Video: Glasgow Queen Street

For 20 weeks, it’s been all change at Glasgow Queen Street as a considerable package of work is pushed forward as part of the ongoing Edinburgh Glasgow Improvement Programme (EGIP). Involved are platform extensions to handle new eight-car trains, track layout changes in the station throat and, through the thousand-yard long approach tunnel, renewal of its degraded 40-year-old slab-track.

Even after breaking out around 10,000 tonnes of concrete to a depth of 600mm, another 250mm of sandstone and mudrocks still had to be excavated to create sufficient headroom for the conductor bar that will carry the traction current. The new slab-track – an Austrian system – has a design life of 60 years.

In the station throat, new drainage and multiduct was installed before work got underway on a new layout to align with the extended platforms, incorporating seven S&C units; four more are located in the tunnel. The signalling infrastructure is also being renewed, with axle counters replacing track circuits.

All in all, it’s expected that an average daily workforce of around 70 will have worked a total of half-a-million man hours by the time Queen Street High Level welcomes commuters again on 7th August. A two-year redevelopment of the station buildings is on course to begin in November.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Must Read

HS2 tunnel segment factory building complete

Structural work on the temporary pre-cast factory that will produce tunnel wall segments for HS2’s 10-mile-long Chiltern tunnels, has been completed at...

Network Rail acquires Brunel’s ‘Bristol Old Station’

Network Rail has acquired ‘Bristol Old Station’, the iconic Grade I listed building, designed by Isambard Kingdom Brunel, that was Bristol’s first...

Work on reconnecting the line to Levenmouth gets underway

The first phase of work which will lead to the reinstatement of passenger services to Leven will begin shortly.

Narborough station footbridge to be removed, repaired, repainted and replaced

An £800,000 project to strengthen, refurbish and brighten up the footbridge at Narborough station in Leicestershire will take three months to complete.

Weekend work to improves Clacton on Sea line in Essex

The railway line to Clacton on Sea in Essex is to be upgraded over weekends until the end of October 2020.