Home Rail News Stairway to Ealing Broadway

Stairway to Ealing Broadway

The Christmas shutdown gives Network Rail, and London Underground for that matter, a chance to undertake those jobs that would be difficult at other times of the year. Some are major pieces of work, others are routine but take a long time (such as the wholesale replacement of track drainage at Weedon, Northamptonshire).

The justification for these works is usually fairly obvious. Failing infrastructure, operational bottlenecks, capacity improvements, and even new railway construction.

Sometimes, however, the need for a project to take place can be a little obscure. Take, for example, the Crossrail preparatory works carried out by Network Rail at Christmas to install a new emergency escape footbridge at Ealing Broadway station. The project had an interesting ‘raison d’être’ since there is already adequate access to the platforms for the existing trains. However, the new bridge is required because of the enormous capacity of the intended new Crossrail trains. It was decided that the current station infrastructure would unacceptably restrict emergency evacuation of passengers, and that this should be resolved by an additional footbridge at the other end of the platforms.

This sounds simple enough until one considers the surrounding environment at the site. Residential properties are very close to the line, making it difficult to find adequate site access and ensuring that noise and vibration would be significant issues. Ground conditions meant that piled foundations would be necessary, and the only feasible way to place the footbridge structure would be by employing a large crane.

Preparation is key

Taylor Woodrow, part of the Vinci organisation, was employed by the project to carry out the works. The project team held detailed meetings with local residents about the impact of the works, agreeing, for example, to restrict piling activity to daytime hours over the Christmas period. The possibility of obtaining access to the new bridge site via an adjacent NHS facility was identified, and negotiations were entered into with a view to gaining agreement both to temporary access for the crane and construction works and to permanent access to the completed footbridge. Thanks are due to the NHS for their cooperation in this regard.

Christmas 2015 was planned as the date to erect the footbridge span serving Platforms 2 and 3 with a second span to Platform 1 to follow at a later date. Sarens was engaged to carry out the contract lifting operations over the Christmas period.

The piled foundations for the first span were installed beforehand so that, at Christmas, effort could be focussed on the lifting operations. A four-day hire of a 400 tonne mobile crane commenced at 05:00 on Christmas morning and nine main lifts were completed by 11:30 the same day. These lifts involved the placement of support columns, stair units and the bridge span itself. Extremely high winds had been forecast for the day, and the team were relieved that all these main lifts were successfully completed before the winds arrived.

Just down the line at Stockley, the works there were less fortunate. Only 10 miles or so further west, that site was hit earlier by the winds and some of the lifts there had to be postponed. At Ealing Broadway the only crane lifts delayed by the winds were secondary lifts of materials and plant, and these delays had no significant effect upon the programme.

Additional works at the site included some piling to the rail embankment adjacent to the new footbridge. This provided embankment support where it was necessary to trim the bank to construct the access route from the new bridge onto the NHS site and thence to the public road. The large crane was used to assist this work during the remainder of its contracted four-day stay on site.

The plan now is to install the piled foundations and pile caps on Platform 1 ready for the stairs to be installed there and for the installation of the second bridge span over to that platform. The aspiration is to undertake all of these works before Easter, using normal weeknight possessions rather than blocking the line over the Easter holiday.

Chris Parker
Chris Parkerhttp://www.railengineer.co.uk

SPECIALIST AREAS
Conventional and slab-track, permanent way, earthworks and embankments, road-rail plant


Chris Parker has worked in the rail industry since 1972, beginning with British Rail in the civil engineering department in Birmingham and ending his full-time employment at Network Rail HQ in London in 2004. In between, he worked in various locations including Nottingham, Swindon, Derby and York.

His BR experience covered track and structures, design and maintenance, followed by a move into infrastructure management. During the rail privatisation process he was a project manager setting up the Midlands Zone of Railtrack, becoming Zone Civil Engineer before moving into Railtrack HQ in London.

Under Network Rail, he became Track Maintenance Engineer, representing his company and the UK at the UIC and CEN, dealing with international standards for track and interoperability, making full use of his spoken French skills.

Chris is active in the ICE and PWI. He started writing for Rail Engineer in 2006, and also writes for the PWI Journal and other organisations.

7 COMMENTS

  1. A new stairway footbridge has been installed at Ealing Broadway as it will connect the National Rail (Crossrail) platforms to the London Underground Central Line and District Line platforms. It should be easier to transfer from tube to Crossrail without having to take the long detour to get from the Underground to Crossrail and GWR platforms.

    • There was never a long detour, the reason for installing the footbridge is because of the sheer volume of people who will be flooding narrow platforms.

        • What are you talking about Andrew? It says very clearly that the bridge is intended to allow more rapid evacuation of the relief line platforms in an emergency. It has nothing to do with tranferring passengers.You can see clearly from the photo that it does not extend over to the Underground platforms, it simply bridges the GWML relief line tracks.

          And why exactly would anyone taking a train FROM Paddington be getting onto an underground train heading back towards London?

  2. Here’s an overhead view to make things clearer: https://www.google.co.uk/maps/place/Ealing+Broadway/@51.5149413,-0.3007145,185m/data=!3m1!1e3!4m2!3m1!1s0x4876120a0c96043f:0xc2281572fc5616ae!6m1!1e1

    I suspect the car park used was the one just to the south.

    Note at the top the 4 terminating underground platforms (Platforms 5&6, 7&8), and below, the 4 through platforms (platforms 4, 3&2, 1).

    The bridge AFAICS is connecting together through platforms (2 & 3, 1 by Easter), not underground platforms. I think the article missed out that the current span connects Mainline platform 4 to Mainline platforms 2&3 currently.

    This bridge isn’t going to help connectivity between the mainline and tube platforms, unless it is extended north to the tube platforms (which looks possible).

    • To the editors of RailEngineer – sometimes a labelled overhead map can make a massive improvement to some articles – please consider these when appropriate 🙂

Leave a Reply to Guest Cancel reply

Please enter your comment!
Please enter your name here

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Must Read

video

A future role for Bennerley Viaduct

A proposal to install a public access route across Bennerley Viaduct in the East Midlands is currently being considered by planning authorities.

“A little water never hurt anyone…”

Plantworx & Railworx a success despite the summer weather Every two years, the Construction Equipment Association organises a big...

Rail Electrification: Rebuilding Confidence

The Institution of Mechanical Engineers recently held the latest in a series of roughly biennial seminars highlighting railway electrification, with the emphasis being mainly...

Barnard’s Lock Underbridge

A Spongy and Successful Lift Barnard’s Lock is a rail underbridge structure spanning the river Kennet, located 3.7km west...

New main-line interlocking enters service

The Shepperton branch line in the south west of London and north Surrey, which is part of the Feltham signal box area, connects...