams are extracted. Alan Dick Communications (ADComms) at Scunthorpe was contracted to provide the interfaces between the FTN and the local cabling.
  • LED signals supplied by Unipart-Dorman for the red, yellow and green aspects but with a single aperture that can show the three colours.
    In-bearer Clamp Locks by SPX for point operation (none required on the Grantham line).
  • Local power supplies from the local electricity company to supply the Islands and including a battery backed Uninterruptable Power Supply (UPS) giving a four-hour duration should the mains fail plus hard standing for a generator should the outage be prolonged.
  • Level crossing systems of various types, some existing and some new (see later paragraph).

Most of these piece parts can be assembled and connected off site as part of the integrity proving process.

IMG_2837

Delivering the Grantham line

Only the Grantham line has been commissioned so far – over the weekend 27-30 November 2015. The work needed to construct and install the elements of equipment make an interesting account and demonstrate the involvement of many parties in a modern signalling scheme.

Key to any signalling project is the preparation of the control data that is loaded into the electronic interlocking – Smartlock in this instance. This task was carried out by SSL engineers from the York office and then tested at Derby.

The three REBs – at Bingham, Aslockton and Orston Lane – underwent several fit-out stages to accommodate power, lighting and signalling equipment. The REBs were made by Eldapoint of Liverpool, which provided power and lighting wiring and then transported them by lorry to Blackburn Standing of Nottingham for fitting with the power equipment and UPS. That done, they then travelled to MGB Signalling in Plymouth for fitting out with signalling equipment and racking procured jointly by SSL and MGB.

Next move for these REBs was to the SSL depot at Beeston, near Nottingham, where off-site testing could be carried out, known as a ‘hangar test’ facility. Here, by using a test Smartlock, verification testing, functional testing and principles testing can be carried out, connecting to either the signal/level crossing equipment powered up at the Beeston site or to simulations of the external kit.

Once completed, there is a high degree of confidence that the system will need only minimal on-site final testing. The equipment was then transported to the various sites and installed. Prior to this some considerable civils work had to be carried out including signal bases, REB foundations and level crossing alterations, this being contracted to Global Rail of Hatfield.

SSL used its own in-house staff for installation and for functional testing over the commissioning weekend. Bingham and Bottesford West signalboxes were closed with Allington Junction becoming a fringe to Derby ROC. The commissioning went smoothly and the line was handed back to traffic on the Monday morning as planned.

A number of modifications/improvements have been made to the SSL modular signalling system resulting from lessons learned on Ely – Norwich. These include facilitating easier fault finding and maintenance, equipment room reliability and overall system safety.
ENMR_Lidar

Level crossings

The Grantham line has a number of level crossings. Existing Automatic Half Barriers at Scarrington Lane and Normanton are largely unchanged (Normanton had a new signal within its strike-in point and thus needed adjustment to the control circuitry) but with their alarms and status indications now shown on the Netherfield workstation at Derby ROC.

At Bingham and Orston Lane, the manually controlled full barriers have been converted to Obstacle Detection semi-automatic operation (MCB-OD), whilst at Aslockton station, the previous AHB has been converted to an MCB-OD crossing. These use detection equipment to prove that nothing is trapped between the barriers, whence a sequence is initiated to lower them automatically and clear the protecting signals.

The detection process uses a combination of RADAR and LiDAR, the former mounted up to 915mm above rail level to scan the crossing as a general area, the latter (light detection) being two units, one at chest height, the other at near-ground level, to scan the roadway for any object that the RADAR might miss.
SSL was asked by Network Rail to manage the pilot introduction of OD technology on the Ely – Norwich project, but a key challenge was encountered with the low level LiDAR lens becoming obscured by dirt thrown up by trains and road traffic. As a result, all crossings using OD technology are risk assessed to establish if the lowest level detector is actually needed. Some light traffic crossings may be judged not to require it. Both LiDAR units are now equipped with a motorised shutter which automatically opens when the scanning process is taking place. This has solved the problem of dirt accumulation.ENMRRadar

At Bingham, an additional safety feature has been introduced, namely Barrier Protection Management (BPM).

This comprises an inductive loop mounted in the roadway to detect if a vehicle is stopped where the barriers would come down. If activated, it stops the lowering sequence. The road here is much busier than the others and it is possible for traffic to queue across the railway. It is the first application of this feature by SSL but will be used elsewhere in similar circumstances.
Should any of the detection equipment pick up a problem, then the initiation sequence is stopped and the signaller investigates the situation, taking whatever action is needed.

Onwards to the Lincoln line

The Lincoln line will follow a similar pattern this coming autumn but with some added complications. Signalboxes at Lowdham, Fiskerton Junction, Staythorpe crossing, and Newark Castle, together with Gate Boxes at Fiskerton station and Rolleston, will be closed. The level crossings at these locations will be converted to MCB-OD operation except at Newark Castle. The barriers here are currently locally controlled from the adjacent signalbox and will be converted to remote CCTV monitoring under the control of Derby ROC.

AHBs at Gonalston and Thurgarton will stay the same but with alarms and indications sent to Derby. The AHB at Bleasby will be converted to MCB-OD operation.
With all these crossings to be altered and tested, it has been decided to commission the line in three stages, planned for September, October and November 2016, rather than having a changeover in a single weekend.

However, this does necessitate establishing temporary fringe boxes at Fiskerton Junction and Staythorpe for a short duration. The Newark flat crossing with the ECML will need an interface with Doncaster Power Box to be developed.

Lessons learned

Modular signalling can offer a much cheaper solution for secondary lines when compared to conventional signal technology. By using a state-of-the-art computer-based interlocking (CBI) like Smartlock, the system will be future proofed to accommodate ETCS. Cable lengths from the TFMs are calculated to be within limits to ensure effective immunisation for any future electrification.

This scheme has been the second modular signalling project for SSL and has enabled the company to consolidate the experience gained from the Ely to Norwich project. SSL believes it places the company in a strong position to deliver further modular-based schemes, realising re-signalling on secondary lines at a much lower cost than traditionally designed schemes.

East-Notts

 

Thanks to Andy Cokayne (project director) and James Suter (project engineer) for explaining the scheme in detail, and to Judy Viitanen for arranging the visit.

 

It all comes down to planning

Francis Paonessa, Susan Cooklin (route services director) and Toufil Machnouk (senior programme manager) at Stockley.

Over Christmas, Network Rail successfully invested more than £150 million to improve the railway across the country.

The Orange Army built new signalling, new bridges, new track and new facilities – all to give passengers better, more reliable journeys.

The investment will benefit millions of people. Commuters, families, friends; young or old, north or south, urban or rural; the impact the railway has on this country cannot be overstated. Whether you use the railway regularly or rarely (and more people than ever are using it regularly with passengers numbers having doubled to 4.5 million per day since 1997 and are set to double again in the next 25 years) the railway plays a vital role in our lives.

As well as passenger trains, rail freight carrying everything from cars, fuel for our power stations and the latest technology gadgets to your weekly grocery shop contributes £1.6 billion to the UK economy. That figure is predicted to rise to £2 billion by 2023. The demand from passengers and businesses to get more trains on the tracks brings with it immense challenges.

For some, Christmas might be the only time in a year they travel by train, but figures show (and the rest of the industry agrees) it is the quietest time of the year, and therefore the best time to work on it.

Network Rail has no rights to shut the railway and carry out our work when it feels like it, we need to consult and agree with the train and freight operators. However, train operators tell us that passenger numbers drop by up to 50 per cent during bank holidays such as Christmas and, while the reality is that there is no good time to do the essential work that is required, doing big projects and pieces of work over the Christmas and New Year period causes the least disruption and enables operators to offer decent alternative transport arrangements, especially as fewer people are travelling.

But we know from hard experience, of more than a year ago now, that getting it wrong and not ensuring that passengers are properly looked after has disastrous consequences.

The chaos, confusion and anger at Finsbury Park the Christmas before last remains etched on the minds of all of those who were involved.

he awful experience endured by the thousands of passengers who turned up expecting to travel on 27 December 2014 was unacceptable and one the entire rail industry never wants to see repeated.

What could have gone wrong, did go wrong, and the result was one of the worst experiences in my working career. We care deeply about those people who depend on the railway and, although the pictures on television screens, in newspapers and on social media sometimes tell a different story, I know from travelling the length and breadth of the country, meeting hundreds of members of the Orange Army, that our frontline staff feel the same way. They take a huge amount of pride in their jobs. They want to succeed and to return the railway in a better state than they found it.

The reality about major engineering work on the railway at Christmas is that, while 95 per cent of the network is unaffected, the five per cent takes years to plan. We started planning for Christmas 2015 back in 2012, firstly to identify what needed improving, then prioritising which areas needed more work than could be completed over a normal night or weekend shift.

Some people think that we save all our work up to do at bank holidays and wonder why we can’t do it at nights or weekends, but the reality is we’re out maintaining and improving the network every night of the week, not just bank holidays – last year alone LNE route did 16,000 jobs during evenings and weekends. Bank holidays allow us more time to do the biggest, most complicated pieces of work – such as demolishing and rebuilding bridges – while impacting the fewest people.

The Railway Upgrade Plan delivered this Christmas was the biggest yet, with over 8,000 worksites located in some 2,600 possessions on over 500 individual projects.

We had well over 20,000 employees and contractors’ staff working over the ten days.

The lessons of Christmas 2014 have now become part of our DNA and have proven their effectiveness with some £250 million of investment in hundreds of projects successfully completed in the four bank holiday work programmes since then – Easter, the two May bank holidays and August bank holiday.

Plan A was for all 500 Christmas projects to go exactly to plan. But things happen and then it becomes about contingency – plan B.
What if work falls behind? What if a machine fails or a train breaks or a driver phones in sick? What if the weather plays a part and we get blizzards or floods or gales that stop cranes working? How do problems at one site impact another? At what point can we stop the work or scale it back?
Our planning and operational teams across the country spent months analysing every scenario, what the consequences might be, and how we would deal with it. No stone was left unturned. Plans A and B were supported by an entire alphabet of alternatives and, like the railway itself, the decision-making process has been vastly upgraded.

The one thread that ran through every project, every review and every decision was simple; what might be the impact on passengers? In the past year we have changed how we deliver major upgrades and are working even more closely with train operators to make sure that every engineering decision is made with full sight of what that will mean for passengers and, importantly, how we are going to communicate with them. You may have seen our ‘Working For You’ advertising campaign featuring track section manager Barry Robinson from Leeds.

Despite the atrocious weather conditions, virtually all of our work was handed back safely and on time, with all our ‘top 20’ projects – the biggest and potentially most disruptive – handing back early. Over the period there were no major injuries and from the 2,600 possessions taken there were just 14 incidents of possessions overrunning and impacting operators. Most of these were very minor with the total number of delay minutes for the entire duration at under 400. As such, 99.02% of all possessions were handed back without impact to customers and we lost only 1% of our planned work owing to weather or decision to scale back to ensure right-time handback.

Thanks to all the preparation and planning, incorporating the lessons from Christmas 2014, the 2015 Christmas and New Year investment programme was a great success. A huge ‘well done’ and ‘thank you’ goes out to the tens of thousands of railway workers, planners, engineers, signallers, S&T staff, traincrew, crane operators, welders, station staff and numerous others who made this possible and should feel proud of all that has been achieved.

And a lot of this was done in some truly awful weather conditions where, once again, our people responded and put back together a railway that the weather had broken in hundreds of locations across the country.

This opinion piece was written by Francis Paonessa, managing director, infrastructure projects, Network Rail.

Video: Cheshire viaduct repairs

New drainage systems are being installed on two Grade II listed viaducts as part of a £17 million investment on the West Coast Main Line. Dating from the 1840s, the structures’ original drainage had failed, causing track quality issues and numerous brickwork defects which are undergoing repair.

An 11-day blockade is needed to take the track off the viaduct and install pre-cast concrete ballast retention units which will collect water and discharge it into down pipes. An additional benefit of this solution is the relieving on lateral loadings into the parapets, the cause of longitudinal fracturing of the arch barrels.

Although clearly undesirable on such a strategically important route, the 11-day closure minimises the disruption caused by the works overall by driving efficiency improvements. Had they been done piecemeal, six months’ worth of weekend possessions would have been needed; around £500,000 of cost benefits are also generated.

As well as waterproofing the viaducts, two bridge reconstructions, remedial works to an overbridge and a considerable amount of routine maintenance has been progressed during the blockade.

Stairway to Ealing Broadway

The Christmas shutdown gives Network Rail, and London Underground for that matter, a chance to undertake those jobs that would be difficult at other times of the year. Some are major pieces of work, others are routine but take a long time (such as the wholesale replacement of track drainage at Weedon, Northamptonshire).

The justification for these works is usually fairly obvious. Failing infrastructure, operational bottlenecks, capacity improvements, and even new railway construction.

Sometimes, however, the need for a project to take place can be a little obscure. Take, for example, the Crossrail preparatory works carried out by Network Rail at Christmas to install a new emergency escape footbridge at Ealing Broadway station. The project had an interesting ‘raison d’être’ since there is already adequate access to the platforms for the existing trains. However, the new bridge is required because of the enormous capacity of the intended new Crossrail trains. It was decided that the current station infrastructure would unacceptably restrict emergency evacuation of passengers, and that this should be resolved by an additional footbridge at the other end of the platforms.

This sounds simple enough until one considers the surrounding environment at the site. Residential properties are very close to the line, making it difficult to find adequate site access and ensuring that noise and vibration would be significant issues. Ground conditions meant that piled foundations would be necessary, and the only feasible way to place the footbridge structure would be by employing a large crane.

Preparation is key

Taylor Woodrow, part of the Vinci organisation, was employed by the project to carry out the works. The project team held detailed meetings with local residents about the impact of the works, agreeing, for example, to restrict piling activity to daytime hours over the Christmas period. The possibility of obtaining access to the new bridge site via an adjacent NHS facility was identified, and negotiations were entered into with a view to gaining agreement both to temporary access for the crane and construction works and to permanent access to the completed footbridge. Thanks are due to the NHS for their cooperation in this regard.

Christmas 2015 was planned as the date to erect the footbridge span serving Platforms 2 and 3 with a second span to Platform 1 to follow at a later date. Sarens was engaged to carry out the contract lifting operations over the Christmas period.

The piled foundations for the first span were installed beforehand so that, at Christmas, effort could be focussed on the lifting operations. A four-day hire of a 400 tonne mobile crane commenced at 05:00 on Christmas morning and nine main lifts were completed by 11:30 the same day. These lifts involved the placement of support columns, stair units and the bridge span itself. Extremely high winds had been forecast for the day, and the team were relieved that all these main lifts were successfully completed before the winds arrived.

Just down the line at Stockley, the works there were less fortunate. Only 10 miles or so further west, that site was hit earlier by the winds and some of the lifts there had to be postponed. At Ealing Broadway the only crane lifts delayed by the winds were secondary lifts of materials and plant, and these delays had no significant effect upon the programme.

Additional works at the site included some piling to the rail embankment adjacent to the new footbridge. This provided embankment support where it was necessary to trim the bank to construct the access route from the new bridge onto the NHS site and thence to the public road. The large crane was used to assist this work during the remainder of its contracted four-day stay on site.

The plan now is to install the piled foundations and pile caps on Platform 1 ready for the stairs to be installed there and for the installation of the second bridge span over to that platform. The aspiration is to undertake all of these works before Easter, using normal weeknight possessions rather than blocking the line over the Easter holiday.

Extreme collaboration! London Underground and Network Rail working together

Everyone knows that rail travel is one of Britain’s success stories. Trains are bursting at the seams, particularly in the South East during rush hour, and both operators and infrastructure owners are working hard to increase capacity by running more-frequent higher-capacity trains.

This is true both of national rail commuter services and London Underground. The Tube is moving more people than ever. On Friday 4 December last year, a record 4.821 million customers travelled on the Underground network – the busiest day in London Underground’s history. And demand continues to rise. As a result, engineering teams are working harder than ever to renew the asset base and modernise services which are so critical to keep London moving and growing.

Over the holidays, experienced teams from across London Underground were hard at work delivering a significant programme of rail modernisation. Taking advantage of lower traffic and customer levels, a part-closure of the Circle, Hammersmith & City and Metropolitan lines was implemented in order to carry out a record 24,000 hours of upgrade work.

Working together

For some time, the key to delivering a complex project successfully has been collaboration. Rail Engineer has reported on several of these arrangements, at Birmingham New Street station, Hitchin viaduct (the Hitchin Alliance) and the work around Norton Bridge Junction and Stafford (Staffordshire Alliance).

But this year, collaboration was taken one step further as, at Paddington, London Underground teams worked side-by- side with colleagues at Network Rail. This collaboration was a first for LU and more work was completed in a much shorter space of time, ensuring minimum disruption to customers.

LU had planned to renew two platforms at Paddington tube station in 2010. However, it wasn’t able to complete the work within a traditional weekend renewal possession, due to challenges with single line working Ballast Track Renewals (BTRs). Without a service road for the BTR, single line working proved difficult, making a standard weekend closure an impossibility. It wasn’t until Christmas 2015 that the perfect opportunity was presented for the platform renewals to take place by working with Network Rail.

Collaboration was key. Over the year preceding the project, delivery teams from LU and Network Rail held regular monthly meetings to ensure a successful delivery of the platform and ballast track renewal work.

It was proposed that Track Partnership, itself a collaboration between London Underground and Balfour Beatty, would service the BTR of platform 15 using National Supply Chain engineering trains provided by Network Rail. Meanwhile, Network Rail would carry out its planned renewal of nearby platform 14 using LU’s transplant engineering fleet. By sharing resources and running the renewal works alongside one another, LU and Network Rail could hit two birds with one stone.

With another track renewal taking place across London at King’s Cross, it was essential that LU shared assets with Network Rail. A year’s worth of planning ensured that contractual arrangements were in place between the two.

After the planning…

LU’s possession commenced at 02:00 on Christmas Day. LU then worked on the 314 metre long BTR of Platform 15 until 07:00 on 27 December, when the track was handed over to Network Rail. Network Rail then serviced its BTR and switches and crossings (S&Cs) work from platform 15 until 07:00 on 29 December. From 29 December, work continued on both until the start of traffic on New Year’s Eve.

3. NR removing redundant track using LU Engineering Trains [online]

Breaking out the platform foundations proved a major challenge; using additional road-rail vehicles added between two and four hours to the removal time. Though LU was able to obtain core samples of the old platform foundations, engineers were still unsure how the platform would break, which could have risked a delay to handing over platform 15 to Network Rail on time.

While this work was underway, LU also connected the Heathrow Express service bonding location and fourth rail system to the Network Rail overhead line equipment, which will reduce the risk of interference and touch potential developing between the lines.

With Network Rail realigning its track, the Heathrow Express was moved closer to LU – a difficult process requiring an all-line block of Network Rail at Paddington and a possession of LU platforms 15 and 16. The LU delivery team also loaded the check rail sleepers at Cemex’s yard in Birmingham onto the Network Rail wagons, and the team travelled to Birmingham, Bristol and Oxford to ensure that they arrived in the correct train consist on site.

Because the possession limits provided a limited space between Paddington and Praed Street Junction (with street traffic running only 120 metres away), it was crucial that engineering trains didn’t crowd the space. To ensure there was enough space, and to prevent any knock-on effect on traffic hours service, one train was allowed through during the tamping of platform 15.

Organisation

Throughout the project, the car park and welfare facilities were shared, spreading the cost between Network Rail and LU – which saved LU as much
as £60,000. A shared approach to access was the background to a better working relationship. Network Rail staff with a valid PTS certificate were provided access to LU track, and in return, LU staff with a valid LUCAS certificate could access Network Rail track, in both cases following a site briefing. LU staff were identified by wristbands, while Network Rail staff were identified by stickers on their helmets.

To ensure consistent communications throughout the blockade, Network Rail was kept in the loop on LU’s milestone updates, and in return, LU staff working on site took part in Network Rail conference calls.

No lost time accidents were reported despite an estimated 24,000 hours of upgrade work. A visit from the Office of Rail and Road during the blockade confirmed the project’s success (100% mark), general good housekeeping and strong collaborative working practices with Network Rail.

This unique collaboration with Network Rail was a first for LU and a resounding success. The result is a more reliable railway with reduced maintenance requirements. The gap between the train and the platform was also narrowed and made more consistent by realigning the platform copings to match the new track alignments.

Written by Jamie Coulson, who was the delivery engineer with London Underground for the Paddington Christmas blockade.

Video: Conwy Valley recovery

The railway network has suffered the consequences of a very wet winter, with some sections of line closing for several weeks. In North Wales, the Conwy Valley branch has been out of action since the 27th December due to the effects of severe flooding.

Since then, a small orange army, brought together by contractor Alun Griffiths, has been helping Network Rail to bring closer the restoration of train services. Around 1,200 tonnes of material had to be excavated and removed before a partly-failed embankment near Llanwrst could be reinstated. Just to the south, a rail crane was used to lift out a concrete bridge slab, allowing retaining walls to be rebuilt. And 1,000 tonnes of new ballast was brought in to repair one-and-a-half miles of railway where 100 ballast washouts had occurred.

The Conwy Valley line has always been susceptible to flooding, running close to the river for much of its length. A lot has been done to improve it over recent years, but increasing the infrastructure’s resilience to severe weather events will become an ever-greater challenge as they become more frequent.

The immediate focus though is on the recovery works. These are now well advanced and it’s hoped the line will reopen at the end of February.

Crossrail monitoring – Delivering the three Rs

In 2018, Crossrail services are due to commence through central London. As most readers know, the £15 billion project will pass through 37 stations and run 118 km (73 miles) from Maidenhead and Heathrow in the west to Shenfield and Abbey Wood in the east.

The project’s C350 Pudding Mill Lane contract, won by Morgan Sindall, is worth in the region of £100 million and will link the new Crossrail tunnels to the Network Rail infrastructure in the London Borough of Newham. Work comprises the construction of a tunnel portal and a new, elevated Docklands Light Railway station at Pudding Mill Lane, plus associated structures to bring the subterranean railway into the above ground existing rail network. The project will also link new Crossrail tunnels to the existing Network Rail infrastructure.

Critical to the smooth running of the project is an awareness of how the cut and cover tunnel construction work is affecting adjacent rail lines, in this case a 480 metre stretch of Network Rail track and two sections of DLR track totalling another 380 metres. Twenty-four hour monitoring of the track’s condition is therefore imperative if any movement is to be efficiently detected and acted upon. A monitoring system had been established by Crossrail at the beginning of the project but was not delivering reliable, consistent readings, especially in wet weather conditions.

Responsible for surveying and both automated and manual monitoring on this contract is Morgan Sindall chief land surveyor Nick Giles. In 2014, having already successfully implemented an innovative 3D laser scanning solution on Crossrail’s Bridge 53 – a project with restricted access that ruled out an optical solution – Nick was presented with a new challenge, replacing the existing optical monitoring system on the Network Rail and DLR stretches of track (which now fell under his mandate) with a system that would restore the confidence of all parties reliant on its data.

Raising the bar

Crossrail was clear in its requirements for a new monitoring system – it had to be robust, reliable and repeatable (the three Rs) if it was to provide total confidence for those depending on it. For Nick, that meant finding a new approach that not only rectified the issues of the old system but raised the bar even higher. Working with Morgan Sindall monitoring data manager Dave Gibbs, and monitoring surveyor Pawel Owsianka, Nick therefore assessed a number of possibilities before opting for a unique two-pronged approach that would provide a level of confidence that had been missing from the old method.

His solution was to have two systems working in tandem – an optical system for monitoring horizontal displacement comprising total stations and monitoring software, and a flat mesh bi-axial tilt sensor system for monitoring cant and twist consisting of several hundred Senceive high precision wireless tilt meters attached directly to the track. This approach would not only see the two systems providing constant backup checks for each other, but would also enable Morgan Sindall to reduce the number of vulnerable trackside optical instruments.

As part of his optical instrument research, Nick Giles contacted UK Trimble distributor Korec, which had supplied the Bridge 53 laser scanning solution for his previous Crossrail project. During these consultations, Chris Harris, Korec’s geospatial and deformation monitoring specialist, introduced Nick to Trimble’s 4D Control monitoring software, which provides support for the company’s most advanced total station platform, the S8.

GWS8withOlympicstad [online]

Following the evaluation of several manufacturer’s optical systems, Nick selected the Korec – supplied solution of ten S8 Trimble Vision robotic total stations, all managed in real time using 4D Control monitoring software.

The S8s provided Nick with the established technology and reliability that he sought along with sub-mm accuracy and the extra benefits of Trimble’s Magdrive technology, designed to reduce friction and ultimately wear and tear, and a Vision on-board camera for remotely observing anything that might compromise the instrument’s performance such as an obstructed view to a prism.

Ten S8 total stations were subsequently positioned at regular intervals along each section of the Network Rail and DLR track and prisms were fixed to the rails every three metres. This allowed each total station a line-of-sight to up to 60 of the evenly spaced rail mounted prisms.

Flexibility and analysis

For Nick, the real strengths of selecting a Trimble system lay with the 4D Control monitoring software, which offered his team a high level of customisation and flexibility along with remote management of all measurement cycles and communications.

The system delivers twenty-four hour coverage with a pre-programmed hourly cycle that first sees the S8s take readings from up to four reference targets for each setup before moving on to the rail-based prisms. This data is then collected by the 4D Control software, which computes and records the results.

This 4D Control provides the rigorous analysis of this data that Nick Giles and Pawel Owsianka require. The results arrive quickly and easily and, because the raw information is stored in an SQL database, it is easy for Pawel to extract any data he needs to create visual results such as the maps, charts and graphs needed for meetings and client reports.

For Pawel, who looks after data analysis and remote access to the instruments, the customisable nature of the software has been invaluable, allowing him to create the specific software routines he requires for both analysis of the data and report generation.

A drawback to the previous system had been its sounding of multiple alarms which alerted a large number of stakeholders, but without the ‘filter’ of the expert knowledge required to interpret them. This had caused frequent delays to works with action being taken when none was necessary. With 4D Control, Pawel can customise the alarm triggers to provide specific information including tolerances for displacement at any point with pre-programmed trips at 8mm, 15mm and 20mm. This allows him to observe trends rather than ad hoc measurements. Other sets of alarms alert him to factors such as instrument maintenance, damage to an instrument or prism or if the line of sight to a prism has been obstructed.

A major advantage to the system is that Pawel can use it to manage who receives the alarms, allowing the Morgan Sindall monitoring team to establish a new level of security. If an alarm is triggered, an email alert is sent to just three selected members of the Morgan Sindall monitoring team rather than multiple shareholders as the old system had done. One of these three team members can then immediately log onto the system, even from home, and analyse the data before deciding if action is necessary and further parties need to be alerted.

Typically, an initial alarm is triggered if a prism records a movement of 8mm. This information is compared to the findings from the Senceive tilt sensor system and the prism is then ‘watched’ over the next three monitoring cycles, a period of 3 hours, to detect any changes.

LHchrisnnick [online]

Nick reported that a perfect example of the system working exactly as required occurred recently. An alarm had triggered at 8mm, alerting the three selected members of the Morgan Sindall team who then closely monitored the affected prism through its subsequent cycles. No further movement was detected over the next three months. Network Rail was aware of the 8mm alarm from the outset through the regular update meetings but, because no action was necessary, there was no distraction to other parties because of Morgan Sindall’s filtering process. Consequently, when a second alarm was triggered at 15mm, the monitoring team immediately alerted Network Rail, and all stakeholders were informed with full confidence that the alarm was genuine. The track was realigned in less than 12 hours.

Turning data into information

Morgan Sindall produces a daily monitoring report for Crossrail. This textual report details any recorded movement, with a graph if an alarm has been triggered, and is a part of the shift review group made up of Crossrail, DLR and Network Rail which meets every morning. A report generated by the Trimble 4D Control software is also used at a weekly review panel meeting. Additionally, all the data, in Crossrail’s preferred format, is uploaded onto UCIMS, the underground construction information management system developed to monitor construction data for Crossrail.

Nick was quick to stress that the customised nature of the reports that Pawel has been able to generate with Trimble 4D Control has enabled Morgan Sindall to quickly and efficiently analyse and observe trends and present its findings in the preferred formats of its stakeholders. Pawel agreed and emphasised that the flexibility of this software is key to the smooth running of the optical system. He can set up infinite formulae to provide customised analysis which

is especially useful for examining trends. For example, if settlement on a prism is detected, he can immediately set up a graph that will enable him to compare its behaviour with the five other prisms in closest proximity to provide a wider picture. For Pawel, the software’s flexibility means that it is a work in progress and, as the project progresses, so does the sophistication of the information he can provide.

With a project target end date of 2016, Nick reported that the system is going from strength to strength as Pawel continues to develop and improve the routines on the Trimble 4D Control software. Nick concluded: “Managing the monitoring on this project in-house has brought us innumerable benefits, not least satisfied clients and stakeholders.

“Thanks to the dedication and enthusiasm of the monitoring team, combined with the reliability of the Trimble hardware and software, we have been able to restore the confidence of those reliant on the information we supply. This has allowed Network Rail and DLR to avoid any unnecessary possessions and also means that, should a significant movement in the track occur, there is no ambiguity and consequently, in the case of a genuine alert, trains can be stopped immediately.

“Both Network Rail and DLR have reported back that the system has restored their confidence in the monitoring data presented and met their 3R requirements for a robust, reliable and repeatable system. KOREC has been a good partner, providing both consultation and support, and the end result is a system that enables fast and informed decision making, which benefits all involved.”

Healing wounds

Before the advent of Xboxes and all-singing smartphones, kids signed up to a vivid, multi-sensory game accessed through a portal at the far end of the kitchen, known as ‘outdoors’. In the black and white era – albeit slightly rose- tinted – this was unfettered by health and safety, the dress code comprising short trousers, grazed knees, cheeky grins and cockeyed fringes. The social backdrop was industrial, as was parenting. Woe-betide any child who got under mother’s feet. So, after breakfast, they were swept into the real world to learn about life through the unique experiences it flung at them. That culture shaped today’s generation of retirees and those, like me, who still remember coalmines.

Also amongst the latter is Stephen Mackey who grew up at the head of the Rhondda Fawr valley, blessed with an adventure playground on his doorstep. But there was one particular place that drew him back time after time. A short walk from home was a railway tunnel, two miles in length, through which there was no traffic on a Sunday. So he’d take a candle, put it in a tin, and venture forth into the darkness. Near its midpoint, the tunnel abruptly widened for a few yards, a spot he knew as ‘the church’. Here he would sit for hours, reflecting on the courage and resolve of those who had pushed this passageway through the hill 80 years earlier. For reasons he never fully understood, he felt at one with them.

Confrontation with officialdom was an ever-present threat, but this diminished in 1968 when passenger traffic ceased, disenfranchising communities in this remote corner of South Wales. With the help of two mates and a 40-foot rope, Stephen repainted the commemorative cover stone cemented into the east portal’s headwall, appending his name and the request “please open me”. Then, in 1980, with locals persistently breaching the tunnel’s protective blockwalls, the county council arrived to infill the approach cuttings, bulldozers burying their liability beneath tonnes of earth. Stephen watched on with a lump in his throat as part of his childhood vanished. As he headed home, he looked back and shouted: “I’ll open you one day” – the sort of thing you do as an impassioned youth before the burdens of being a grown-up come to bear.

]
Photo: Ben Salter/ David Vousden.

The decades that followed brought industrial decimation to the once-thriving upper Rhondda. Though the physical scars have now healed – revealing a spectacular landscape – economic deprivation still blights the area. Stephen felt this personally a couple of years ago when he was made redundant. With such events comes the need to refocus, a process that often benefits from a good walk. And so, on a late summer afternoon, he found himself in Llwynpia, a couple of miles from home, wondering what to do next. The answer came to him as he passed some blackberry bushes, his attention being drawn to something in the undergrowth. It was a moment of bizarre happenstance. Pulling back the branches, revealed to him was the cover stone he had painstakingly repainted 40 years earlier. Life since has been unrecognisable.

Go west

Through the 1870s, increasing coal production in the Rhondda severely tested the handling capabilities of its monopoly carriers, the Taff Vale Railway and Cardiff Docks. Return journeys typically took two days. This background of crippling congestion spurred the merchant folk of Swansea – where new coal shipping facilities had opened – to develop proposals for the Rhondda & Swansea Bay Railway (R&SBR). Incorporated on 10 August 1882, it established a shorter export route via the Afan valley but, to reach it, the line would first have to overcome a 1,700 feet high natural barrier, Mynydd Blaengwyfni. Set that task was engineer Sydney William Yockney; his father, Samuel Hansard Yockney, had acted as engineer and manager for the contractor at Box Tunnel, bringing him to the attention of Brunel for whom he went on to fulfil a number of other tunnel projects.

Work on the R&SBR was split into three contracts, No.3 being awarded to William Jones of Neath. Included within it was the construction of Rhondda Tunnel, the second longest in Wales at 3,443 yards, for which the resident engineer was William Sutcliffe Marsh.

Ground was first broken on 30 May 1885, completion being due within three years. However, delays in securing land at the eastern end prevented any substantive progress there for another 15 months. Yockney’s reports to the company directors were initially positive, with good ground conditions encountered and little water ingress. The headings were being driven through sandstone at a rate reaching 240 yards per month, the miners working from shafts in the approach cuttings at either end and another just in from the western entrance.

With ground cover exceeding 900 feet, the conventional approach to expediting progress in lengthy tunnels – the sinking of intermediate shafts – was deemed impractical. However, the miners did benefit from rock drilling machines, operated by compressed air which was generated by a pair of horizontal engines and stored in an iron tank before being passed into the tunnel. The machines’ exhaust acted as effective ventilation at the working face.

Duck or grouse

From the hydraulically-powered comfort of the twenty- first century, not one of us can realistically imagine what life was like for the workforce. However, a visiting newspaper reporter did his best to paint a picture. “Taking our places on some temporary seats, the horses started at a brisk walk along the tram-line, and soon we were entering the tunnel. Generally the tunnel was narrow and one had to exercise care in passing one’s arms within the strict limits of the little track, or the jagged points which stuck out here and there would give one a sharp and unpleasant reminder, while an occasional cry of “heads” from our guide warned us of the necessity of sometimes disposing this part of the body somewhat suddenly between our knees. At more than one place however we saw signs of operations already on foot for the purpose of ‘opening out’. We were informed however there is no immediate necessity for this, the great object being to bore the tunnel, and in a very short time a hundred or so gangs of men can quickly enlarge it to the required size for the passage of trains.”

“The side and the roof generally presented a most substantial appearance, the roof particularly being for quite half the distance a level mass of rock. As one passed along, a hissing sound indicated the passing of the air which kept the tunnel even three-quarters of a mile in quite nice and cool. At last the waggons came to a sudden stop and a short walk over the boots in mud took us to a solid wall of rock, which effectually blocked our progress. Not so that of the excavators. Against this solid wall were six men hammering with pickaxe and crowbar, as though their lives depended on it, and though their progress will be slow, they will eventually clear a passage through which it is hoped that millions of passengers and countless tons of coal will pass from the Rhondda to the port at the mouth of the Tawe.”

Tick tock

Despite the miners’ industry, alarm bells started ringing early in 1887 when progress started to slip; according to William Jones, this was the function of a manpower shortage and the underground springs encountered at the east end of the tunnel. Reluctantly, the company pushed back the contractual completion date to 31 July 1889. It wasn’t until 16 March that year, with only 20 weeks to go, that the headings finally met, Yockney recording that the levels were out by just half-an-inch whilst the line was perfect. In celebration, the contractor entertained a hundred navvies to supper, song and recitals at a nearby hotel.

InspectionParty
Photo: Stephen Mackey.

This constructional high-point acted as a counterbalance to the lows that inevitably attended. John Harris, 24, killed by an explosion; William Shod, a haulier, run over by a wagon and fatally injured; Isaac Watson, 36, succumbed to dynamite. And then, on 22 January 1889, news of a huge rock fall spread across the district; seven deaths were reported. Although an exaggeration, the reality – two victims – proved no consolation to the families of George Lever, a 28-year-old miner, and labourer George Smitherham, known to everyone as “Soldier”. Gangs of men laboured for many hours to extricate their bodies from the debris.

With the rate of advance falling to 70-odd yards per month, the company dispensed with William Jones’ services in September 1889, bringing in Messrs Lucas & Aird from Westminster. Employing 1,600 men to finish the line, they set about erecting 300 houses at the Rhondda end and, for four months, workers in the tunnel benefited from new-fangled electric lamps. The venture was back on track.

When Colonel Rich fulfilled his inspection duties for the Board of Trade on 2 May 1890, Yockney was confident of a tick in the box. He had, though, not accounted for Rich’s expectation that the tunnel be fully lined. So, before he would pass it as fit for passenger traffic, 759 yards of brick arch would have to be inserted, springing off arched- concrete sidewalls. Operations resumed the following day, Lucas & Aird having already prepared for such an eventuality; completion came just 54 days later, allowing the tunnel to start earning its keep on 2 July 1890.

Shape of things to come

Wise practice in mining areas was for railway companies to buy any pillars of coal that supported significant structures. Failure of the Lancashire, Derbyshire & East Coast Railway to do so resulted in Bolsover Tunnel sinking by eight feet in 60 years. The R&SBR fell into the same trap of short-term economics, the upshot being areas of worsening distortion resulting from seams being worked both above and below Rhondda Tunnel.

Between 1938 and 1953, around 500 steel ribs were installed in an attempt to resist inward movement of the sidewalls and consequential pushing-up of the crown, mostly through two sections towards the eastern end. Several lengths of arch were relined as loose brickwork fell onto the track and speed restrictions were imposed; a settlement of 15 inches was recorded in just 12 years. All this was exacerbated by considerable water penetration of the lining which extensively washed out the mortar.

Severe distortion was observed near the middle of the tunnel in 1967, close to a geological fault. So rapid was its deterioration that the engineer closed the tunnel on safety grounds on 26 February 1968. This was supposedly a temporary measure whilst a decision was made on the future of the line. After much prevarication, the Ministry of Transport cited a decline in usage and the provision of a bus service as justification for the formal withdrawal of passenger services in December 1970. A cynic might suggest that the tunnel’s estimated repair cost of £90,000 also had an influence.

Turning the clocks back

It’s not clear yet whether Stephen Mackey can help to unravel the actions of distant decision- makers 46 years ago. Having unearthed the cover stone, he placed an advert on Facebook and in the local paper, asking for help in moving it to a local stonemason for restoration. And so, on 9 September 2014, 19 like-minds assembled at the RAFA Club in Treorchy to hatch a plan. Two days later, the stone was rescued, and it now sits resplendent on the platform end of Treherbert Station.

RT-Ribs
Photo: Historical Railway Estate.

But one of those 19 had much bigger ideas…to reopen the tunnel as a walking and cycling route. The initial response of those around the table was one of predictable scepticism; the reality – 18 months later – is that Stephen is now chairman of the Rhondda Tunnel Society, a charitable body with more than 3,100 worldwide members.

The Welsh Government is engaged, starting negotiations for the tunnel to be transferred into its ownership and commissioning Sustrans to carry out a scoping study on how a reopening might be achieved. Not surprisingly, its conclusion that the economy could benefit by as much as £14.4 million over 30 years has uplifted the campaigners.

Custodian currently is the Historical Railways Estate, part of Highways England. Last April, its engineer, contractor Hammond ECS and a mines rescue team made the first official incursion into the tunnel for 40 years via a cramped access shaft and drain. The resulting report concludes that “the masonry forming the tunnel does not appear to have become any worse since it was closed to rail traffic” and that it is “not in a condition that would prevent future similar examinations.”

The vision now is ambitious, a catalyst for the rebirth of the Rhondda and Afan valleys: museum, bike hire, bed and breakfast, a restaurant in the form of a Pullman car, golf buggies offering guided tours – the list goes on. More immediate is the hope that the eastern portal will be excavated so machinery can be brought in to undertake a full survey, and of course prove to any doubters that the thing actually exists.

Who knows? As Stephen is keen to point out, this would be the longest cycling tunnel in the world for half the year when the 3,963-yard Snoqualmie Tunnel in America closes for bad weather. He’s become very skilled at public relations! But even as officially the second longest, a consensus is emerging around the tourism and connectivity potential a reopened Rhondda Tunnel could offer. “It’s a full time job I’ve got now,” says Stephen breathlessly. It’s unfortunate that he’s not getting paid for it, but you can tell he’s enjoying the ride.

Lead photo: Stephen Mackey.

Monitoring train fleets

If you own a wind farm in the sea, you really want to know how well each turbine is performing. Clearly, if one turbine is producing less electricity than the norm, you can see this, but it’s not good enough. You also need to know why, so you can fix it. Moreover it’s also pretty important to know precisely why, as it’s a difficult journey just to get to the turbine let alone climbing up and down the mast – you wouldn’t want to find you’ve brought the wrong parts or tools!

What has this got to do with train maintenance, you might ask? It was just one of the examples of successful remote condition monitoring mentioned during a two day conference in December 2015.

Over 160 people gathered in London for the fourth Annual Fleet Maintenance Congress organised by London Business Conferences. The snappy subtitle for the congress was “Reducing Cost Through Integrating CBM and Data Analytics”.

Whilst the language may be challenging, the numbers attending suggested that there was a great deal of interest in this topic. Moreover, the title might sound as though it was for computer experts and statisticians but, in fact, it was for and delivered by real train maintenance managers grappling to deliver more for less in a competitive environment, whilst getting to grips with the latest tools to do so, just as has been happening over the history of railways.

Advance warning

It is worth a small aside to mention some of the principles that underpin this article. The basis of remote condition monitoring is that you gain knowledge of the performance of a piece of equipment by monitoring its performance. This might include fitting sensors to items of equipment or using measurements already made within the equipment. The sensors might be on the train or they might be trackside.

As an example, door systems often monitor door speeds so that any reduction in speed (increasing friction in the system, say) can be corrected by increasing the power of the motor. Changes over time in the current drawn by the motor will therefore indicate deterioration in the mechanical guides or some other fault. Data about the current consumed is sent back to base over a wireless communications link (perhaps 3G/4G) into a shore-based database which can be accessed by the maintainer. This is Remote Condition Monitoring (RCM).

Condition-Based Maintenance (CBM) is the process of turning RCM data into information. With CBM, analysis is often carried out by experts in both train maintenance and data processing and, sometimes, by combining data from a number of sources. In the simple doors example for basic RCM, if the motor current goes consistently above a defined threshold, the maintenance planner can call the train into the workshop for attention. Generally, this will be far less frequently than routinely checking the door system.

For the data analyst, the door currents of all the doors over days, weeks, months or years can be analysed which might deliver insights into door system, operator and customer behaviour. This is a very simplistic illustration, but it shows the basic principle.

Conference basics

The conference included a good-sized exhibition space occupied by providers of RCM and CBM tools and solutions. The conference itself was a mixture of railway managers describing the challenges they face that are leading them into RCM/CBM, some case studies, both successful and others that were more challenging, and finally some presentations from companies selling RCM/ CBM technology and expertise.

The scene was set really well by Tom Hopkins, Heathrow Express head of engineering, who reminded us of the basics:

  1. Introducing RCM and CBM is not just introducing new technology. Most technology programmes are really, at their heart, business change programmes and Tom emphasised that unless people, process and technology receive equal weight supportedby excellent leadership, there is a good chance the project will, at best, not deliver the expected benefits and, at worst, fail.
  2. Today’s new trains should come with systems that capture train and sub-system status and parameters with software to capture and analyse this information.
  3. On older fleets, monitoring systems can be retrofitted “at a price”. Some owners or operators have capitalised on projects such as accessing OTMR (On Train Monitoring Recorder) information, taking advantage of the opportunity provided by fitting customer Wi-Fi. Others have chosen to fit sensors to monitor unreliable equipment.
  4. The biggest challenge for all the systems, whether new or old, is analysing the mass of data that is produced and deciding the trigger levels. This cannot just be decided by the CBM vendor alone; it needs input from sub system designers, maintainers and operators using analysis techniques such as Reliability Centred Maintenance.
  5. Finally, the RCM and CBM systems should be at least linked to the asset management system.

Extra benefits

This theme of retrofitting sensors was picked up by Justin Southcombe of Perpetuum (UK) and by Ross Balcombe of South Eastern Trains (SET). Perpetuum makes self-powered wireless vibration sensors (the product of research by Southampton University) and SET has used these devices to monitor axle bearings on its fleet. The train operator wanted to be able confidently to extend the interval between wheelset overhauls, and the vibration sensors were able to provide early warning of any issues with the wheel bearings.

London_Underground_1992_Stock_at_Theydon_Bois_by_tompagenet [online]

Justin said that they had carried out a limited trial to validate the principle before rolling it out across 1000s of wheels. The analysis of the vibration sensors is able to identify the ‘signature’ of early wear of bearings. A great deal of ‘noise’ had to be filtered out of the signals in order to deliver the information SET required, and it was soon realised that this ‘noise’, which was actually vibration signals from wheels and rails, could be valuable. By filtering in different ways, wheel and track defects could be monitored too. As a result, wheel and rail defects are being advised both to South Eastern Trains and to Network Rail.

While track information had not been the initial objective there was no possibility of understating its significance now, and examples of how careful analysis of data can yield far more than expected were highlighted throughout the conference.

RCM meets Oyster

Gaining unexpected information was evident in the presentation by Steve Foot and Chris Welford of London Underground. They are working on LU’s “Predict and Prevent” programme which aims to produce more and more availability and reduced failure rates at a time of increased ridership – indeed the latest record of 4.8 million customers in a day was announced during the conference.

They acknowledged that LU’s newest trains have very sophisticated RCM systems, a comment echoed by many speakers about modern trains in general. However, they chose to highlight a case study of the Central line trains which were fitted with an early Train Control and Monitoring System from new in 1992/3. This system always had the ability to download data from the train to shore, but LU’s more recent work had seen installation of Wi-Fi to allow the data to be extracted more frequently, and the use of data scientists working with the engineers to bring additional insights into the data.

LU was fortunate to be able to access some of the Transport for London Oyster card data scientists who have experience in finding patterns in seemingly random Oyster use and they helped Steve’s team develop their own job specification for the Predict and Prevent team’s own data scientists. Steve’s team delivered a computer tool for maintainers to interrogate the system and had brought about a number of benefits including an increase in the number of orders for work, resulting in an improvement in reliability. However one particular success was the enthusiasm with which the new system was received by the staff.

Increased capacity through RCM

Relationships, reducing failures of the whole railway system and coping with increasing ridership were themes of Neil O’Connor’s presentation. Neil is fleet depot manager for South West Trains. The introduction to his presentation was illustrated by a seething mass of people waiting for trains under the famous clock at Waterloo Station.

Ridership on SWT has increased significantly over the years. Waterloo alone has seen passenger arrivals and departures increase by 50% in the last 15 years and it is forecast to increase by another 30% over the next 15. The solution is more trains, but Neil only had a certain sized depot to fit them into. His solution was to reduce the number of interventions on the older trains by, inter alia, fitting new traction equipment and using various RCM techniques to improve the maintainers’ knowledge of the fleets.

Understanding the data

In his opening remarks, Tom Hopkins stressed the importance of setting the right trigger levels in the analytics. This was reinforced by a comment from Steve Foote who mentioned that point machines all seem to have different current-time signatures even where the machine and the points are of the same type and configuration.

Perpetuum and SET had adopted one technique for learning about how to use data – by using their pilot installation. Tsuyoshi Ichigi from the Technology R&D Centre of Japan Railways East Group described the approach JR East had taken to understand how to turn the data on the performance of doors and the heating/air conditioning (HVAC) system of the prototype E235 train into information.

Examples of the doors and HVAC had been set up so that engineers and researchers could validate their understanding of the data coming off the train. For example, they were able to apply controlled amounts of contamination to HVAC filters in the laboratory in order to understand both the impact on performance and how this is relayed by the monitoring system. The laboratory work was carried out for a much larger range of abnormal conditions than would be practicable to perform on the prototype train. This presentation introduced the use of Principal Component Analysis, which is a technique used to emphasise variation and bring out strong patterns in a dataset. It is often used to make data easy to explore and visualise – and is far too complex to explain here.

European perspective

Later on, Bas Sprangers and Jan Luijben of the Amsterdam Public Transport operator GVB presented on the challenges for introducing CBM on a fleet that has been supplied by different suppliers, all of whom have provided different systems and some of which do not send all the appropriate data, such as mileage. Like others, they recognised the value of analytics and CBM; for them it will help them improve availability to help meet ever-increasing demand. They described a particular challenge they have related to EU procurement rules for public bodies, which makes it difficult to take the knowledge gained from a small-scale contract (perhaps a small supplier’s intellectual property), and apply that knowledge to a bigger contract which might need to be opened to competition.

Whilst talking about EU regulations, the issue of approval of changes to maintenance regimes was discussed. All operators will understand the importance of safety in all railway operations. In the EU at least, any change in the maintenance regime has to be justified and certified and it is no good saying that this or that maintenance interval can be extended just because “the computer says it is OK”.

Although the RCM and CBM computer tools bring much greater clarity and certainty to maintenance decisions, it is still maintenance engineers who have to justify what is or is not in the fleet maintenance regime and this has to go into a well-argued case with evidence for certification and safety regulators to consider.

Belgium Railways (SNCB), Italian Railways (Trenitalia), French Railways (SNCF) and Finnish Railways (VR) all presented their experience both of retrofitting existing trains and of learning to manage with the vast quantity of data that new trains deliver. Two particularly noteworthy points were made by VR and Trenitalia.

Firstly, from VR and to illustrate the diverse data sources there is the short hand, “the three Vs of data”:

» Variety – forms, structure, sources;

» Volume – How much of it in kilobytes, megabytes, gigabytes, terabytes;

» Velocity – streamed or occasional and does it all arrive in the right order.

Secondly, Trenitalia had specified a performance requirement for the RCM systems on its newest train fleet that:

» >80% of all maintenance work orders should come from the RCM system;

» <5% of these notifications should be “no fault found”;

» <5% repeat repairs.

JRE_SeriesE235

ROSCO benefits

A slightly different perspective was presented by Olivier André of Porterbrook Leasing with the aim of showing how it can be to a leasing company’s commercial advantage to provide some or all of the technology to enable RCM and possibly to sell the service of providing the data or information from these systems to lessees (or others?). He highlighted that C4 Underframe and C6 (carbody) overhauls present the opportunity to add facilities such as an Ethernet backbone for IP connectivity, CCTV, Wi-Fi (passengers and RCM data) sensors, and track to train wireless links.

Olivier suggested the benefits would be:

To the train operating company (TOC):

  • Possible standard architecture/open system;
  • Future proofing an older train;
  • Freedom to choose his own back office (not being tied to train supplier’s solution).

To the leasing company:

  • Protecting the value of the asset;
  • Differentiation of Porterbrook as a lessor;
  • Ability to cross reference across fleets operating on different TOCs;
  • Possibly to reduce/eliminate heavy maintenance and add tasks to routine maintenance.

After two long days

At the end of a full two-day programme, delegates had a much better appreciation of the benefits, and pitfalls, of RCM and CBM. Probably the most discussions revolved around:

» New trains will generally come with RCM, but work is still necessary to determine the CBM requirements for the particular railway’s environment. There was criticism of some suppliers (no names quoted) who seek to monetise the data these systems produce and the lack of open data structures. There were no presentations from rolling stock suppliers and perhaps these issues might be addressed next time.

» CBM is in its infancy on rolling stock compared with RCM, which is seen as a mature technology. Some of the presenters reported on their struggle to make a business case for retrofitting RCM because they need the benefits of CBM to justify RCM and CBM benefits are, often, educated guesswork. Maturity of CBM will only come as operators and suppliers pool data and are able to review others’ results.

» Many asset managers see the opportunity, but don’t have the skills in-house to carry out the development work on CBM for their network. There are outside companies that have these skills, but, for the public sector at least, the challenges of contracting in a scalable form for these services are real.

Like all good conferences, despite the amount of information received, there were still questions unanswered. No doubt these will be taken up next year.

Written by Malcolm Dobell, former head of train systems engineering at London Underground.